Page images
PDF
EPUB

available its records used in the computation of the labor indices. After the receipt of such certificate by the Contracting Officer, the revised contract unit prices shall be computed in accordance with the provisions of this clause, and this contract shall be amended accordingly.

(g) In the event of any total or partial termination of any item of this contract for the convenience of the Government, the month in which notice of such termination is received by the Contractor, if prior to the month in which delivery is required by this contract, shall be considered the month in which delivery of such terminated or partially terminated item is required for the purpose of determining the current labor and materials indices under paragraphs (c) and (d) hereof: Provided, however, That as to the quantity of such item which is not terminated for convenience, the month in which delivery is required by this contract shall continue to apply for determining said indices. In the case of termination of any item for default on the part of the Contractor, any price revision shall be limited to the quantity of each item which has been delivered by the Contractor and accepted by the Government prior to receipt by the Contractor of notice of termination for default.

(h) As used in this clause the phrase "the month in which delivery of supplies is required to be made in accordance with the terms of this contract" shall mean any month in which under the terms of this contract a specific quantity of units of the supplies called for by this contract is required to be delivered: Provided, however, That in case the failure of the Contractor to make delivery of such quantity shall have arisen out of causes beyond the control and without the fault or negligence of the Contractor, within the meaning of paragraph (c) of the clause of this contract entitled "Default," the quantity not delivered shall be required to be delivered as promptly as possible after the cessation of the cause of such failure, and the delivery schedule set forth in this contract shall be amended accordingly.

(1) Failure to agree upon any determination to be made under this clause shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes."

Notes

(1) Bidder insert the same percentage figures for the corresponding blanks in paragraphs (b) and in (e) (1) and (ii). In paragraph (e) (iii), bidder insert the percentage representing the difference between the sum of the percentages inserted in paragraph (b) and 100 percent.

(2) Bidder identify the shop and plant in which the standard steel mill item identified in paragraph (d) will be finally fabricated or processed into the contract item.

(3) Bidder insert the month of bid opening, or the month in which the Contractor

submitted its proposal if this is a negotiated contract.

(4) Bidder insert the unit price and unit of measure of the standard steel mill item used by the Contractor in the manufacture of the contract item.

(5) Bidder identify the standard steel mill item used by the Contractor in the manufacture of the contract item.

(6) Bidder insert the date set for bid opening, or the date of the Contractor's quotation if this is a negotiated contract.

(7) Bidder insert the number of days which represents the Contractor's best estimate of the period of time required for processing the standard steel mill item in the shop identified in paragraph (c).

(8) In negotiated procurements of nonstandard steel items, when there is no established or published price to the public, or when it is not desirable to use such price, this paragraph may refer to another appropriate price basis, such as an established interplant price.

[25 F.R. 14182, Dec. 31, 1960]

§ 7.106-3 Escalation clause for standard supplies.

The following price escalation clause is authorized for use in negotiated fixedprice supply contracts for standard supplies for which established prices exist. The clause may be used only when the total contract price is over $5,000 and delivery is not to be completed within six months after the contract date. The percentage figure to be used in subparagraph (d) (3) of the clause shall not exceed 10 percent. If any standard trade discounts offered by the contractor against its list or catalog price are taken into account in negotiating the contract unit price, the Contracting Officer's file should contain a statement setting forth the list or catalog price and the discounts. The discounts referred to do not include prompt payment or cash discounts.

PRICE ESCALATION (MAY 1957)

(a) The Contractor warrants that the unit prices stated herein, excluding any part of the prices which reflects requirements for preservation, packaging, and packing beyond standard commercial practice, are not in excess of the Contractor's applicable established prices in effect on the contract date for like quantities of the supplies covered by this contract. The term "established price" as used in this clause is the net price after applying any applicable standard trade discounts offered by the Contractor from its list or catalog price.

(b) The Contractor shall promptly notify the Contracting Officer as to the amount and effective date of each decrease in any applicable established price, and each applicable contract unit price shall be decreased by

the same percentage that the applicable established price is decreased. Any such decrease in a unit price shall apply to those supplies delivered on and after the effective date of each applicable decrease in the Contractor's established price, and this contract shall be amended accordingly. The Contractor shall certify on each invoice submitted under the contract that each unit price stated therein reflects all decreases, if any, which the Contractor had made in the established price applicable thereto, since the contract date; or shall certify on the final invoice that all such decreases have been applied to supplies delivered on and after the effective date of each such decrease in the Contractor's established prices.

(c) The Contractor may from time to time after the date of this contract and during the performance hereof, by written notice to the Contracting Officer, request an upward adjustment in any of the contract unit prices to be effective as of a date to be specified by the Contractor. Such request shall be acted upon in accordance with the following provisions of this clause.

(d) An upward adjustment in a contract unit price may be made under this clause only in accordance with the following conditions:

(1) Such an upward adjustment shall be made only if the Contractor's applicable established price has increased subsequent to the contract date.

(2) No unit price shall be increased by a percentage greater than the percentage increase in the Contractor's applicable established price.

(3) The aggregate of the increases in any unit price made under this clause shall not exceed percent of the original applicable contract unit price.

-----

(4) No adjusted unit price shall be effective earlier than the effective date of the increase in the applicable established price, or the date of receipt by the Contracting Officer of the Contractor's request for adjustment, whichever is the later.

(5) No upward adjustment in unit prices hereunder shall apply to supplies which were required by the contract delivery schedule to be delivered prior to the effective date of the related increase in the applicable established price, unless the Contractor's failure to deliver supplies in accordance with the delivery schedule results from causes beyond the control and without the fault or negligence of the Contractor, within the meaning of paragraph (c) of the clause of this contract entitled "Default," in which case the contract shall be amended to make an equitable extension of the delivery schedule.

(e) In the event the requested upward adjustment in any contract unit price is acceptable to the Contracting Officer, he shall so notify the Contractor, and the contract shall be amended accordingly. In the event the requested upward adjustment is not acceptable to the Contracting Officer, or if the Contracting Officer does not reach an agree

ment with the Contractor with respect to a price increase, the Contracting Officer may, within 30 days after receipt of the Contractor's request, cancel without liability to either party the Contractor's right to proceed with performance of that portion of the contract which is undelivered at the time of such cancellation.

(f) During the period after the Contractor has requested an upward adjustment, and prior to an agreement between the parties with respect to the request, or cancellation of the contract pursuant to paragraph (e), the Contractor shall continue deliveries according to the terms of the contract. The Contractor shall be paid for such deliveries at the applicable increased unit prices as requested, provided that such requested increases satisfy all the conditions and do not exceed the limitations of paragraph (d), and provided further that if the parties agree on an increase less than that requested, payments previously made at the requested amount shall be adjusted accordingly. If the Contracting Officer neither reaches an agreement with the Contractor on the requested adjustment, nor cancels the contract, the Contractor shall continue deliveries according to the terms of the contract, and the Contractor shall be paid therefor at the applicable increased unit prices as requested, provided that such requested increases satisfy all the conditions and do not exceed the limitations of paragraph (d).

[25 F.R. 41183, Dec. 31, 1960] § 7.106-4

Escalation clause for semistandard supplies.

The following price escalation clause is authorized for use in negotiated fixedprice supply contracts for semistandard supplies, the prices of which can be reasonably related to the prices of nearly equivalent standard supplies for which established prices exist. The clause may be used only when the total contract price is over $5,000 and delivery is not to be completed within six months after the contract date. A clear understanding should be set forth in writing prior to making the contract as to the identity of the standard supply items which are applicable. The percentage figure to be used in subparagraph (d)(3) of the clause shall not exceed 10 percent. any standard trade discounts offered by the Contractor against its list or catalog price are taken into account in negotiating the contract unit price, the Contracting Officer's file should contain a statement setting forth the list or catalog price and the discounts. The discounts referred to do not include prompt payment or cash discounts. When the supplies being purchased are standard

If

supplies in all respects except for preservation, packaging, and packing requirements, the following clause should not be used; in such cases the Escalation Clause for Standard Supplies, in § 7.106-3, is the appropriate clause.

PRICE ESCALATION (MAY 1957)

(a) The Contractor warrants that the supplies covered by this contract are supplies which the Contractor customarily offers for sale commercially, except for modifications in accordance with the specifications of this contract, and that as of the contract date any differences between the unit prices stated herein and the Contractor's established prices for like quantities of the supplies which are the nearest commercial equivalents of the supplies covered by this contract (herein referred to as "the established prices") are due to compliance with such specifications, and to compliance with any requirements which this contract may contain for preservation, packaging, and packing beyond standard commercial practice. The term "established price" as used in this clause is the net price after applying any applicable standard trade discounts offered by the Contractor from its list or catalog price.

(b) The Contractor shall promptly notify the Contracting Officer as to the amount and effective date of each decrease in any applicable established price, and each applicable contract unit price shall be decreased by the same percentage that the applicable established price is decreased. Any such decrease in a unit price shall apply to those supplies delivered on and after the effective date of each applicable decrease in the Contractor's established price, and this contract shall be amended accordingly. The Contractor shall certify on each invoice submitted under the contract that each unit price stated therein reflects all decreases, if any, which the Contractor had made in the established price applicable thereto, since the contract date, or shall certify on the final invoice that all such decreases have been applied to supplies delivered on and after the effective date of each such decrease in the Contractor's established prices.

(c) The Contractor may from time to time after the date of this contract and during the performance hereof, by written notice to the Contracting Officer, request an upward adjustment in any of the contract unit prices to be effective as of a date to be specified by the Contractor. Such request shall be acted upon in accordance with the following provisions of this clause.

(d) An upward adjustment in a contract unit price may be made under this clause only in accordance with the following conditions:

(1) Such an upward adjustment shall be made only if the Contractor's applicable es

tablished price has increased subsequent to the contract date.

(2) No unit price shall be increased by a percentage greater than the percentage increase in the Contractor's applicable established price.

(3) The aggregate of the increases in any unit price made under this clause shall not exceed ---- percent of the original applicable contract unit price.

(4) No adjusted unit price shall be effective earlier than the effective date of the increase in the applicable established price, or the date of receipt by the Contracting Officer of the Contractor's request for adjustment, whichever is the later.

(5) No upward adjustment in unit prices hereunder shall apply to supplies which were required by the contract delivery schedule to be delivered prior to the effective date of the related increase in the applicable established price, unless the Contractor's failure to deliver supplies in accordance with the delivery schedule results from causes beyond the control and without the fault or negligence of the Contractor, within the meaning of paragraph (b) of the clause of this contract entitled "Default," in which case the contract shall be amended to make an equitable extension of the delivery schedule.

(e) In the event the requested upward adjustment in any contract unit price is acceptable to the Contracting Officer, he shall so notify the Contractor, and the contract shall be amended accordingly. In the event the requested upward adjustment is not acceptable to the Contracting Officer, or if the Contracting Officer does not reach an agreement with the Contractor with respect to a price increase, the Contracting Officer may, pursuant to the clause of the contract entitled "Termination for Convenience of the Government," terminate the Contractor's right to proceed with performance of that portion of the contract which is undelivered at the time of such termination.

(f) During the period after the Contractor has requested an upward adjustment, and prior to an agreement between the parties with respect to the request, or termination of the contract pursuant to paragraph (e), the Contractor shall continue deliveries according to the terms of the contract. The Contractor shall be paid for such deliveries at the applicable increased unit prices as requested, provided that such requested increases satisfy all the conditions and do not exceed the limitations of paragraph (d), and provided further that if the parties agree on an increase less than that requested, payments previously made at the requested amount shall be adjusted accordingly. If the Contracting Officer either reaches an agreement with the Contractor on the requested adjustment, nor terminates the contract, the Contractor shall continue deliveries according to the terms of the contract, and the Contractor shall be paid therefor at

the applicable increased unit prices as requested, provided that such requested increases satisfy all the conditions and do not exceed the limitations of paragraph (d).

[25 F.R. 14184, Dec. 31, 1960]

§ 7.107 Price escalation clause (labor and material).

(a) The following price escalation clause is authorized for use in negotiated fixed-price supply contracts, other than fixed-price incentive or redeterminable contracts, where (1) the price exceeds $50,000, (2) the period of performance exceeds six months, (3) there is no major element of design engineering or developmental work involved in producing the items being procured, and (4) one or more identifiable labor or material cost factors are subject to change.

(b) The Schedule shall describe in detail the types of labor and materials subject to escalation, the labor rates (including fringe benefits, if any), and unit prices of materials, which may be increased or decreased, and the quantities of labor and specified materials allocable to each unit of supplies to be delivered under the contract. The following sample format illustrates a type of schedule description that may be used:

The following types of labor and material are subject to price escalation pursuant to clause of this contract.

[blocks in formation]

PRICE ESCALATION (JAN. 1958)

(a) The Contractor warrants that the prices set forth in this contract do not include any allowance for any contingency to cover increased costs of performance resulting from increases (1) the Contractor's rates of pay for labor or (ii) the unit prices for materials, set forth in the Schedule.

(b) If at any time during the performance of this contract there is an increase or decrease in the rates of pay for labor or unit prices for materials set forth in the Schedule, the Contractor shall notify the Contracting Officer thereof within 60 days of such increase or decrease or within such further period as may be approved in writing by the Contracting Officer, but in any event not later than final payment under the contract. Such notice shall include the Contractor's proposal for an equitable adjustment in the contract unit prices to be negotiated in accordance with paragraph (c) below and shall be accompanied by data, in such form as the Contracting Officer may require, explaining (i) the causes, (ii) the effective date, and (iii) the amount, both of the increase or decrease and of the Contractor's proposal for an equitable adjustment.

(c) Promptly upon receipt of any notice and data described in (b) above, the Contractor and the Contracting Officer shall negotiate an equitable adjustment, and the effective date thereof, in the contract unit prices to reflect any change in the cost of performance of this contract due to the increase or decrease in rates of pay for labor or unit prices for materials set forth in the Schedule: Provided, however, That such negotiations may be postponed by the Contracting Officer until an accumulation of such increases and decreases results in an adjustment allowable under (d) (v). The equitable adjustment and the effective date thereof, shall be set forth in an amendment or supplemental agreement to this contract. Such amendment or supplemental agreement shall also revise the rates of pay for labor or unit prices for materials set forth in the Schedule to reflect the increase or decrease therein. Failure of the parties to agree to an adjustment under this clause shall be deemed to be a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes." Pending agreement on, or determination of, any such adjustment and its effective date, the Contractor shall continue performance.

(d) Notwithstanding any other provision of this clause, any price adjustment under this clause shall be subject to the following limitations:

(1) There shall be no adjustment for supplies whose production cost is not affected by a change in the rates of pay for labor or unit prices for materials set forth in the Schedule;

(ii) There shall be no adjustment other than for increases or decreases in the rates

of pay for labor or unit prices for materials set forth in the Schedule;

(iii) There shall be no adjustment for any increase or decrease in the quantities of labor or materials set forth in the Schedule for each item to be delivered hereunder;

(iv) No upward adjustment shall apply to supplies which were required by the contract delivery schedule to be delivered prior to the effective date of the adjustment, unless the Contractor's failure to deliver supplies in accordance with the delivery schedule results from causes beyond the control and without the fault or negligence of the Contractor within the meaning of the clause of this contract entitled "Default," in which case the contract shall be amended to make equitable extension of the delivery

an

schedule;

(v) Except as provided in (e) below, there shall be no adjustment for any change in rates of pay for labor or unit prices for materials which would not result in a net change of at least three percent of the then current total contract price; and

(vi) There shall be no adjustment upward which would cause any adjusted contract unit price to exceed percent of the corresponding original contract unit price. (e) If, after delivery of the last unit called for by this contract, either party requests negotiation pursuant to (c) above, the limitations of (d) (v) shall not apply.

(f) The final invoice submitted under this contract shall include a certification that the Contractor has not experienced a decrease in rates of pay for labor or unit prices for materials set forth in the Schedule or that it has given notice of all such decreases in compliance with (b) above.

(g) The Contracting Officer may examine the Contractor's books, records, and other supporting data relevant to the costs of labor and materials during all reasonable times until three years after final payment under this contract.

[25 F.R. 14185, Dec. 31, 1960, as amended at 28 FR. 2100, Mar. 5, 1963]

§ 7.108 Incentive price revision clauses. [28 F.R. 2100, Mar. 5, 1963]

§ 7.108-1 Firm targets.

When in accordance with the provisions of Subpart D, Part 3 of this chapter, the fixed-price incentive con

When the total final negotiated cost is Equal to the total target cost---Greater than the total target cost___.

Less than the total target cost..

tract described in § 3.404-4(a) (2) of this chapter is to be used, the following clause shall be made a part of the contract. As to each item which is to be subject to incentive price revision, the contract schedule shall set forth the target cost, target profit, and target price.

INCENTIVE PRICE REVISION (FIRM TARGET)
(MAR. 1964)

(a) General. The supplies or services identified in the Schedule as Items

are subject to price revision in accordance with the provisions of this clause: Provided, That in no event shall the total final price of such items exceed dollars

(8‒‒‒‒‒‒‒‒). Any supplies or services which are to be ordered separately under, or otherwise added to, this contract, and which are to be subject to price revision in accordance with the provisions of this clause, shall be identified as such in a modification to this contract.

(b) Submission of data. Within (--) days after the end of the month in which the Contractor has delivered the last unit of supplies and completed the services called for by those items referred to in paragraph (a) above, the Contractor shall submit, in such form as the Contracting Officer may require, (1) a detailed statement of all costs incurred up to the end of that month in performing all work under such items, and (11) an estimate of costs of such further performance, if any, as may be necessary to complete performance of all work with respect to such items.

(c) Price revision. Upon submission of the data required by paragraph (b) above, the Contractor and the Contracting Officer shall promptly establish the total final price in accordance with the following:

(1) On the basis of the information required by paragraph (b) above, together with any other pertinent information, there shall be established by negotiation the total final cost reasonably incurred or to be incurred for and properly allocable to the supplies delivered (or services performed) and accepted by the Government, which are subject to price revision under this clause.

(2) The total final price shall be established by adjusting the total final negotiated cost by an amount for profit or loss determined as follows:

[blocks in formation]
« PreviousContinue »