class pays a total charge for its share of the costs of operation and maintenance based upon actual use.

§ 35.929-2 General requirements for all user charge systems.

User charge systems based on actual use under § 35.929-1(a) or ad valorem taxes under § 35.929-1(b) shall also meet the following requirements:

(a) Initial basis for operation and maintenance charges. For the first year of operation, operation and maintenance charges shall be based upon past experience for existing treatment works or some other method that can be demonstrated to be appropriate to the level and type of services provided.

(b) Biennial review of operation and maintenance charges. The grantee shall review not less often than every 2 years the waste water contribution of users and user classes, the total costs of operation and maintenance of the treatment works, and its approved user charge system. The grantee shall revise the charges for users or user classes to accomplish the following:

(1) Maintain the proportionate distribution of operation and maintenance costs among users and user classes as required herein;

(2) Generate sufficient revenue to pay the total operation and maintenance costs necessary to the proper operation and maintenance (including replacement) of the treatment works;

and

(3) Apply excess revenues collected from a class of users to the costs of operation and maintenance attributable to that class for the next year and adjust the rate accordingly.

(c) Toxic pollutants. The user charge system shall provide that each user which discharges any toxic pollutants which cause an increase in the cost of managing the effluent or the sludge of the grantee's treatment works shall pay for such increased costs.

(d) Charges for operation and maintenance for extraneous flows. The user charge system shall provide that the costs of operation and maintenance for all flow not directly attributable to users (i.e., infiltration/inflow) be distributed among all users of the grantee's treatment works system based upon either of the following:

(1) In the same manner that it distributes the costs of operation and maintenance among users (or user classes) for their actual use, or

(2) Under a system which uses one of any combination of the following factors on a reasonable basis:

(i) Flow volume of the users; (ii) Land area of the users;

(iii) Number of hookups or discharges to the users;

(iv) Property valuation of the users, if the grantee has a user charge system based on ad valorem taxes approved under § 35.929-1(b).

(e) Adoption of system. One or more municipal legislative enactments or other appropriate authority must incorporate the user charge system. If the project is a regional treatment system accepting wastewaters from other municipalities, the subscribers receiving waste treatment services from the grantee shall adopt user charge systems in accordance with section 204(b)(1)(A) of the Act and §§ 35.929 through 35.929-3. These user charge systems shall also be incorporated in appropriate municipal legislative enactments or other appropriate authority of all municipalities contributing wastes to the treatment works. The public shall be informed of the financial impact of the user charge system on them and shall be consulted prior to adoption of the system, in accordance with 40 CFR Part 25.

(f) Notification. Each user charge system must provide that each user be notified, at least annually, in conjunction with a regular bill, of the rate and that portion of the user charges or ad valorem taxes which are attributable to waste water treatment services.

(g) Inconsistent agreements. The grantee may have preexisting agreements which address: (1) The reservation of capacity in the grantee's treatment works, or (2) the charges to be collected by the grantee in providing wastewater treatment services or reserving capacity. The user charge system shall take precedence over any terms or conditions of agreements or contracts between the grantee and users (including industrial users, special districts, other municipalities, or Federal agencies or installations) which are inconsistent with the re

quirements of section 204 (b)(1)(A) of the Act and these regulations.

(h) Costs of pretreatment program. A user charge system submitted by a municipality with an approved pretreatment program shall provide that the costs necessary to carry out the program and to comply with any applicable requirements of section 405 of the Act and related regulations are included within the costs of operation and maintenance of the system and paid through user charges, or are paid in whole or in part by other identified sources of funds.

[43 FR 44049, Sept. 27, 1978, as amended at 44 FR 10304, Feb. 16, 1979]

[blocks in formation]

(a) When a grantee's user charge system is approved, implementation of the approved system shall become a condition of the grant.

(b) The grantee shall maintain such records as are necessary to document compliance with these regulations.

(c) Appendix B to this subpart contains guidelines with illustrative examples of acceptable user charge systems.

(d) The Regional Administrator may review, no more often than annually, a grantee's user charge system to assure that it continues to meet the requirements of §§ 35.929-1 through 35.929-3.

[blocks in formation]

if he determines that the applicant has submitted the items required under § 35.920-3(a); (In the case of grant assistance awarded solely for the acquisition of eligible land, the following provisions are deferred until the award of the ensuing step 3 assistance for the construction of facilities: Sections 35.925-10, 35.925-11(b), 35.93512(c) and (d), 35.935-13(c), 35.93515(c), 35.935-16(b) and (c));

(2) Step 2. Construction drawings and specifications, if he determines that the applicant has submitted the items required under § 35.920-3(b);

(3) Step 3. Building and erection of a treatment works, if he determines that the applicant has submitted the items required under § 35.920-3(c); or

(4) Step 2 & 3. A combination of design (step 2) and construction (step 3) for a treatment works (see § 35.909) if he determines that the applicant has submitted the items required under § 35.920-3(d).

(b) The Regional Administrator may award Federal assistance by a grant or grant amendment from any allotment or reallotment available to a State under § 35.910 et seq. for payment of 100 percent of the cost of construction of treatment works required to train and upgrade waste treatment works operations and maintenance personnel and for the costs of other operator training programs. Costs of other operator training programs are limited to mobile training units, classroom rental, specialized instructors, and instructional material, under section 109(b) of the Act.

(1) Where a grant is made to serve two or more States, the Administrator is authorized to make an additional grant for a supplemental facility in each State. The Federal funds awarded under section 109(b) to any State for all training facilities or programs shall not exceed $500,000.

(2) Any grantee who received a grant under section 109(b) before December 27, 1977, is eligible to have the grant increased by funds made available under the Act, not to exceed 100 percent of eligible costs.

[43 FR 44049, Sept. 27, 1978, as amended at 44 FR 39340, July 5, 1979]

[blocks in formation]

§ 35.930-4 Project scope.

The grant agreement must define the scope of the project for which Federal assistance is awarded under the grant. The project scope must include a step or an identified segment. Grant assistance may be awarded for a segment of step 3 treatment works construction, when that segment in and of itself does not provide for achievement of applicable effluent discharge limitations, if:

(a) The segment is to be a component of an operable treatment works which will achieve the applicable effluent discharge limitations; and

(b) A commitment for completion of the entire treatment works is submitted to the Regional Administrator and that commitment is reflected in a special condition in the grant agreement.

§ 35.930-5 Federal share.

(a) General. The grant shall be 75 percent of the estimated total cost of construction that the Regional Administrator approves in the grant agreement, except as otherwise provided in paragraphs (b) and (c) of this section and in §§ 35.925-15, 35.925-16, 35.92517, 35.930-1(b), and paragraph 10 of Appendix A.

(b) Innovative and alternative technology. In accordance with § 35.908(b), the amount of any step 2, step 3, or step 2+3 grant assistance awarded from funds allotted for fiscal years 1979, 1980, and 1981 shall be 85 percent of the estimated cost of construction for those eligible treatment works or significant portions of them that the Regional Administrator determines meet the criteria for innovative or alternative technology in Appendix E. These grants depend on the availability of funds from the reserve under § 35.915-1(b). The proportional State contribution to the non-Federal share of construction costs for 85-percent grants must be the same as or greater than the proportional State contribution (if any) to the non-Federal share of eligible construction costs for all treatment works which receive 75-percent grants in the State.

(c) Modification and replacement of innovative and alternative projects. In accordance with § 35.908(c) and procedures published by EPA, the Regional Administrator may award grant assistance to fund 100 percent of the eligible costs of the modification or replacement of any treatment works constructed with grant assistance based upon a Federal share of 85 percent under paragraph (b) of this section.

NOTE: For a class deviation document affecting § 35.930-5(b), see 45 FR 84998, Dec. 24, 1980.

§ 35.930-6 Limitation on Federal share.

The grantee must exert its best efforts to perform the project work as specified in the grant agreement within the approved cost ceiling. If at any time the grantee believes that the costs which it expects to incur in the performance of the project will exceed or be substantially less than the previously approved estimated total project costs, the grantee must notify the Regional Administrator and the State agency promptly in writing. As soon as practicable, the grantee must give the revised estimate of total cost for the performance of the project (see § 30.900 of this subchapter). Delay in submission of the notice and excess cost information may prejudice ap

proval of an increase in the grant amount. The United States shall not be obligated to pay for costs incurred in excess of the approved grant amount or any amendment to it until the State has approved an increase in the grant amount from available allotments under § 35.915 and the Regional Administrator has issued a written grant amendment under § 35.955.

§ 35.935 Grant conditions.

In addition to the EPA general grant conditions (Subpart C and Appendix A to Part 30 of this subchapter), each treatment works grant shall be subject to the following conditions:

§ 35.935-1 Grantee responsibilities.

(a) Review or approval of project plans and specifications by or for EPA is for administrative purposes only and does not relieve the grantee of its responsibility to design, construct, operate, and maintain the treatment works described in the grant application and agreement.

(b) By its acceptance of the grant, the grantee agrees to complete the treatment works in accordance with the facilities plan, plans and specifications, and related grant documents approved by the Regional Administrator, and to maintain and operate the treatment works to meet the enforceable requirements of the Act for the design life of the treatment works. The Regional Administrator is authorized to seek specific enforcement or recovery of funds from the grantee, or to take other appropriate action (see § 35.965), if he determines that the grantee has failed to make good faith efforts to meet its obligations under the grant.

(c) The grantee agrees to pay, pursuant to section 204(a)(4) of the Act, the non-Federal costs of treatment works construction associated with the project and commits itself to complete the construction of the operable treatment works and complete waste treatment system (see definitions in § 35.905) of which the project is a part. (d) The Regional Administrator may include special conditions in the grant or administer this subpart in the manner which he determines most appropriate to coordinate with, restate,

[blocks in formation]

(a) The grantee must comply with the property provisions of § 30.810 et seq. of this subchapter with respect to all property (real and personal) acquired with project funds.

(b) With respect to real property (including easements) acquired in connection with the project, whether such property is acquired with or in anticipation of EPA grant assistance or solely with funds furnished by the grantee or others:

(1) The acquisition must be conducted in accordance with Part 4 of this chapter;

(2) Any displacement of a person by or as a result of any acquisition of the real property shall be conducted under the applicable provisions of Part 4 of this chapter; and

(3) The grantee must obtain (before initiation of step 3 construction), and must thereafter retain, a fee simple or such estate or interest in the site of a step 3 project, and rights of access, as the Regional Administrator finds sufficient to assure undisturbed use and possession for the purpose of construction and operation for the estimated life of the project. If a step 3 project serves more than one municipality, the grantee must insure that the participating municipalities have, or will have before the initiation of step 3 construction, such interests or rights in land as the Regional Administrator finds sufficient to assure their undisturbed utilization of the project site for the estimated life of the project.

(c) With respect to real property acquired with EPA grant assistance, the grantee must defer acquisition of such property until approval of the Region

al Administrator is obtained under § 35.940-3.

§ 35.935-4 Step 2+3 projects.

A grantee which has received step 2+3 grant assistance must make submittals required by § 35.920-3(c), together with approvable user charge and industrial cost recovery systems and a preliminary plan of operation. The Regional Administrator shall give written approval of these submittals before advertising for bids on the step 3 construction portion of the step 2+3 project. The cost of step 3 work initiated before such approval is not allowable. Failure to make the above submittals as required is cause for invoking sanctions under § 35.965.

§ 35.935-5 Davis-Bacon and related statutes.

Before soliciting bids or proposals for step 3-type work, the grantee must consult with the Regional Administrator concerning compliance with DavisBacon and other statutes referenced in § 30.415 et seq. of this subchapter. § 35.935-6 Equal employment opportunity. Contracts involving step 3-type work of $10,000 or more are subject to equal employment opportunity requirements under Executive Order 11246 (see Part 8 of this chapter). The grantee must consult with the Regional Administrator about equal employment opportunity requirements before issuance of an invitation for bids where the cost of construction work is estimated to be more than $1 million or where required by the grant agreement.

[blocks in formation]

audit, examination, excerpts, copies and transcriptions. The grantee must insure that a party to a subagreement will provide access to the project work, sites, documents, and records. See §§ 30.605 and 30.805 of this subchapter, clause 9 of Appendix C-1 to this subpart, and clause 10 of Appendix C-2 to this subpart.

§ 35.935-8 Supervision.

In the case of any project involving Step 3, the grantee will provide and maintain competent and adequate engineering supervision and inspection of the project to ensure that the construction conforms with the approved plans and specifications.

§ 35.935-9 Project initiation and completion.

(a) The grantee agrees to expeditiously initiate and complete the step 1, 2, or 3 project, or cause it to be constructed and completed, in accordance with the grant agreement and application, including the project progress schedule, approved by the Regional Administrator. Failure of the grantee to promptly initiate and complete step 1, 2, or 3 project construction may result in annulment or termination of the grant.

(b) No date reflected in the grant agreement, or in the project completion schedule, or extension of any such date, shall modify any compliance date established in an NPDES permit. It is the grantee's obligation to request any required modification of applicable permit terms or other enforceable requirements.

(c) The invitation for bids for step 3 project work is expected to be issued promptly after grant award. Generally this action should occur within 90 to 120 days after award unless compliance with State or local laws requires a longer period of time. The Regional Administrator shall annul or terminate the grant if initiation of all significant elements of step 3 construction has not occurred within 12 months of the award for the step 3 project (or approval of plans and specifications, in the case of a step 2+3 project). (See definition of "initiation of construction" under "con