Page 115 - Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Contracting Officer, who shall reduce his decision to writing and mail or otherwise furnish a copy thereof to the Architect-Engineer.
Page 117 - If any such change causes an increase or decrease in the cost of, or the time required for the performance of any part of the work under this contract, whether changed or not changed by any such order, an equitable adjustment shall be made in the contract price or deliver}! schedule, or both, and the contract shall be modified in writing accordingly.
Page 107 - I hereby determine that: a. the above-described item(s) is (are) not mined, produced, or manufactured, or the articles, materials, or supplies from which it (they) is (are) manufactured, are not mined. produced, or manufactured (as the case may be) in the United States in sufficient and reasonably available commercial quantities and of a satisfactory quality; and b.
Page 64 - ... for technical or special property that he determines to require a substantial initial investment or an extended period of preparation for manufacture, and for which he determines that formal advertising would be likely to result in additional cost to the Government by reason of duplication of investment or would result in duplication of necessary preparation which would unduly delay the procurement of the property...
Page 118 - Title to all property furnished by the Government shall remain in the Government. Title to all property purchased by the Contractor, for the cost of which the Contractor is entitled to be reimbursed as a direct item of cost under this contract, shall pass to and vest in the Government upon delivery of such property by the vendor.
Page 117 - Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change : Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim asserted at any time prior to final Payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes.
Page 115 - The decision of the Secretary or his duly authorized representative for the determination of such appeals shall be final and conclusive unless determined by a court of competent jurisdiction to have been fraudulent, or capricious, or arbitrary, or so grossly erroneous as necessarily to Imply bad faith, or not supported by substantial evidence.
Page 94 - Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however. That the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim asserted at any time prior to final payment under this contract.
Page 62 - Technical or Specialized Supplies Requiring Substantial Initial Investment or Extended Period of Preparation for Manufacture.
Page 151 - Lessee for the purpose of securing business. For breach or violation of this warranty the Government shall have the right to annul this lease without liability or in its discretion to require the Lessee to pay.