§ 6.1002 Applicability.

(a) Administrative actions requiring environmental review. The environmental review requirements apply to the activities of EPA as set forth below:

(1) Major research or demonstration projects which affect the global commons or a foreign nation.

(2) Ocean dumping activities carried out under section 102 of the MPRSA which affect the related environment.

(3) Major permitting or licensing by EPA of facilities which affect the global commons or the environment of a foreign nation. This may include such actions as the issuance by EPA of hazardous waste treatment, storage, or disposal facility permits pursuant to section 3005 of the Resource Conservation and Recovery Act (42 U.S.C. Section 6925), NPDES permits pursuant to section 402 of the Clean Water Act (33 U.S.C. Section 1342), and prevention of significant deterioration approvals pursuant to Part C of the Clean Air Act (42 U.S.C. Section 7470 et seq.).

(4) Wastewater Treatment Construction Grants Program under Section 201 of the Clean Water Act when activities addressed in the facility plan would have environmental effects abroad.

(5) Other EPA activities as determined by OER and ΟΙΑ (see § 6.1007(c)).

§ 6.1003 Definitions.

As used in this subpart, "environment" means the natural and physical environment and excludes social, economic and other environments; "global commons" is that area (land, air, water) outside the jurisdiction of any nation; and "responsible official" is either the EPA Assistant Administrator or Regional Administrator as appropriate for the particular EPA program. Also, an action "significantly" affects the environment if it does significant harm to the environment even though on balance the action may be beneficial to the environment. To the extent applicable, the responsible official shall address the considerations set forth in the CEQ Regulations under 40 CFR 1508.27 in determining significant effect.

demonstration

§ 6.1004 Environmental review and assessment requirements. (a) Research and projects. The appropriate Assistant Administrator is responsible for performing the necessary degree of environmental review on research and demonstration projects undertaken by EPA. If the research or demonstration project affects the environment of the global commons, the applicant shall prepare an environmental analysis. This will assist the responsible official in determining whether an EIS is necessary. If it is determined that the action significantly affects the environment of the global commons, then an EIS shall be prepared. If the undertaking significantly affects a foreign nation EPA shall prepare a unilateral, bilateral or multilateral environmental study. EPA shall afford the affected foreign nation or international body or organization an opportunity to participate in this study. This environmental study shall discuss the need for the action, analyze the environmental impact of the various alternatives considered and list the agencies and other parties consulted.

(b) Ocean dumping activities. (1) The Assistant Administrator for Water and Waste Management shall ensure the preparation of appropriate environmental documents relating to ocean dumping activities in the global commons under section 102 of the MPRSA. For ocean dumping site designations prescribed pursuant to section 102(c) of the MPRSA and 40 CFR Part 228, EPA shall prepare an environmental impact statement consistent with the requirements of EPA's Procedures for the Voluntary Preparation of Environmental Impact Statements dated October 21, 1974 (see 39 FR 37419). Also EPA shall prepare an environmental impact statement for the establishment or revision of criteria under section 102(a) of MPRSA.

(2) For individual permits issued by EPA under section 102(b) an environmental assessment shall be made by EPA. Pursuant to 40 CFR Part 221, the permit applicant shall submit with the application an environmental analysis which includes a discussion of the need for the action, an outline of al

ternatives, and an analysis of the environmental impact of the proposed action and alternatives consistent with the EPA criteria established under Section 102(a) of MPRSA. The information submitted under 40 CFR Part 221 shall be sufficient to satisfy the environmental assessment require

ment.

(c) EPA permitting and licensing activities. The appropriate Regional Administrator is responsible for conducting concise environmental reviews with regard to permits issued under Section 3005 of the Resource Conservation and Recovery Act (RCRA permits), Section 402 of the Clean Water Act (NPDES permits), and Section 165 of the Clean Air Act (PSD permits), for such actions undertaken by EPA which affect the global commons or foreign nations. The information submitted by applicants for such permits or approvals under the applicable consolidated permit regulations (40 CFR Parts 122 and 124) and Prevention of Significant Deterioration (PSD) regulations (40 CFR Part 52) shall satisfy the environmental document requirement under Section 2-4(b) of Executive Order 12114. Compliance with applicable requirements in Part 124 of the consolidated permit regulations (40 CFR Part 124) shall be sufficient to satisfy the requirements to conduct a concise environmental review for permits subject to this paragraph.

(d) Wastewater Treatment Facility Planning. 40 CFR 6.507 details the environmental review process for the facilities planning under the wastewater treatment works construction grants program. For the purpose of these regulations, the facility plan shall also include a concise environmental review of those activities that would have environmental effects abroad. This shall apply only to the Step 1 grants awarded after the effective date of these regulations. Where water quality impacts identified in a facility plan are the subject of water quality agreements with Canada or Mexico, nothing in these regulations shall impose on the facility planning process coordination and consultation requirements in addition to those required by such agreements.

(e) Review by other Federal agencies and other appropriate officials. The responsible officials shall consult with other Federal agencies with relevant expertise during the preparation of the environmental document. As soon as feasible after preparation of the environmental document, the responsible official shall make the document available to the Council on Environmental Quality, Department of State, and other appropriate officials. The responsible official with assistance from OIA shall work with the Department of State to establish procedures for communicating with and making documents available to foreign nations and international organizations.

§ 6.1005 Lead or cooperating agency.

(a) Lead Agency. Section 3-3 of Executive Order 12114 requires the creation of a lead agency whenever an action involves more than one federal agency. In implementing Section 3-3, EPA shall, to the fullest extent possible, follow the guidance for the selection of a lead agency contained in 40 CFR 1501.5 of the CEQ regulations.

(b) Cooperating Agency. Under section 2-4(d) of the Executive Order, Federal agencies with special expertise are encouraged to provide appropriate resources to the agency preparing environmental documents in order to avoid duplication of resources. In working with a lead agency, EPA shall to the fullest extent possible serve as a cooperating agency in accordance with 40 CFR 1501.6. When other program commitments preclude the degree of involvement requested by the lead agency, the responsible EPA official shall so inform the lead agency in writing.

§ 6.1006 Exemptions and considerations.

Under section 2-5 (b) and (c) of the Executive Order, Federal agencies may provide for modifications in the contents, timing and availability of documents or exemptions from certain requirements for the environmental review and assessment. The responsible official, in consultation with the Director, Office of Environmental Review (OER), and the Director, Office of International Activities

(OIA), may approve modifications for situations described in section 2-5(b). The responsible official, in consultation with the Director, OER and Director OIA, shall obtain exemptions from the Administrator for situations described in section 2-5(c). The Department of State and the Council on Environmental Quality shall be consulted as soon as possible on the utilization of such exemptions.

§ 6.1007 Implementation.

(a) Oversight. OER is responsible for overseeing the implementation of these procedures and shall consult with OIA wherever appropriate. OIA shall be utilized for making formal contacts with the Department of State. OER shall assist the responsible officials in carrying out their responsibilities under these procedures.

(b) Information exchange. OER with the aid of OIA, shall assist the Department of State and the Council on Environmental Quality in developing the informational exchange on environmental review activities with foreign nations.

(c) Unidentified activities. The responsible official shall consult with OER and OIA to establish the type of environmental review or document appropriate for any new EPA activities or requirements imposed upon EPA by statute, international agreement other agreements.

APPENDIX A-STATEMENT

or

OF PROCE

[blocks in formation]

and floodplain management, including the restoration and preservation of such land areas as natural undeveloped floodplains, and to prescribe procedures to implement the policies and procedures of this Executive Order. Guidance for implementation of the Executive Order has been provided by the U.S. Water Resources Council in its Floodplain Management Guidelines dated February 10, 1978 (see 40 FR 6030).

b. Executive Order 11990 entitled "Protection of Wetlands", dated May 24, 1977, requires Federal agencies to take action to avoid adversely impacting wetlands wherever possible, to minimize wetlands destruction and to preserve the values of wetlands, and to prescribe procedures to implement the policies and procedures of this Executive Order.

c. It is the intent of these Executive Orders that, wherever possible, Federal agencies implement the floodplains/wetlands requirements through existing procedures, such as those internal procedures established to implement the National Environmental Policy Act (NEPA) and OMB A95 review procedures. In those instances where the environmental impacts of a proposed action are not significant enough to require an environmental impact statement (EIS) pursuant to section 102(2)(C) of NEPA, or where programs are not subject to the requirements of NEPA, alternative but equivalent floodplain/wetlands evaluation and notice procedures must be established.

Section 2 Purpose

a. The purpose of this Statement of Procedures is to set forth Agency policy and guidance for carrying out the provisions of Executive Orders 11988 and 11990.

b. EPA program offices shall amend existing regulations and procedures to incorporate the policies and procedures set forth in this Statement of Procedures.

c. To the extent possible, EPA shall accommodate the requirements of Executive Orders 11988 and 11990 through the Agency NEPA procedures contained in 40 CFR Part

6.

Section 3 Policy

a. The Agency shall avoid wherever possible the long and short term impacts associated with the destruction of wetlands and the occupancy and modification of floodplains and wetlands, and avoid direct and indirect support of floodplain and wetlands development wherever there is a practicable alternative.

b. The Agency shall incorporate floodplain management goals and wetlands protection considerations into its planning, regulatory, and decisionmaking processes. It shall also promote the preservation and res

90-125 0-82--10

toration of floodplains so that their natural and beneficial values can be realized. To the extent possible EPA shall:

(1) Reduce the hazard and risk of flood loss and wherever it is possible to avoid direct or indirect adverse impact on floodplains;

(2) Where there is no practical alternative to locating in a floodplain, minimize the impact of floods on human safety, health, and welfare, as well as the natural environment;

(3) Restore and preserve natural and beneficial values served by floodplains;

(4) Require the construction of EPA structures and facilities to be in accordance with the standards and criteria, of the regulations promulgated pursuant to the National Flood Insurance Program;

(5) Identify floodplains which require restoration and preservation and recommend management programs necessary to protect these floodplains and to include such considerations as part of on-going planning programs; and

(6) Provide the public with early and continuing information concerning floodplain management and with opportunities for participating in decision making including the (evaluation of) tradeoffs among competing alternatives.

c. The Agency shall incorporate wetlands protection considerations into its planning, regulatory, and decisionmaking processes. It shall minimize the destruction, loss, or degradation of wetlands and preserve and enhance the natural and beneficial values of wetlands. Agency activities shall continue to be carried out consistent with the Administrator's Decision Statement No. 4 dated February 21, 1973 entitled "EPA Policy to Protect the Nation's Wetlands."

Section 4 Definitions

a. "Base Flood" means that flood which has a one percent chance of occurrence in any given year (also known as a 100-year flood). This term is used in the National Flood Insurance Program (NFIP) to indicate the minimum level of flooding to be used by a community in its floodplain management regulations.

b. "Base Floodplain" means the 100-year floodplain (one percent chance floodplain). Also see definition of floodplain.

c. "Flood or Flooding" means a general and temporary condition of partial or complete inundation of normally dry land areas from the overflow of inland and/or tidal waters, and/or the unusual and rapid accumulation or runoff of surface waters from any source, or flooding from any other

source.

d. "Floodplain" means the lowland and relatively flat areas adjoining inland and coastal waters and other floodprone areas such as offshore islands, including at a mini

mum, that area subject to a one percent or greater chance of flooding in any given year. The base floodplain shall be used to designate the 100-year floodplain (one percent chance floodplain). The critical action floodplain is defined as the 500-year floodplain (0.2 percent chance floodplain).

e. "Floodproofing" means modification of individual structures and facilities, their sites, and their contents to protect against structural failure, to keep water out or to reduce effects of water entry.

f. "Minimize" means to reduce to the smallest possible amount or degree.

g. "Practicable" means capable of being done within existing constraints. The test of what is practicable depends upon the situation and includes consideration of the pertinent factors such as environment, community welfare, cost, or technology.

h. "Preserve" means to prevent modification to the natural floodplain environment or to maintain it as closely as possible to its natural state.

i. "Restore" means to re-establish a setting or environment in which the natural functions of the floodplain can again operate.

j. "Wetlands" means those areas that are inundated by surface or ground water with a frequency sufficient to support and under normal circumstances does or would support a prevalence of vegetative or aquatic life that requires saturated or seasonally saturated soil conditions for growth and reproduction. Wetlands generally include swamps, marshes, bogs, and similar areas such as sloughs, potholes, wet meadows, river overflows, mud flats, and natural ponds.

[blocks in formation]

(3) All agency actions where there is sufficient independent statutory authority to carry out the floodplain/wetlands procedures.

(4) In program areas where there is no EIS requirement nor clear statutory authority for EPA to require procedural implementation, EPA shall continue to provide leadership and offer guidance so that the value of floodplain management and wetlands protection can be understood and carried out to the maximum extent practicable in these programs.

c. These procedures shall not apply to any permitting or source review programs of EPA once such authority has been transferred or delegated to a State. However, EPA shall, to the extent possible, require States to provide equivalent effort to assure support for the objectives of these procedures as part of the state assumption proc

ess.

Section 6 Requirements

a. Floodplain/Wetlands review of proposed Agency actions.

(1) Floodplain/Wetlands DeterminationBefore undertaking an Agency action, each program office must determine whether or not the action will be located in or affect a floodplain or wetlands. The Agency shall utilize maps prepared by the Federal Insurance Administration (Flood insurance Rate Maps or Flood Hazard Boundary Maps), Fish and Wildlife Service (National Wetlands Inventory Maps), and other appropriate agencies to determine whether a proposed action is located in or will likely affect a floodplain or wetlands. If there is no adverse floodplain/wetlands impact identified, the action may proceed without further consideration of the remaining procedures set forth below.

(2) Early Public Notice-When it is apparent that a proposed or potential agency action is likely to impact a floodplain or wetlands, the public should be informed through appropriate public notice procedures.

(3) Floodplain/Wetlands Assessment-If the Agency determines a proposed action is located in or affects a floodplain or wetlands, a floodplain/wetlands assessment shall be undertaken. For those actions where an environmental assessment (EA) or environmental impact statement (EIS) is prepared pursuant to 40 CFR Part 6, the floodplain/wetlands assessment shall be prepared concurrently with these analyses and shall be included in the EA or EIS. In all other cases, a "floodplain/wetlands assessment" shall be prepared. Assessments shall consist of a description of the proposed action, a discussion of its effect on the floodplain/wetlands, and shall also describe the alternatives considered.

(4) Public Review of Assessments-For proposed actions impacting floodplain/wetlands where an EA or EIS is prepared, the opportunity for public review will be provided through the EIS provisions contained in 40 CFR Parts 6, 25, or 35, where appropriate. In other cases, an equivalent public notice of the floodplain/wetlands assessment shall be made consistent with the public involvement requirements of the applicable program.

(5) Minimize, Restore or Preserve-If there is no practicable alternative to locating in or affecting the floodplain or wetlands, the Agency shall act to minimize potential harm to the floodplain or wetlands. The Agency shall also act to restore and preserve the natural and beneficial values of floodplains and wetlands as part of the analysis of all alternatives under consideration.

(6) Agency Decision-After consideration of alternative actions, as they have been modified in the preceding analysis, the Agency shall select the desired alternative. For all Agency actions proposed to be in or affecting a floodplain/wetlands, the Agency shall provide further public notice announcing this decision. This decision shall be accompanied by a Statement of Findings, not to exceed three pages. This Statement shall include: (i) The reasons why the proposed action must be located in or affect the floodplain or wetlands; (ii) a description of significant facts considered in making the decision to locate in or affect the floodplain or wetlands including alternative sites and actions; (iii) a statement indicating whether the proposed action conforms to applicable State or local floodplain protection standards; (iv) a description of the steps taken to design or modify the proposed action to minimize potential harm to or within the floodplain or wetlands; and (v) a statement indicating how the proposed action affects the natural or beneficial values of the floodplain or wetlands. If the provisions of 40 CFR Part 6 apply, the Statement of Findings may be incorporated in the final EIS or in the environmental assessment. In other cases, notice should be placed in the FEDERAL REGISTER or other local medium and copies sent to Federal, State, and local agencies and other entities which submitted comments or are otherwise concerned with the floodplain/wetlands assessment. For floodplain actions subject to Office of Management and Budget (OMB) Circular A-95, the Agency shall send the Statement of Findings to State and areawide A-95 clearinghouse in the geographic area affected. At least 15 working days shall be allowed for public and interagency review of the Statement of Findings.

[blocks in formation]