§ 35.936-7 Small and minority business.

Grantees shall make positive efforts to use small business and minorityowned business sources of supplies and services. Such efforts should allow these sources the maximum feasible opportunity to compete for subagreements to be performed using Federal grant funds.

§ 35.936-8 Privity of contract.

Neither EPA nor the United States shall be a party to any subagreement (including contracts or subcontracts), nor to any solicitation or request for proposals. (See §§ 35.937-9(a), 35.9384(c)(5), and Appendixes C-1 and C-2 to this subpart for the required solicitation statement and contract provisions.) However, in accordance with § 35.970 the Regional Administrator, if a grantee requests, may provide technical and legal assistance in the administration and enforcement of any contract related to treatment works for which an EPA grant was made.

§ 35.936-9 Disputes.

Only an EPA grantee may initiate and prosecute an appeal to the Administrator under the disputes provision of a grant with respect to its subagreements (see Subpart J of Part 30 of this subchapter). Neither a contractor nor a subcontractor may prosecute an appeal under the disputes provisions of a grant in its own name or interest.

§ 35.936-10 Federal procurement regulations.

Regulations applicable to direct Federal procurement shall not be applicable to subagreements under grants except as stated in this subchapter.

§ 35.936-11 General requirements for subagreements.

Subagreements must:

(a) Be necessary for and directly related to the accomplishment of the project work;

(b) Be in the form of a bilaterally executed written agreement (except for small purchases of $10,000 or less); (c) Be for monetary or in-kind consideration; and

(d) Not be in the nature of a grant or gift.

[blocks in formation]

(a) Procurement records and files for purchases in excess of $10,000 shall include the following:

(1) Basis for contractor selection;

(2) Justification for lack of competition if competition appropriate to the type of project work to be performed is required but is not obtained; and (3) Basis for award cost or price.

(b) The grantee or contractors of the grantee must retain procurement documentation required by § 30.805 of this subchapter and by this subpart, including a copy of each subagreement, for the period of time specified in § 30.805. The documentation is subject to all the requirements of § 30.805. A copy of each subagreement must be furnished to the project officer upon request.

§ 35.936-13 Specifications.

(a) Nonrestrictive specifications. (1) No specification for bids or statement of work in connection with such works shall be written in such a manner as to contain proprietary, exclusionary, or discriminatory requirements other than those based upon performance, unless such requirements are necessary to test or demonstrate a specific thing or to provide for necessary interchangeability of parts and equipment, or at least two brand names or trade names of comparable quality or utility are listed and are followed by the words "or equal." If brand or trade names are specified, the grantee must be prepared to identify to the Regional Administrator or in any protest action the salient requirements (relating to the minimum needs of the project) which must be met by any offeror. The single base bid method of solicitation for equipment and parts for determination of a low, responsive bidder may not be utilized. With regard to materials, if a single material is specified, the grantee must be prepared to substantiate the basis for the selection of the material.

(2) Project specifications shall, to the extent practicable, provide for maximum use of structures, machines, products, materials, construction methods, and equipment which are readily available through competitive

90-125 0-82--28

procurement, or through standard or proven production techniques, methods, and processes, except to the extent that innovative technologies may be used under § 35.908 of this subpart.

(b) Sole source restriction. A specification shall not require the use of structures, materials, equipment, or processes which are known to be available only from a sole source, unless the Regional Administrator determines that the grantee's engineer has adequately justified in writing that the proposed use meets the particular project's minimum needs or the Regional Administrator determines that use of a single source is necessary to promote innovation (see § 35.908). Sole source procurement must be negotiated under § 33.500 et seq., including full cost review.

(c) Experience clause restriction. The general use of experience clauses requiring equipment manufacturers to have a record of satisfactory operation for a specified period of time or of bonds or deposits to guarantee replacement in the event of failure is restricted to special cases where the grantee's engineer adequately justifies any such requirement in writing. Where such justification has been made, submission of a bond or deposit shall be permitted instead of a specified experience period. The period of time for which the bond or deposit is required should not exceed the experience period specified. No experience restriction will be permitted which unnecessarily reduces competition or innovation.

(d) Buy American. (1) Definitions. As used in this subpart, the following definitions apply:

(i) "Construction material" means any article, material, or supply brought to the construction site for incorporation in the building or work.

(ii) "Component" means any article, material, or supply directly incorporated in construction material.

(iii) "Domestic construction material" means an unmanufactured construction material which has been mined or produced in the United States, or a manufactured construction material which has been manufactured in the United States if the

cost of its components which are mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components.

(iv) "Nondomestic construction material" means a construction material other than a domestic construction material.

(2) Domestic preference. Domestic construction material may be used in preference to nondomestic materials if it is priced no more than 6 percent higher than the bid or offered price of the nondomestic materials including all costs of delivery to the construction site, any applicable duty, whether or not assessed. Computations will normally be based on costs on the date of opening of bids or proposals.

(3) Waiver. The Regional Administrator may waive the Buy American provision based upon those factors that he considers relevant, including: (i) Such use is not in the public interest;

(ii) The cost is unreasonable;

(iii) The Agency's available resources are not sufficient to implement the provision, subject to the Deputy Administrator's concurrence;

(iv) The articles, materials, or supplies of the class or kind to be used or the articles, materials, or supplies from which they are manufactured are not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities or satisfactory quality for the particular project; or

(v) Application of this provision is contrary to multilateral government procurement agreements, subject to the Deputy Administrator's concur

rence.

(4) Contract provision. Notwithstanding any other provision of this subpart, bidding documents and construction contracts for any step 3 project for which the Regional Administrator receives an application after February 1, 1978, shall contain the "Buy American" provision which requires use of domestic construction materials in preference to nondomestic construction materials.

(5) Substitution. If a nondomestic construction material or component is proposed for use, a bidder or contractor may substitute an approved domes

tic material or component (at no change in price), if necessary to comply with this subsection.

(6) Procedures. The Regional Administrator may use the appropriate procedures of § 35.939 in making the determinations with respect to this subsection. He shall generally observe the Buy American procedures, regulations, precedents, and requirements of other Federal departments and agencies.

[43 FR 44049, Sept. 27, 1978, as amended at 44 FR 37596, June 27, 1979; 44 FR 39340, July 5, 1979]

NOTE: For a class deviation document affecting § 35.936-13(a), see 47 FR 4066, Jan. 28, 1982.

§ 35.936-14 Force account work.

(a) A grantee must secure the project officer's prior written approval for use of the force account method for (1) any step 1 or step 2 work in excess of $10,000; (2) any sewer rehabilitation work in excess of $25,000 performed during step 1 (see § 35.927-3(a)); or (3) any step 3 work in excess of $25,000; unless the grant agreement stipulates the force account method.

(b) The project officer's approval shall be based on the grantee's demonstration that he possesses the necessary competence required to accomplish such work and that (1) the work can be accomplished more economically by the use of the force account method, or (2) emergency circumstances dictate its use.

(c) Use of the force account method for step 3 construction shall generally be limited to minor portions of a project.

§ 35.936-15 Limitations on subagreement award.

No subagreement shall be awarded: (a) To any person or organization which does not meet the responsibility standards in § 30.340-2 (a) through (d) and (g) of this subchapter;

(b) If any portion of the contract work not exempted by § 30.420-3(b) of this subchapter will be performed at a facility listed by the Director, EPA Office of Federal Activities, in violation of the antipollution requirements of the Clean Air Act and the Clean Water Act, as set forth in § 30.420-3 of this subchapter and 40 CFR, Part 15

(Administration of the Clean Air Act and the Federal Water Pollution Control Act with respect to Federal contracts, grants, or loans); or

(c) To any person or organization which is ineligible under the conflict of interest requirements of § 30.420-4 of this subchapter.

§ 35.936-16 Code or standards of conduct.

(a) The grantee must maintain a code or standards of conduct which shall govern the performance of its officers, employees, or agents in the conduct of project work, including procurement and expenditure of project funds. The grantee's officers, employees, or agents shall neither solicit nor accept gratuities, favors, or anything of monetary value from contractors or potential contractors. The grantee must avoid personal or organizational conflicts of interest or noncompetitive procurement practices which restrict or eliminate competition or otherwise restrain trade.

(b) To the extent permissible by State or local law or formal institutional requirements and procedures, the standards shall provide for penalties, sanctions, or other adequate disciplinary actions to be instituted for project-related violations of law or of the code or standards of conduct by either the grantee officers, employees, or agents, or by contractors or their agents.

(c) The grantee must inform the project officer in writing of each serious allegation of a project-related violation and of each known or proven project-related violation of law or code or standards of conduct, by its officers, employees, contractors, or by their agents. The grantee must also inform the project officer of the prosecutive or disciplinary action the grantee takes, and must cooperate with Federal officials in any Federal prosecutive or disciplinary action. Under § 30.245 of this subchapter, the project officer must notify the Director, EPA Security and Inspection Division, of all notifications from the grantee.

(d) EPA shall cooperate with the grantee in its disciplinary or prosecutive actions taken for any apparent project-related violations of law or of

[blocks in formation]

§ 35.936-18 Negotiation of subagreements. (a) Formal advertising, with adequate purchase descriptions, sealed bids, and public openings shall be the required method of procurement unless negotiation under paragraph (b) of this section is necessary to accomplish sound procurement.

(b) All negotiated procurement shall be conducted in a manner to provide to the maximum practicable extent open and free competition appropriate to the type of project work to be performed. The grantee is authorized to negotiate subagreements in accordance with the applicable procedures of this subchapter (see §§ 35.937 et seq. and 35.500 et seq.) if any of the following conditions exist:

(1) Public exigency will not permit the delay incident to formally advertised procurement (e.g., an emergency

procurement).

(2) The aggregate amount involved does not exceed $10,000 (see § 35.93619 for small purchases).

(3) The material or service to be procured is available from only one person or entity. If the procurement is expected to aggregate more than $10,000, the grantee must document its file with a justification of the need for noncompetitive procurement, and provide such documentation to the project officer on request.

(4) The procurement is for personal or professional services (including architectural or engineering services) or for any service that a university or other educational institution may render.

(5) No responsive, responsible bids at acceptable price levels have been received after formal advertising, and, with respect to procurement under § 35.938-4, the Regional Administrator's prior written approval has been obtained.

(6) The procurement is for materials or services where the prices are established by law.

(7) The procurement is for technical items or equipment requiring standardization and interchangeability of parts with existing equipment.

(8) The procurement is for experimental, developmental or research services.

§ 35.936-19 Small purchases.

(a) A small purchase is the procurement of materials, supplies, and services when the aggregate amount involved in any one transaction does not exceed $10,000. The small purchase limitation of $10,000 applies to the aggregate total of an order, including all estimated handling and freight charges, overhead, and profit to be paid under the order. In arriving at the aggregate amount involved in any one transaction, all items which should properly be grouped together must be included. Reasonable competition shall be obtained.

(b) Subagreements for small purchases need not be in the form of a bilaterally executed written agreement. Where appropriate, unilateral purchase orders, sales slips, memoranda of oral price quotations, and the like may be used to minimize paperwork. Retention in the purchase files of these documents and of written quotations received, or references to catalogs or printed price lists used, will suffice as the record supporting the price paid.

§ 35.936-20 Allowable costs.

(a) Incurring costs under subagreements which are not awarded or administered in compliance with this part or Part 33 of this subchapter, as appropriate, shall be cause for disallowance of those costs.

(b) Appropriate cost principles which apply to subagreements under EPA grants are identified in § 30.710 of this subchapter. Under that section, the contractor's actual costs, direct and indirect, eligible for Federal participation in a cost reimbursement contract shall be those allowable under the applicable provisions of 41 CFR 1-15.2 (Principles and Procedures

for Use in Cost-Reimbursement Type Supply and Research Contracts With Commercial Organizations) and 41 CFR 1-15.4 (Construction and Architect-Engineer Contracts).

(c) Reasonable costs of compliance with the procurement and project management requirements of these regulations are allowable costs of administration under the grant. Costs of announcement, selection, negotiation, and cost review and analysis in connection with procurement of architectural or engineering services are allowable, even when conducted before award of the grant. Legal and engineering costs which a grantee is required to incur in a protest action under § 35.939 are allowable.

§ 35.936-21 Delegation to State agencies; certification of procurement systems. (a) Under § 35.912 and Subpart F of this part, the Regional Administrator may delegate authority to a State agency to review and certify the technical and administrative adequacy of procurement documentation required under these sections.

(b) If a State agency believes that State laws which govern municipal procurement include the same requirements or operate to provide the same protections as do §§ 35.936, 35.937 and 35.938, the State may request the Administrator

to approve the State system instead of the procedures of these sections. EPA shall review the State system to determine its adequaсу.

(c) If a State agency determines that an applicant's procurement ordinances or applicable statutes include the same requirements or operate to provide the same protections as do §§ 35.936, 35.937 and 35.938, the State may certify (accompanied by appropriate documentation) the adequacy of the municipality's ordinances and statutes and request the Administrator to approve the municipality's system instead of the procedures of these sections. EPA shall conduct or may request the State to conduct a review of the municipality's system to determine its adequacy.

§ 35.936-22 Bonding and insurance.

(a) On contracts for the building and erection of treatment works or contracts for sewer system rehabilitation exceeding $100,000, each bidder must furnish a bid guarantee equivalent to 5 percent of the bid price. In addition, the contractor awarded a construction contract for the building and erection of treatment works or sewer system rehabilitation must furnish performance and payment bonds, each of which shall be in an amount not less than 100 percent of the contract price. Construction contracts less than $100,000 shall be subject to State and local requirements for bid guarantees, performance bonds, and payment bonds. For contracts or subcontracts in excess of $100,000 the Regional Administrator may authorize the grantee to use its own bonding policies and requirements if he determines, in writing, that the Government's interest is adequately protected.

(b) Contractors should obtain such construction insurance (e.g., fire and extended coverage, workmen's compensation, public liability and property damage, and "all risk" builder's risk or installation floater coverage) as is required by State or local law or the grantee or as is customary and appropriate. Under the Flood Disaster Protection Act of 1973, a contractor must purchase flood insurance to cover his risk of loss if the grantee has not purchased the insurance (see § 30.405-10 of this subchapter).

§ 35.937 Subagreements for architectural or engineering services.

(a) Applicability. Except as § 35.9372 otherwise provides, the provisions of §§ 35.937 through 35.937-11 apply to all subagreements of grantees for architectural or engineering services where the aggregate amount of services involved is expected to exceed $10,000. The provisions of §§ 35.937-2, 35.937-3, and 35.937-4 are not required, but may be followed, where the population of the grantee municipality is 25,000 or less according to the most recent U.S. census. When $10,000 or less of services (e.g., for consultant or consultant subcontract services) is