" If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted by an act of the Contracting Officer in the administration of... "
The Code of Federal Regulations of the United States of America - Page 242
1977
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1977
...in FPR 1—1.1310—2(a) under the conditions set in the manner prescribed therein. §9—7.802—21 Suspension of work. SUSPENSION OF WORK (a) The contracting...unreasonable suspension or delay, and the contract medified in writing accordingly. However, no adjustment shall be made under this clause for any suspension...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1981
...appropriate for the convenience of the Government. Ib) If the performance of all or any part of the wort is. for an unreasonable period of time, suspended...within a reasonable time), an adjustment shall be mate for any increase in cost of performance of this contract (excluding profit) necessarily caused...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1981
...or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted by an act of the Contracting Officer in the administration...time), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit! necessarily caused by such unreasonable...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1969
...or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted by an act of the Contracting Officer in the administration...time), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by such unreasonable...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1971
...of the work is, for an unreasonable period of time, suspended, delayed, or interrupted by an act oí the Contracting Officer in the administration of this...time), an adjustment shall be made for any Increase in the cost of performance of this contract (excluding profit) necessarily caused by such unreasonable...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1967
...or any part of the work Is, for an unreasonable period of time, suspended, delayed, or interrupted by an act of the Contracting Officer In the administration...If no time Is specified within a reasonable time) , and adjustment shall be made for any Increase In the cost of performance of this contract (excluding...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1983
...all or any pan of the work is, for an unreasonable period of lime, suspended, delayed, or interrupted by an act of the Contracting Officer in the administration...contract (or if no time is specified, within a reasonable lime), an adjustment shall be made for any increase in the cod of performance of this contract (excluding...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1974
...all or any pan of the work is. for an unreasonable period of time, suspended, delayed, or interrupted by an act of the Contracting Officer in the administration...time specified in this contract (or if no time is speciñed, within a reasonable time), an adjustment shall be made for any increase in the cost of performance...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 2000
...of the owner in administration of this contract, or by his failure to act within the time specfied in this contract (or if no time is specified, within...time), an adjustment shall be made for any increase in the cost of performance of this contract (eieluding profit) necessarily caused by such unreasonable...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1982
...of the owner in administration of this contract, or by his failure to act within the time specfied in this contract (or if no time is specified, within...time), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by such unreasonable...