7-2101.4 Specifications and Drawings. Insert the clause in 7-602.2. 7-2101.5 Changes. Insert the clause in 7-602.3.

7-2101.6 Differing Site Conditions. Insert the clause in 7-602.4. 7-2101.7 Termination for Default

Damages for Delay · Time Extensions.

TERMINATION FOR DEFAULT - DAMAGES FOR DELAY - TIME EXTENSIONS (1976 OCT)

(a) If the Contractor refuses or fails to prosecute the work, or any separable part thereof, with such diligence as will insure its completion within the time specified in this contract, or any extension thereof, or fails to complete said work within such time, the Government may, by written notice to the Contractor, terminate his right to proceed with the work or such part of the work as to which there has been delay. In such event the Government may take over the work and prosecute the same to completion, by contract or otherwise, and may take possession of and utilize in completing the work such materials, appliances, and plant as may be on the site of the work and necessary therefor. In addition, if title to property is vested in the Contractor under this contract it shall revest in the Government notwithstanding any other provision of this contract, except as to such property as the Contractor has disposed of by bona fide sale or property which has been removed from the site by the Contractor. Whether or not the Contractor's right to proceed with the work is terminated, he and his sureties shall be liable for any damage to the Government resulting from his refusal or failure to complete the work within the specified time.

(b) If fixed and agreed liquidated damages are provided in the contract and if the Government so terminates the Contractor's right to proceed, the resulting damage will consist of such liquidated damages until such reasonable time as may be required for final completion of the work together with any increased costs occasioned the Government in completing the work.

(c) If fixed and agreed liquidated damages are provided in the contract and if the Government does not so terminate the Contractor's right to proceed, the resulting damage will consist of such liquidated damages until the work is completed or accepted.

(d) The Contractor's right to proceed shall not be so terminated nor the Contractor charged with resulting damage if:

(1) The delay in the completion of the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, acts of the public enemy, acts of the Government in either its sovereign or contractual capacity, acts of another Contractor in the performance of a contract with the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, unusually severe weather, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of both the Contractor and such subcontractors or suppliers; and

(2) The Contractor, within ten (10) days from the beginning of any such delay (unless the Contracting Officer grants a further period of time before the date of final payment under the contract), notifies the Contracting Officer in writing of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of the delay and extend the time for completing the work when, in his judgment, the findings of fact justify such an extension, and his findings of fact shall be final and conclusive on the parties, subject only to appeal as provided in the "Disputes" clause of this contract.

(e) If, after notice of termination of the Contractor's right to proceed under the provisions of this clause, it is determined for any reason that the Contractor was not in default under the provisions of this clause, or that the delay was excusable under the provisions of this clause, the rights and obligations of the parties shall, if the contract contains a clause providing for termination for convenience of the Government, be the same as if the notice of termination had been issued pursuant to such clause. If, in the foregoing circumstances, this contract does not contain a clause providing for termination for convenience of the Government, the contract shall be equitably adjusted to compensate for such termination and the contract modified accordingly, failure to agree to any such adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled “Disputes".

7-2101.7

ARMED SERVICES PROCUREMENT REGULATION

7:528

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

authorize such payment to be made in full without retention of a percentage. Also, whenever the work is substantially complete, the Contracting Officer shall retain an amount he considers adequate for the protection of the Government and, at his discretion, may release to the Contractor all or a portion of any excess amount. Furthermore, on completion and acceptance of each separate unit or other division of the contract on which the price is stated separately in the contract, payment may be made therefor without retention of a percentage.

*(b) In further consideration of the performance hereof, the Contractor shall receive title to all property to be dismantled or demolished which is not specifically designated as being retained by the Government, said title to vest in the Contractor immediately upon the Contractor's receipt of the notice of award and furnishing of performance bond. The Government will not be responsible for the condition of or any loss or damage to such property from any cause whatsoever. In the event the Contractor does not wish to remove from the site any part of the property he has acquired hereunder, the Contracting Officer may, upon written request, grant the Contractor permission to leave such property on the premises. The Contractor agrees as a condition of the granting of such permission to waive any right, title, claim or interest in and to such property. *Delete if inapplicable.

(c) Upon completion and acceptance of all work required hereunder, final payment of the amount due the Contractor under this contract will be made upon the presentation of a properly executed voucher therefor, and in addition, if requested, a release of all claims against the Government arising under and by virtue of this contract, other than such claims, if any, in stated amounts as may be specifically excepted by the Contractor from the operation of the release. (End of clause)

(b) In accordance with 4-504, insert the following clause in contracts providing for payment of compensation by the contractor to the Government in consideration of the right to salvage and remove for his own use the materials resulting from the dismantling or demolition operation. In special circumstances where it will be advantageous to the Government, the clause may be modified to provide for payments by the contractor to the Government in increments and for transfer of title to the contractor for increments of property only upon receipt of such payments.

PAYMENT BY CONTRACTOR TO GOVERNMENT (1976 OCT)

(a) The Contractor shall receive title to all property to be dismantled or demolished covered by this contract not specifically designated in the specifications as being retained by the Government, said title to vest in the Contractor immediately upon receipt of the notice of award and furnishing of performance bond. The Government will not be responsible for the condition of or any loss or damage to such property from any cause whatsoever. All property acquired by the Contractor hereunder shall be removed from the site by the Contractor promptly, as the storage of such property on the site will not be permitted beyond the completion date hereof. In the event the Contractor does not wish to remove from the site any part of the property he has acquired hereunder, the Contracting Officer may, upon written request, grant the Contractor permission to leave such property on the premises. The Contractor agrees as a condition of the granting of such permission to waive any right, title, claim or interest in and to such property.

(b) The Contractor shall perform the work called for in the "Statement of Work" clause of this contract and, unless otherwise provided in the specifications, within days of the receipt of notice of award and before proceeding with dismantling or demolition, shall pay..... ...(figures)........... Checks shall be made payable to the office designated for contract administration and shall be forwarded to the Contracting Officer.

(End of clause)

7-2101.3

ARMED SERVICES PROCUREMENT REGULATION

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

7:529

7-2101.4 Specifications and Drawings. Insert the clause in 7-602.2. 7-2101.5 Changes. Insert the clause in 7-602.3.

7-2101.6 Differing Site Conditions. Insert the clause in 7-602.4. 7-2101.7 Termination for Default

TERMINATION FOR DEFAULT

(1976 OCT)

Damages for Delay - Time Extensions.

[blocks in formation]

(a) If the Contractor refuses or fails to prosecute the work, or any separable part thereof, with such diligence as will insure its completion within the time specified in this contract, or any extension thereof, or fails to complete said work within such time, the Government may, by written notice to the Contractor, terminate his right to proceed with the work or such part of the work as to which there has been delay. In such event the Government may take over the work and prosecute the same to completion, by contract or otherwise, and may take possession of and utilize in completing the work such materials, appliances, and plant as may be on the site of the work and necessary therefor. In addition, if title to property is vested in the Contractor under this contract it shall revest in the Government notwithstanding any other provision of this contract, except as to such property as the Contractor has disposed of by bona fide sale or property which has been removed from the site by the Contractor. Whether or not the Contractor's right to proceed with the work is terminated, he and his sureties shall be liable for any damage to the Government resulting from his refusal or failure to complete the work within the specified time.

(b) If fixed and agreed liquidated damages are provided in the contract and if the Government so terminates the Contractor's right to proceed, the resulting damage will consist of such liquidated damages until such reasonable time as may be required for final completion of the work together with any increased costs occasioned the Government in completing the work.

(c) If fixed and agreed liquidated damages are provided in the contract and if the Government does not so terminate the Contractor's right to proceed, the resulting damage will consist of such liquidated damages until the work is completed or accepted.

(d) The Contractor's right to proceed shall not be so terminated nor the Contractor charged with resulting damage if:

(1) The delay in the completion of the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, acts of the public enemy, acts of the Government in either its sovereign or contractual capacity, acts of another Contractor in the performance of a contract with the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, unusually severe weather, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of both the Contractor and such subcontractors or suppliers; and

(2) The Contractor, within ten (10) days from the beginning of any such delay (unless the Contracting Officer grants a further period of time before the date of final payment under the contract), notifies the Contracting Officer in writing of the causes of delay. The Contracting Of ficer shall ascertain the facts and the extent of the delay and extend the time for completing the work when, in his judgment, the findings of fact justify such an extension, and his findings of fact shall be final and conclusive on the parties, subject only to appeal as provided in the "Disputes" clause of this contract.

(e) If, after notice of termination of the Contractor's right to proceed under the provisions of this clause, it is determined for any reason that the Contractor was not in default under the provisions of this clause, or that the delay was excusable under the provisions of this clause, the rights and obligations of the parties shall, if the contract contains a clause providing for termination for convenience of the Government, be the same as if the notice of termination had been issued pursuant to such clause. If, in the foregoing circumstances, this contract does not contain a clause providing for termination for convenience of the Government, the contract shall be equitably adjusted to compensate for such termination and the contract modified accordingly, failure to agree to any such adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes".

7-2101.7

ARMED SERVICES PROCUREMENT REGULATION

7:530

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

(f) The rights and remedies of the Government provided in this clause are in addition to any other rights and remedies provided by law or under this contract.

(g) As used in paragraph (d)(1) of this clause, the term “subcontractors or suppliers" means subcontractors or suppliers at any tier.

(End of clause)

During a period of national emergency, paragraph (d) of the above clause may be changed by deleting the word "unforeseeable" and inserting the phrase "other than normal weather", after the word "causes" wherever it appears.

7-2101.8 Termination for Convenience of the Government.

(a) Insert the following clause in contracts exceeding $10,000 in value. In accordance with E-621, the last sentence of paragraph (j) of the clause may be deleted in contracts with agencies of the United States Government, foreign governments or agencies thereof, or State or local governments or agencies thereof.

TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (1976 OCT)

(a) The performance of work under this contract may be terminated by the Government in accordance with this clause in whole, or from time to time in part, whenever the Contracting Officer shall determine that such termination is in the best interest of the Government. Any such termination shall be effected by delivery to the Contractor of a Notice of Termination specifying the extent to which performance of work under the contract is terminated, and the date upon which such termination becomes effective. Upon receipt by the Contractor of the Notice of Termination, if title to property is vested in the Contractor under this contract, it shall revest in the Government notwithstanding any other provision of this contract, except as to such property as the Contractor has disposed of by bona fide sale or property which has been removed from the site by the Contractor.

(b) After receipt of a Notice of Termination, and except as otherwise directed by the Contracting Officer, the Contractor shall:

(i) stop work under the contract on the date and to the extent specified in the Notice of Termination;

(ii) place no further orders or subcontracts for materials, services or facilities, except as may be necessary for completion of such portion of the work under the contract as is not terminated;

(iii) terminate all orders and subcontracts to the extent that they relate to the performance of work terminated by the Notice of Termination;

(iv) assign to the Government, in the manner, at the times, and to the extent directed by the Contracting Officer, all of the right, title, and interest of the Contractor under the orders and subcontracts so terminated, in which case the Government shall have the right, in its discretion, to settle or pay any or all claims arising out of the termination of such orders and subcontracts;

(v) settle all outstanding liabilities and all claims arising out of such termination of orders and subcontracts, with the approval or ratification of the Contracting Officer, to the extent he may require, which approval or ratification shall be final for all the purposes of this clause;

(vi) transfer title and deliver to the Government, in the manner, at the times, and to the extent, if any, directed by the Contracting Officer, (A) the fabricated or unfabricated parts, work in process, completed work, supplies, and other material produced as a part of, or acquired in connection with the performance of, the work terminated by the Notice of Termination, and (B) the completed or partially completed plans, drawings, information, and other property which, if the contract had been completed, would have been required to be furnished to the Government;

7-2101.8

ARMED SERVICES PROCUREMENT REGULATION

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

7:531

(vii) use his best efforts to sell, in the manner, at the times, to the extent, and at the price or prices directed or authorized by the Contracting Officer, any property of the types referred to in (vi) above; provided, however, that the Contractor (A) shall not be required to extend credit to any purchaser, and (B) may acquire any such property under the conditions prescribed by and at a price or prices approved by the Contracting Officer; and provided further that the proceeds of any such transfer or disposition shall be applied in reduction of any payments to be made by the Government to the Contractor under this contract or shall otherwise be credited to the price or cost of the work covered by this contract or paid in such other manner as the Contracting Officer may direct;

(viii) complete performance of such part of the work as shall not have been terminated by the Notice of Termination; and

(ix) take such action as may be necessary, or as the Contracting Officer may direct, for

the protection and preservation of the property related to this contract which is in the possession of the Contractor and in which the Government has or may acquire an interest.

At any time after expiration of the plant clearance period, as defined in Section VIII, Armed Services Procurement Regulation, as it may be amended from time to time, the Contractor may submit to the Contracting Officer a list, certified as to quantity and quality, of any or all items of termination inventory not previously disposed of, exclusive of items the disposition of which has been directed or authorized by the Contracting Officer, and may request the Government to remove such items or enter into a storage agreement covering them. Not later than fifteen (15) days thereafter, the Government will accept title to such items and remove them or enter into a storage agreement covering the same; provided, that the list submitted shall be subject to verification by the Contracting Officer upon removal of the items, or if the items are stored, within fortyfive (45) days from the date of submission of the list, and any necessary adjustment to correct the list as submitted shall be made prior to final settlement.

(c) After receipt of a Notice of Termination, the Contractor shall submit to the Contracting Officer his termination claim, in the form and with certification prescribed by the Contracting Officer. Such claim shall be submitted promptly but in no event later than one year from the effective date of termination, unless one or more extensions in writing are granted by the Contracting Officer, upon request of the Contractor made in writing within such one year period or authorized extension thereof. However, if the Contracting Officer determines that the facts justify such action, he may receive and act upon any such termination claim at any time after such one year period or any extension thereof. Upon failure of the Contractor to submit his termination claim within the time allowed, the Contracting Officer may determine, on the basis of information available to him, the amount, if any, due to the Contractor by reason of the termination and shall thereupon pay to the Contractor the amount so determined.

(d) Subject to the provisions of paragraph (c), the Contractor and the Contracting Officer may agree upon the whole or any part of the amount or amounts to be paid to the Contractor by reason of the total or partial termination of work pursuant to this clause, which amount or amounts may include a reasonable allowance for profit on work done; provided, that such agreed amount or amounts, exclusive of settlement costs, shall not exceed the total contract price as reduced by the amount of payments otherwise made and as further reduced by the contract price of work not terminated. The contract shall be amended accordingly, and the Contractor shall be paid the agreed amount. Nothing in paragraph (e) of this clause, prescribing the amount to be paid to the Contractor in the event of failure of the Contractor and the Contracting Officer to agree upon the whole amount to be paid to the Contractor by reason of the termination of work pursuant to this clause, shall be deemed to limit, restrict, or otherwise determine or affect the amount or amounts which may be agreed upon to be paid to the Contractor pursuant to this paragraph (d).

(e) In the event of the failure of the Contractor and the Contracting Officer to agree, as provided in paragraph (d), upon the whole amount to be paid to the Contractor by reason of the termination of work pursuant to this clause, the Contracting Officer shall pay to the Contractor the amounts determined by the Contracting Officer as follows, but without duplication of any amounts agreed upon in accordance with paragraph (d):