(i) Any monitoring data plotted on graphs must be presented in a manner that will facilitate identification and analysis of trends. The data may be summarized to facilitate graphical representation.

(ii) Plan and sectional drawings of project structures sufficient to show the location of all critical or representative existing monitoring instruments must be included. If these drawings have been included in a previous report prepared and filed by an independent consultant, they may be incorporated by specific reference to that earlier report.

(2) Analyses. The report must:

(1) Analyze the safety of the project works and the maintenance and methods of operation of the development fully in light of the independent consultant's reviews, field inspections, assessments, and evaluations described in § 12.35;

(ii) Identify any changes in the information and analyses required by paragraph (b) of this section that have occurred since the last report by an independent consultant under this subpart and analyze the implications of those changes; and

(iii) Analyze the adequacy of existing monitoring instruments, periodic observation programs, and other methods of monitoring project works and conditions effecting the safety of the project or project works with respect to the development.

(3) Incorporation by reference. To the extent that conditions, assumptions, and available information have not changed since the last previous report by an independent consultant under this subpart, the analyses required under paragraphs (c)(2)(i) and (ii) of this section may be incorporated by specific reference to the last previous report.

(4) Recommendations. Based on the independent consultant's field observations and evaluations of the project works and the maintenance, surveillance, and methods of operation of the development, the report must contain the independent consultant's rec

ommendations on:

(i) Any corrective measures necessary for the structures or for the maintance or surveillance procedures

or methods of operation of the project works;

(ii) A reasonable time to carry out each corrective measure; and

(iii) Any new or additional monitoring instruments, periodic observations, or other methods of monitoring project works or conditions that may be required.

(5) Dissenting views. If the inspection and report were conducted and prepared by more than one independent consultant, the report must clearly indicate any dissenting views concerning the analyses or recommendations of the report that might be held by any individual consultant.

(6) List of participants. The report must identify all professional personnel who have participated in the inspection of the project or in preparation of the report and the independent consultant who directed those activities.

(7) Statement of independence. The independent consultant must declare that all conclusions and recommendations in the report are made independently of the licensee, its employees, and its representatives.

(8) Signature. The report must be signed by each independent consultant responsible for the report.

§ 12.38 Time for inspections and reports.

(a) General rule. After the initial inspection and report under this subpart for a project development, a new inspection under this subpart must be completed and the report on it filed not later than five years from the date the last report on an inspection was to be filed under this subpart.

(b) Initial inspection and report. (1) For any development that has a dam that is more than 32.8 feet (10 meters) in height above streambed or impounds an impoundment with a gross storage capacity of more than 2,000 acre feet (2.5 million cubic meters), which development was constructed before the date of issuance of the order licensing or amending a license to include that development, the initial inspection under this subpart must be completed and the report on it filed not later than two years after the date of issuance of the order licensing the development or

amending the license to include the development.

(2) For any development that was constructed after the date of issuance of the order licensing or amending a license to include the development, the initial inspection under this subpart must be completed and the report on it filed not later than five years from the date of first commercial operation, or the date on which the impoundment first reaches its normal maximum surface elevation, whichever occurs first.

(3) For any development not set forth in either subparagraph (b)(1) or (b)(2), the initial inspection under this subpart must be completed and the report on it filed by a date specified by the Regional Engineer. The filing date must not be more than two years after the date of notification that an inspection and report under this subpart are required.

(4) The last independent consultant's inspection and report made for a development before March 1, 1981 in compliance with the Commission's rules then in effect is deemed to fulfill the requirements for an initial inspection and report under this subpart for that development, except that the first report filed under this subpart for that development after March 1, 1981 must contain the information and analyses required by § 12.37(b).

(c) Extension of time. For good cause shown, the Regional Engineer may extend the time for filing an independent consultant's report under this subpart.

$12.39 Taking corrective measures after the report.

(a) Corrective plan and schedule. (1) Not later than 60 days after the report of the independent consultant is filed with the Regional Engineer, the licensee must submit to the Regional Engineer three copies of a plan and schedule for designing and carrying out any corrective measures that the licensee proposes.

(2) The plan and schedule may include any proposal, including taking no action, that the licensee considers a preferable alternative to any corrective measure recommended in the report of the independent consultant. Any proposed alternative must be accompanied by the licensee's complete

justification and detailed analysis and evaluation in support of that alternative.

(b) Carrying out the plan. The licensee must complete all corrective measures in accordance with the plan and schedule submitted to, and approved or modified by, the Regional Engineer.

(c) Extension of time. For good cause shown, the Regional Engineer may extend the time for filing the plan and schedule required by this section.

Subpart E-Other Responsibilities of Applicant or Licensee

§12.40 Quality control programs.

(a) General rule. During any construction, repair, or modification of project works, including any corrective measures taken pursuant to §12.39 of this part, the applicant or licensee must maintain any quality control program that may be required by the Regional Engineer, commensurate with the scope of the work and meeting any requirements or standards set by the Regional Engineer. If a quality control program is required, the construction, repair, or modification may not begin until the Regional Engineer has approved the program.

(b) If the construction, repair, or modification work is performed by a construction contractor, quality control inspection must be performed by the licensee, the design engineer, or an independent firm, other than the construction contractor, directly accountable to the licensee. This paragraph is not intended to prohibit additional quality control inspections by the construction contractor, or a firm accountable to the construction contractor, for the construction contractor's purposes.

(c) If the construction, repair, or modification of project works is performed by the applicant's or licensee's own personnel, the applicant or licensee must provide for separation of authority within its organization to make certain that the personnel responsible for quality control inspection are, to the satisfaction of the Regional Engineer or other authorized Commission representative, independent from the personnel who are responsible for

the construction, repair or modification.

§ 12.41 Monitoring instruments.

(a) In designing a project, a licensee must make adequate provision for installing and maintaining appropriate monitoring instrumentation whenever any physical condition that might affect the stability of a project structure has been discovered or is anticipated. The instrumentation must be satisfactory to the Regional Engineer and may include, for example, instruments to monitor movement of joints, foundation or embankment deformation, seismic effects, hydrostatic pore pressures, structural cracking, or internal stresses on the structure.

(b) If an applicant or licensee discovers any condition affecting the safety of the project or project works during the course of construction or operation, the applicant or licensee must install and maintain any monitoring devices and instruments that may be required by the Regional Engineer or other authorized Commission representative to monitor that condition. § 12.42 Warning and safety devices.

To the satisfaction of, and within a time specified by, the Regional Engineer, an applicant or licensee must install, operate, and maintain any signs, lights, sirens, barriers, or other safety devices that may reasonably be necessary or desirable to warn the public of fluctuations in flow from the project or otherwise to protect the public in the use of project lands and waters.

$12.43 Power and

communication

lines and gas pipelines.

(a) A licensee must take all reasonable precautions, and comply with all reasonable specifications that may be provided by the Regional Engineer, to ensure that any power or communication line or gas pipeline that is located over, under, or in project waters does not obstruct navigation for recreational or commercial purposes or otherwise endanger public safety.

(b) Clearances between any power or communication line constructed after March 1, 1981 and any vessels using

project waters must be at least sufficient to conform to any applicable requirements of the National Electrical Safety Code in effect at the time the power or communication line is constructed.

(c) The Regional Engineer may require a licensee or applicant to provide signs at or near power or communication lines to advise the public of the clearances for any power or communication lines located over, under, or in project waters.

§ 12.44 Testing spillway gates.

(a) General requirement. An applicant or licensee must make adequate provision, to the satisfaction of the Regional Engineer or other authorized Commission representative, to ensure that all spillway gates are operable at all times, particularly during adverse weather conditions.

(b) Annual test. (1) At least once each year, each spillway gate at a project must be operated to spill water, either during regular project operation or on a test basis.

(2) If an applicant or licensee does not operate each spillway gate on a test basis during the periodic inspection by the Commission staff, the applicant or licensee must submit to the Regional Engineer at least once each year a written statement, verified in accordance with § 12.13, that each spillway has been operated at least once during the twelve months preceding the inspection.

(c) Load-test of standby power. (1) An applicant or licensee must load-test the standby emergency power for spillway gate operation at regular intervals, but not less than once during each year, and submit to the Regional Engineer, at least once each year, a written statement, verified in accordance with §12.13, describing the intervals at which the standby emergency power was load-tested during the year preceding the inspection.

(2) The Commission staff may direct that a spillway gate be operated using standby emergency power during the periodic inspection.

[merged small][merged small][merged small][ocr errors]
[blocks in formation]

16.6 Notification procedures under section 15 of the Federal Power Act. 16.7 Information to be made available to the public at the time of notification of intent under section 15(b) of the Federal Power Act.

16.8 Consultation requirements. 16.9 Applications for new licenses and nonpower licenses for projects subject to sections 14 and 15 of the Federal Power Act.

16.10 Information to be provided by an applicant for new license: Filing requirements.

16.11 Nonpower licenses.

16.12 Application for exemption from licensing by a licensee whose license is subject to sections 14 and 15 of the Federal Power Act.

16.13 Standards and factors for issuing a new license.

[blocks in formation]

Subpart E-Projects With Minor and Minor Part Licenses Not Subject to Sections

14 and 15 of the Federal Power Act 16.19 Procedures for an existing licensee of a minor hydroelectric power project or of a minor part of a hydroelectric power project with a license not subject to sections 14 and 15 of the Federal Power Act. 16.20 Applications for subsequent license for a project with an expiring license not subject to sections 14 and 15 of the Federal Power Act.

16.21 Operation of projects with a minor or minor part license not subject to sections 14 and 15 of the Federal Power Act after expiration of a license.

16.22 Application for an exemption by a licensee with a minor or minor part license for a project not subject to sections 14 and 15 of the Federal Power Act.

Subpart F-Procedural Matters

16.23 Failure to file timely notices of in

tent.

16.24 Prohibitions against filing applications for new license, nonpower license, exemption, or subsequent license. 16.25 Disposition of a project for which no timely application is filed following a notice of intent to file.

16.26 Disposition of a project for which no timely application is filed following a notice of intent not to file.

AUTHORITY: 16 U.S.C. 791a-825r; 42 U.S.C. 7101-7352.

SOURCE: Order 513, 54 FR 23806, June 2, 1989, unless otherwise noted.

Subpart A-General Provisions

§ 16.1 Applicability.

This part applies to the filing and processing of an application for:

(a) A new license, a nonpower license, or an exemption from licensing for a hydroelectric project with an existing license subject to the provisions of sections 14 and 15 of the Federal Power Act.

(b) A subsequent license or an exemption from licensing for a hydroelectric project with an existing minor license or minor part license not subject to the provisions of sections 14 and 15 of the Federal Power Act because those sections were waived pursuant to section 10(i) of the Federal Power Act.

§ 16.2 Definitions.

For purposes of this part:

(a) New license means a license, except an annual license, for a water power project that is issued under section 15(a) of the Federal Power Act after an original license expires.

(b) New license application filing deadline, as provided in section 15(c)(1) of the Federal Power Act, is the date 24 months before the expiration of an existing license.

(c) Nonpower license means a license for a nonpower project issued under section 15(b) of the Federal Power Act. (d) Subsequent license means a license for a water power project issued under Part I of the Federal Power Act after a minor or minor part license that is not subject to sections 14 and 15 of the Federal Power Act expires.

[Order 513, 54 FR 23806, June 2, 1989, as amended by Order 513-A, 55 FR 15, Jan. 2, 1990; Order 533, 56 FR 23154, May 20, 1991]

§ 16.3 Public notice of projects under expiring licenses.

In addition to the notice of a licensee's intent to file or not to file an application for a new license provided in §16.6(d), the Commission will publish, in its annual report and annually in the FEDERAL REGISTER, a table showing the projects whose licenses will expire during the succeeding six years. The table will:

(a) List the licenses according to their expiration dates; and

(b) Contain the following information: license expiration date; licensee's name; project number; type of principal project works licensed, e.g., dam and reservoir, powerhouse, transmission lines; location by state, county, and stream; location by city or nearby city when appropriate; whether the existing license is subject to sections 14 and 15 of the Federal Power Act; and plant installed capacity.

§ 16.4 Acceleration of a license expiration date.

(a) Request for acceleration. (1) A licensee may file with the Commission, in accordance with the formal filing requirements in subpart T of part 385 of this chapter, a written request for acceleration of the expiration date of its existing license, containing the statements and information specified in

§16.6(b) and a detailed explanation of the basis for the acceleration request.

(2) If the Commission grants the request for acceleration pursuant to paragraph (c), the Commission will deem the request for acceleration to be a notice of intent under §16.6 and, unless the Commission directs otherwise, the licensee shall make available the information specified in §16.7 no later than 90 days from the date that the Commission grants the request for acceleration.

(b) Notice of request for acceleration. (1) Upon receipt of a request for acceleration, the Commission will give notice of the licensee's request and provide a 45-day period for comments by interested persons by:

(i) Publishing notice in the Federal Register;

(ii) Publishing notice once in a daily or weekly newspaper published in the county or counties in which the project or any part thereof or the lands affected thereby are situated; and

(iii) Notifying appropriate Federal, state, and interstate resource agencies and Indian tribes by mail.

(2) The notice issued pursuant to paragraphs (1) (i) and (ii) and the written notice given pursuant to paragraph (1)(iii) will be considered as fulfilling the notice provisions of § 16.6(d) should the Commission grant the acceleration request and will include an explanation of the basis for the licensee's acceleration request.

(c) Commission order. If the Commission determines it is in the public interest, the Commission will issue an order accelerating the expiration date of the license to not less than five years and 90 days from the date of the Commission order.

§ 16.5 Site access for a competing applicant.

(a) Access. If a potential applicant for a new license, subsequent license, or nonpower license for a project has complied with the first stage consultation provisions of §16.8(b)(1) and has notified the existing licensee in writing of the need for and extent of the access required, the existing licensee must allow the potential applicant to enter upon or into designated land, buildings, or other property in the project area at

A