such subcontract requiring the subcontractor to appropriately indemnify the engineer. It is also expected that any subcontractor subject to such indemnification will generally require substantially similar indemnification for defective cost or pricing data required to be submitted by his lower tier subcontractors.)

11. SUBCONTRACTS

(a) Any subcontractors and outside associates or consultants required by the engineer in connection with services under this agreement will be limited to such individuals or firms as were specifically identified and agreed to during negotiations, or as the owner specifically authorizes during the performance of this agreement. The owner must give prior approval for any substitutions in or additions to such subcontractors, associates, or consultants.

(b) The engineer may not subcontract services in excess of thirty (30) percent (or

percent, if the owner and the engineer hereby agree) of the contract price to subcontractors or consultants without the owner's prior written approval.

12. LABOR STANDARDS

To the extent that this agreement involves "construction" (as defined by the Secretary of Labor), the engineer agrees that such construction work shall be subject to the following labor standards provisions, to the extent applicable:

(a) Davis-Bacon Act (40 U.S.C. 276a276a-7);

(b) Contract Work Hours and Safety Standards Act (40 U.S.C. 327-333);

(c) Copeland Anti-Kickback Act (18 U.S.C. 874); and

(d) Executive Order 11246 (Equal Employment Opportunity);

and implementing rules, regulations, and relevant orders of the Secretary of Labor or EPA. The engineer further agrees that this agreement shall include and be subject to the "Labor Standards Provisions for Federally Assisted Construction Contracts" (EPA form 5720-4) in effect at the time of execution of this agreement.

[blocks in formation]

maximum practicable opportunity to participate in the performance of EPA grantassisted contracts and subcontracts.

15. COVENANT AGAINST CONTINGENT FEES

The engineer warrants that no person or selling agency has been employed or retained to solicit or secure this contract upon an agreement or understanding for a commission, percentage, brokerage, or contingent fee, excepting bona fide employees. For breach or violation of this warranty the owner shall have the right to annul this agreement without liability or in its discretion to deduct from the contract price or consideration, or otherwise recover, the full amount of such commission, percentage, brokerage, or contingent fee.

16. GRATUITIES

(a) If it is found, after notice and hearing. by the owner that the engineer, or any of the engineer's agents or representatives, offered or gave gratuities (in the form of entertainment, gifts, or otherwise), to any official, employee, or agent of the owner, of the State, or of EPA in an attempt to secure a contract or favorable treatment in awarding, amending, or making any determinations related to the performance of this agreement, the owner may, by written notice to the engineer, terminate the right of the engineer to proceed under this agreement. The owner may also pursue other rights and remedies that the law or this agreement provides. However, the existence of the facts upon which the owner bases such findings shall be in issue and may be reviewed in proceedings under the remedies clause of this agreement.

(b) In the event this agreement is terminated as provided in paragraph (a) hereof, the owner shall be entitled: (1) To pursue the same remedies against the engineer as it could pursue in the event of a breach of the contract by the engineer, and (2) as a penalty, in addition to any other damages to which it may be entitled by law, to exemplary damages in an amount (as determined by the owner) which shall be not less than 3 nor more than 10 times the costs the engineer incurs in providing any such gratuities to any such officer or employee.

17. PATENTS

If this agreement involves research, developmental, experimental, or demonstration work and any discovery or invention arises or is developed in the course of or under this agreement, such invention or discovery shall be subject to the reporting and rights provisions of Subpart D of 40 CFR, Part 30. in effect on the date of execution of this agreement, including Appendix B of Part 30. In such case, the engineer shall report

the discovery or invention to EPA directly or through the owner, and shall otherwise comply with the owner's responsibilities in accordance with Subpart D of 40 CFR, Part 30. The engineer agrees that the disposition of rights to inventions made under this agreement shall be in accordance with the terms and conditions of Appendix B. The engineer shall include appropriate patent provisions to achieve the purpose of this condition in all subcontracts involving research, developmental, experimental, or demonstration work.

18. COPYRIGHTS AND RIGHTS IN DATA

(a) The engineer agrees that any plans, drawings, designs, specifications, computer programs (which are substantially paid for with EPA grant funds), technical reports, operating manuals, and other work submitted with a step 1 facilities plan or with a step 2 or step 3 grant application or which are specified to be delivered under this agreement or which are developed or produced and paid for under this agreement (referred to in this clause as "Subject Data") are subject to the rights in the United States, as set forth in Subpart D of 40 CFR, Part 30 and in Appendix C to 40 CFR, Part 30, in effect on the date of execution of this agreement. These rights include the right to use, duplicate, and disclose such subject data, in whole or in part, in any manner for any purpose whatsoever, and to have others do so. For purposes of this clause, "grantee" as used in Appendix C refers to the engineer. If the material is copyrightable, the engineer may copyright it, as Appendix C permits, subject to the rights in the Government in Appendix C, but the owner and the Federal Government reserve a royalty-free, nonexclusive, and irrevocable license to reproduce, publish, and use such materials, in whole or in part, and to authorize others to do so. The engineer shall include appropriate provisions to achieve the purpose of this condition in all subcontracts expected to produce copyrightable subject data.

(b) All such subject data furnished by the engineer pursuant to this agreement are instruments of his services in respect of the project. It is understood that the engineer does not represent such subject data to be suitable for reuse on any other project or for any other purpose. If the owner reuses the subject data without the engineer's specific written verification or adaptation, such reuse will be at the risk of the owner, without liability to the engineer. Any such verification or adaptation will entitle the engineer to further compensation at rates agreed upon by the owner and the engineer.

APPENDIX C-2-REQUIRED PROVISIONS-Construction ContraCTS

SUPPLEMENTAL GENERAL CONDITIONS

1. General.

2. Changes.

3. Differing Site Conditions. 4. Suspension of Work.

5. Termination for Default; Damages for Delay; Time Extensions.

6. Termination for Convenience. 7. Remedies.

8. Labor Standards.

9. Utilization of Small or Minority Busi

ness.

10. Audit; Access to Records.

11. Price Reduction for Defective Cost or Pricing Data.

12. Covenant Against Contingent Fees. 13. Gratuities.

14. Patents.

15. Copyrights and Rights in Data. 16. Prohibition Against Listed Violating Facilities.

17. Buy American.

1. GENERAL

(a) The owner and the contractor agree that the following supplemental general provisions apply to the work to be performed under this contract and that these provisions supersede any conflicting provisions of this contract.

(b) This contract is funded in part by a grant from the U.S. Environmental Protection Agency. Neither the United States nor any of its departments, agencies or employees is a party to this contract. This contract is subject to regulations contained in 40 CFR 35.936, 35.938, and 35.939 in effect on the date of execution of this contract.

(c) The owner's rights and remedies provided in these clauses are in addition to any other rights and remedies provided by law or under this contract.

2. CHANGES

(a) The owner may, at any time, without notice to the sureties, by written order designated or indicated to be a change order, make any change in the work within the general scope of the contract, including but not limited to changes

(1) In the specifications (including drawings and designs);

(2) In the method or manner of performance of the work;

(3) In the owner-furnished facilities, equipment, materials, services, or site; or

(4) Directing acceleration in the performance of the work.

(b) Any other written order or an oral order (which terms as used in this paragraph (b) shall include direction, instruction, interpretation, or determination) from

the owner, which causes any such change, shall be treated as a change order under this clause, if the contractor gives the owner written notice stating the date, circumstances, and source of the order and if the contractor regards the order as a change order.

(c) Except as provided in this clause, no order, statement, or conduct of the owner shall be treated as a change under this clause or shall entitle the contractor to an equitable adjustment.

(d) If any change under this clause causes an increase or decrease in the contractor's cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any order, an equitable adjustment shall be made and the contract modified in writing accordingly. However, except for claims based on defective specifications, no claim for any change under paragraph (b) of this section 2., shall be allowed for any costs incurred more than 20 days before the contractor gives written notice as there required. Also, in the case of defective specifications for which the owner is responsible, the equitable adjustment shall include any increased cost reasonably incurred by the contractor in attempting to comply with such defective specifications.

(e) If the contractor intends to assert a claim for an equitable adjustment under this clause, he must, within 30 days after receipt of a written change order under (a) above or the furnishing of a written notice under paragraph (b) of this section 2., submit to the owner a written statement setting forth the general nature and monetary extent of such claim, unless the owner extends this period. The statement of claim hereunder may be included in the notice under paragraph (b) of this section 2.

(f) No claim by the contractor for an equitable adjustment hereunder shall be allowed if asserted after final payment under this contract.

3. DIFFERING SITE CONDITIONS

(a) The contractor shall promptly, and before such conditions are disturbed, notify the owner in writing of: (1) Subsurface or latent physical conditions at the site differing materially from those indicated in this contract, or (2) unknown physical conditions at the site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in this contract. The owner shall promptly investigate the conditions. If he finds that such conditions do materially differ and cause an increase or decrease in the contractor's cost of, or the time required for, performance of any part of the work under this contract, whether or not changed as a result of such conditions, an equitable adjustment

shall be made and the contract modified in writing accordingly.

(b) No claim of the contractor under this clause shall be allowed unless the contractor has given the notice required in paragraph (a) of this clause, except that the owner may extend the prescribed time.

(c) No claim by the contractor for an equitable adjustment hereunder shall be allowed if asserted after final payment under this contract.

4. SUSPENSION OF WORK

(a) The owner may order the contractor in writing to suspend, delay, or interrupt all or any part of the work for such period of time as he may determine to be appropriate for the convenience of the owner.

(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted by an act of the owner in administration of this contract, or by his failure to act within the time specfied in this contract (or if no time is specified, within a reasonable time), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by such unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent (1) that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the contractor or (2) for which an equitable adjustment is provided for or excluded under any other provision of this contract.

(c) No claim under this clause shall be allowed (1) for any costs incurred more than 20 days before the contractor shall have notified the owner in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order), and (2) unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of such suspension, delay, or interruption, but not later than the date of final payment under the contract.

5. TERMINATION FOR DEFAULT; DAMAGES FOR DELAY, TIME EXTENSIONS

(a) If the contractor refuses or fails to prosecute the work, or any separable part of the work, with such diligence as will insure its completion within the time specified in this contract, or any extension thereof, or fails to complete said work within such time, the owner may, by written notice to the contractor, terminate his right to proceed with the work or such part of the work as to which there has been delay. In such

event the owner may take over the work and prosecute the same to completion, by contract or otherwise, and may take possession of and use in completing the work such materials, appliances, and plant as may be on the site of the work and necessary therefor. Whether or not the contractor's right to proceed with the work is terminated, he and his sureties shall be liable for any damage to the owner resulting from his refusal or failure to complete the work within the specified time.

(b) If the contract provides for liquidated damages, and if the owner terminates the contractor's right to proceed, the resulting damage will consist of such liquidated damages until such reasonable time as may be required for final completion of the work together with any increased costs the owner incurs in completing the work.

(c) If the contract provides for liquidated damages and if the owner does not terminate the contractor's right to proceed, the resulting damage will consist of such liquidated damages until the work is completed or accepted.

(d) The contractor's right to proceed shall not be terminated nor the contractor charged with resulting damage if:

(1) The delay in the completion of the work arises from causes other than normal weather beyond the control and without the fault or negligence of the contractor, including, but not restricted to, acts of God, acts of the public enemy, acts of the owner in either its sovereign or contractual capacity, acts of another contractor in the performance of a contract with the owner, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, unusually severe weather, or delays of subcontractors or suppliers arising from causes other than normal weather beyond the control and without the fault or negligence of both the contractor and such subcontractors or suppliers; and

(2) The contractor, within 10 days from the beginning of any such delay (unless the owner grants a further period of time before the date of final payment under the contract), notifies the owner in writing of the causes of delay. The owner shall ascertain the facts and the extent of the delay and extend the time for completing the work when, in his judgment, the findings of fact justify such an extension. His findings of fact shall be final and conclusive on the parties, subject only to appeal as the remedies clause of this contract provides.

(e) If, after notice of termination of the contractor's right to proceed under the provisions of this clause, it is determined for any reason that the contractor was not in default under this clause, or that the delay was excusable under this clause, the rights and obligations of the parties shall be the same as if the notice of termination has

been issued under the clause providing for termination for convenience of the owner.

(f) The rights and remedies of the owner provided in this clause are in addition to any other rights and remedies provided by law or under this contract.

(g) As used in paragraph (d)(1) of this clause, the term "subcontractors or suppliers" means subcontractors or suppliers at any tier.

6. TERMINATION FOR CONVENIENCE

(a) The owner may terminate the performance of work under this contract in accordance with this clause in whole, or from time to time in part, whenever the owner shall determine that such termination is in the best interest of the owner. Any such termination shall be effected by delivery to the contractor of a notice of termination specifying the extent to which performance of work under the contract is terminated, and the date upon which such termination becomes effective.

(b) After receipt of a notice of termination, and except as otherwise directed by the owner, the contractor shall:

(1) Stop work under the contract on the date and to the extent specified in the notice of termination;

(2) Place no further orders or subcontracts for materials, services, or facilities except as necessary to complete the portion of the work under the contract which is not terminated;

(3) Terminate all orders and subcontracts to the extent that they relate to the performance of work terminated by the notice of termination;

(4) Assign to the owner, in the manner, at the times, and to the extent directed by the owner, all of the right, title, and interest of the contractor under the orders and subcontracts so terminated. The owner shall have the right, in its discretion, to settle or pay any or all claims arising out of the termination of such orders and subcontracts;

(5) Settle all outstanding liabilities and all claims arising out of such termination of orders and subcontracts, with the approval or ratification of the owner to the extent he may require. His approval or ratification shall be final for all the purposes of this clause;

(6) Transfer title to the owner, and deliver in the manner, at the times, and to the extent, if any, directed by the owner, (i) the fabricated or unfabricated parts, work in process, completed work, supplies, and other material produced as a part of, or acquired in connection with the performance of, the work terminated by the notice of termination, and (ii) the completed or partially completed plans, drawings, information, and other property which, if the contract had

been completed, would have been required to be furnished to the owner;

(7) Use his best efforts to sell, in the manner, at the times, to the extent, and at the price or prices that the owner directs or authorizes, any property of the types referred to in paragraph (b)(6) of this clause, but the contractor (i) shall not be required to extend credit to any purchaser, and (ii) may acquire any such property under the conditions prescribed and at a price or prices approved by the owner. The proceeds of any such transfer or disposition shall be applied in reduction of any payments to be made by the owner to the contractor under this contract or shall otherwise be credited to the price or cost of the work covered by this contract or paid in such other manner as the owner may direct;

(8) Complete performance of such part of the work as shall not have been terminated by the notice of termination; and

(9) Take such action as may be necessary, or as the owner may direct, for the protection and preservation of the property related to this contract which is in the possession of the contractor and in which the owner has or may acquire an interest.

(c) After receipt of a notice of termination, the contractor shall submit to the owner his termination claim, in the form and with the certification the owner prescribes. Such claim shall be submitted promptly but in no event later than 1 year from the effective date of termination, unless one or more extensions in writing are granted by the owner upon request of the contractor made in writing within such 1year period or authorized extension. However, if the owner determines that the facts justify such action, he may receive and act upon any such termination claim at any time after such 1-year period or extension. If the contractor fails to submit his termination claim within the time allowed, the owner may determine, on the basis of information available to him, the amount, if any, due to the contractor because of the termination. The owner shall then pay to the contractor the amount so determined.

(d) Subject to the provisions of paragraph (c), the contractor and the owner may agree upon the whole or any part of the amount or amounts to be paid to the contractor because of the total or partial termination of work under this clause. The amount or amounts may include a reasonable allowance for profit on work done. However, such agreed amount or amounts, exclusive of settlement costs, shall not exceed the total contract price as reduced by the amount of payments otherwise made and as further reduced by the contract price of work not terminated. The contract shall be amended accordingly, and the contractor shall be paid the agreed amount. Nothing in paragraph (e) of this clause, prescribing the amount to

be paid to the contractor in the event of failure of the contractor and the owner to agree upon the whole amount to be paid to the contractor because of the termination of work under this clause, shall be deemed to limit, restrict, or otherwise determine or affect the amount or amounts which may be agreed upon to be paid to the contractor pursuant to this paragraph (d).

(e) If the contractor and the owner fail to agree, as paragraph (d) of this section 6., provides, on the whole amount to be paid to the contractor because of the termination of work under this clause, the owner shall determine, on the basis of information available to him, the amount, if any, due to the contractor by reason of the termination and shall pay to the contractor the amounts determined as follows:

(1) For all contract work performed before the effective date of the notice of termination, the total (without duplication of any items) of

(i) The cost of such work;

(ii) The cost of settling and paying claims arising out of the termination of work under subcontracts or orders as paragraph (b)(5) of this clause provides. This cost is exclusive of the amounts paid or payable on account of supplies or materials delivered or services furnished by the subcontractor before the effective date of the notice of termination. These amounts shall be included in the cost on account of which payment is made under paragraph (1)(i) of this section 6.; and

(iii) A sum, as profit on paragraph (1)(i) of this section 6., that the owner determines to be fair and reasonable. But, if it appears that the contractor would have sustained a loss on the entire contract had it been completed, no profit shall be included or allowed under this paragraph (1) (iii) of this section 6., and an appropriate adjustment shall be made reducing the amount of the settlement to reflect the indicated rate of loss; and

(2) The reasonable cost of the preservation and protection of property incurred under paragraph (b)(9) of this clause; and any other reasonable cost incidental to termination of work under this contract, including expense incidental to the determination of the amount due to the contractor as the result of the termination of work under this contract. The total sum to be paid to the contractor under paragraph (e)(1) of this clause shall not exceed the total contract price as reduced by the amount of payments otherwise made and as further reduced by the contract price of work not terminated. Except for normal spoilage, and except to the extent that the owner shall have otherwise expressly assumed the risk of loss, there shall be excluded from the amounts payable to the