Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects |
From inside the book
Results 1-5 of 77
Page 11
... damaged because of such temporary use of the project ; shall remove to the extent directed by the Engineer any work or materials used in the temporary maintenance and shall complete the project in every respect as though its prosecution ...
... damaged because of such temporary use of the project ; shall remove to the extent directed by the Engineer any work or materials used in the temporary maintenance and shall complete the project in every respect as though its prosecution ...
Page 14
... damage which may result from the moving of material or equipment . Load limits within the project shall not exceed legal limits of adjacent highways unless permitted in writing by the Engineer . The Contractor shall be liable for all damage ...
... damage which may result from the moving of material or equipment . Load limits within the project shall not exceed legal limits of adjacent highways unless permitted in writing by the Engineer . The Contractor shall be liable for all damage ...
Page 17
... damages which may occur after such delivery , and for any demurrage charges . 106.10 Material Guarantee . See SF 23A , General Provisions . 106.11 Rights in and Use of Materials Found on the Work . The Contractor , with ap- proval may ...
... damages which may occur after such delivery , and for any demurrage charges . 106.10 Material Guarantee . See SF 23A , General Provisions . 106.11 Rights in and Use of Materials Found on the Work . The Contractor , with ap- proval may ...
Page 18
... damages arising from the infringement upon or use of any patented , trademark or copyrighted design , device , material , or process . 107.04 Surfaces Opened by Permit . The right to construct or reconstruct any utility service in the ...
... damages arising from the infringement upon or use of any patented , trademark or copyrighted design , device , material , or process . 107.04 Surfaces Opened by Permit . The right to construct or reconstruct any utility service in the ...
Page 19
... damage , or unnecessary delay or interference with the railway company's trains or other property . Railroad liability insurance shall be obtained by the Contractor as provided in the special provisions . 107.09 Construction Over or ...
... damage , or unnecessary delay or interference with the railway company's trains or other property . Railroad liability insurance shall be obtained by the Contractor as provided in the special provisions . 107.09 Construction Over or ...
Contents
1 | |
6 | |
7 | |
8 | |
11 | |
17 | |
23 | |
26 | |
216 | |
219 | |
225 | |
227 | |
231 | |
232 | |
235 | |
237 | |
33 | |
37 | |
46 | |
48 | |
51 | |
52 | |
53 | |
56 | |
57 | |
58 | |
59 | |
61 | |
63 | |
65 | |
77 | |
79 | |
81 | |
82 | |
83 | |
90 | |
92 | |
93 | |
97 | |
103 | |
104 | |
105 | |
107 | |
184 | |
156 | |
157 | |
159 | |
182 | |
184 | |
188 | |
192 | |
197 | |
199 | |
204 | |
207 | |
210 | |
212 | |
213 | |
239 | |
240 | |
244 | |
245 | |
247 | |
249 | |
250 | |
251 | |
254 | |
257 | |
259 | |
261 | |
263 | |
266 | |
268 | |
270 | |
277 | |
280 | |
286 | |
287 | |
288 | |
291 | |
295 | |
297 | |
300 | |
302 | |
304 | |
305 | |
307 | |
312 | |
313 | |
314 | |
318 | |
322 | |
323 | |
324 | |
330 | |
337 | |
351 | |
353 | |
354 | |
Other editions - View all
Common terms and phrases
accepted aggregate Aluminum Alloy applied approved areas asphalt assembly ASTM backfill Basis of Payment bid schedule bituminous material bolts cleaned compacted completed compression members concrete Construction Requirements contract price contract unit price Contracting Officer Contractor Cubic yard curb curing damage designated determined as provided diameter dimensions drilled Emulsified Engineer equipment erection excavation expansion joints eyebars fabricated falsework finished full compensation furnished gabion gage galvanized grade grout holes inch installed joints Linear foot lump sum masonry meet the requirements metal Method of Measurement minimum mixing mortar mulch nuts paid paint panels pavement pay items listed Pay unit percent pipe placed plans plant plates portland cement prestressing price and payment protected quantity reasonably close conformity reinforcing steel removed requirements of AASHTO riprap rivets samples Section sheeting shown sieve special provisions Square yard stone structural steel subgrade surface temperature tensile strength thickness topsoil traffic weight welded width wire
Popular passages
Page 315 - The Contractor warrants that no person or selling agency has been employed or retained to solicit or secure this contract upon an agreement or understanding for a commission, percentage, brokerage, or contingent fee, excepting bona fide employees or bona fide established commercial or selling agencies maintained by the Contractor for the purpose of securing business. For breach or violation of this warranty the Government shall have the right to annul this contract without liability or in its discretion...
Page 314 - (5) The contractor will furnish all information and reports required by Executive Order No. 11246 of September 24, 1965, and by the rules, regulations, and orders of the Secretary of Labor, or pursuant thereto, and will permit access to his books, records, and accounts by the contracting agency and the Secretary of Labor for purposes of investigation to ascertain compliance with such rules, regulations, and orders.
Page 314 - Labor, or as otherwise provided by law. (g) The Contractor will include the provisions of paragraphs (a) through (g) in every subcontract or purchase order unless exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to section 204 of Executive Order No.
Page 314 - September 24, 1965, so that such provisions will be binding upon each subcontractor or vendor. The contractor will take such action with respect to any subcontract or purchase order as the contracting agency may direct as a means of enforcing such provisions including sanctions for noncompliance; Provided, however, That in the event the contractor becomes involved in or is threatened with, litigation with a subcontractor or vendor as a result of such direction by the contracting agency, the contractor...
Page 313 - The contractor agrees that the Comptroller General of the United States or any of his duly authorized representatives shall, until the expiration of 3 years after final payment under this contract or such lesser time specified in either Appendix M of the Armed Services Procurement Regulation or the Federal Procurement Regulations Part 1-20, as appropriate...
Page 313 - Contractor further agrees to include in all his subcontracts hereunder a provision to the effect that the subcontractor agrees that the Comptroller General of the United States or any of his duly authorized representatives shall, until the expiration of 3 years after final payment under...
Page 313 - Part 1-20, as appropriate, have access to and the right to examine any directly pertinent books, documents, papers, and records of such subcontractor, involving transactions related to the subcontract. The term "subcontract...
Page 307 - Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Contracting Officer, who shall reduce his decision to writing and mail or otherwise furnish a copy thereof to the Contractor.
Page 315 - ENTERPRISES (a) It is the policy of the Government that minority business enterprises shall have the maximum practicable opportunity to participate in the performance of Government contracts.
Page 307 - ... unless the same is fraudulent or capricious or arbitrary or so grossly erroneous as necessarily to imply bad faith or is not supported by substantial evidence.