| United States. Court of Claims - Law reports, digests, etc - 1948 - 886 pages
...beginning of any such delay, or such longer period as may be allowed by the Contracting Officer, notify the Contracting Officer in writing of the causes of...judgment the findings of fact justify such an extension. The decision of the Contracting Officer thereon shall be final, subject only to appeal under Article... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1950 - 940 pages
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30 days,... | |
| United States. Court of Claims - Law reports, digests, etc - 1942 - 818 pages
...the beginning of any such delay notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...fact justify such an extension, and his findings of facts thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30... | |
| United States. Court of Claims - Law reports, digests, etc - 1947 - 806 pages
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...of fact justify such an extension, and his findings pi fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within... | |
| United States. Court of Claims - Law reports, digests, etc - 1946 - 920 pages
...liquidated damages because of unforeseeable causes of delay, including strikes, and it provides that the contracting officer "shall ascertain the facts...judgment the findings of fact justify such an extension." This, of course, makes it mandatory upon the contracting officer to make findings of fact upon an application... | |
| United States. General Accounting Office - Finance, Public - 1950 - 710 pages
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30 days,... | |
| Administrative law - 1939 - 1306 pages
...final settlement of the contract) notify the contracting officer In writing of the causes of delay, who shall ascertain the facts and the extent of the delay...Justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal within 30 days,... | |
| Administrative law - 1976 - 1202 pages
...acts of the public enemy, acts of the Government in either its sovereign or contractual capacity, acts of another Contractor in the performance of a contract...provided in the "Disputes" clause of this contract. 7-602.5 ARMED SERVICES PROCUREMENT REGULATION CONTRACT CLAUSES AND SOLICITATION PROVISIONS (e) If,... | |
| Administrative law - 1979 - 1304 pages
...acts of the public enemy, acts of the Government in either its sovereign or contractual capacity, acts of another contractor in the performance of a contract...parties subject only to appeal as provided in the clause of this contract entitled "Disputes." ' (e) If, after notice of termination of the Contractor's... | |
| Administrative law - 1964 - 1202 pages
...acts of the public enemy, acts of the Government in either its sovereign or contractual capacity, acts of another contractor in the performance of a contract...the parties, subject only to appeal as provided in Clause 6 of these General Provisions. (e) If, after notice of termination of the Contractor's right... | |
| |