CONTRACT CLAUSES AND SOLICITATION PROVISIONS

7-602.40 Cleaning Up.

CLEANING UP (1965 JAN)

The Contractor shall at all times keep the construction area, including storage areas used by him, free from accumulations of waste material or rubbish and prior to completion of the work remove any rubbish from the premises and all tools, scaffolding, equipment, and materials not the property of the Government. Upon completion of the construction the Contractor shall leave the work and premises in a clean, neat and workmanlike condition satisfactory to the Contracting Officer.

7-602.41 Additional Definitions.

(End of clause)

ADDITIONAL DEFINITIONS (1965 JAN)

(a) Wherever in the specifications or upon the drawings the words "directed", "required", "ordered", "designated", "prescribed", or words of like import are used, it shall be understood that the "direction", "requirement", "order", “designation", or "prescription", of the Contracting Officer is intended and similarly the words "approved", "acceptable”, “satisfactory" or words of like import shall mean "approved by" or "acceptable to", or "satisfactory to" the Contracting Officer, unless otherwise expressly stated.

(b) Where "as shown", "as indicated", "as detailed", or words of similar import are used, it shall be understood that the reference is made to the drawings accompanying this contract unless stated otherwise. The word "provided" as used herein shall be understood to mean “provided complete in place", that is "furnished and installed".

7-602.42 Accident Prevention.

(End of clause)

(a) Normally the following clause concerning safety controls, records, reports and corrective action to be taken shall be inserted.

ACCIDENT PREVENTION (1977 JUN)

(a) In order to provide safety controls for protection to the life and health of employees and other persons; for prevention of damage to property, materials, supplies, and equipment; and for avoidance of work interruptions in the performance of this contract, the Contractor shall comply with all pertinent provisions of Corps of Engineers Manual, EM 385-1-1, dated 1 June 1977, entitled "General Safety Requirements", as amended, and will also take or cause to be taken such additional measures as the Contracting Officer may determine to be reasonably necessary for the purpose.

(b) The Contractor will maintain an accurate record of, and will report to the Contracting Officer in the manner and on the forms prescribed by the Contracting Officer, exposure data and all accidents resulting in death, traumatic injury, occupational disease, and damage to property, materials, supplies and equipment incident to work performed under this contract.

(c) The Contracting Officer will notify the Contractor of any noncompliance with the foregoing provisions and the action to be taken. The Contractor shall, after receipt of such notice, immediately take corrective action. Such notice, when delivered to the Contractor or his representative at the site of the work, shall be deemed sufficient for the purpose. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such stop orders shall be made the subject of claim for extension of time or for excess costs or damages by the Contractor.

(d) Compliance with the provisions of this clause by subcontractors will be the responsibility |

of the Contractor.

(End of clause)

(b) In contracts involving work of long duration or of hazardous character, the following paragraph (e) will be added to the above clause:

7-602.42

ARMED SERVICES PROCUREMENT REGULATION

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

(e) Prior to commencement of the work the Contractor will:

(1) submit in writing his proposals for effectuating this provision for accident prevention; (2) meet in conference with representatives of the Contracting Officer to discuss and develop mutual understandings relative to administration of the over-all safety program.

7-602.43 Government Inspectors.

GOVERNMENT INSPECTORS (1965 JAN)

The work will be conducted under the general direction of the Contracting Officer and is subject to inspection by his appointed inspectors to insure strict compliance with the terms of the contract. No inspector is authorized to change any provision of the specifications without written authorization of the Contracting Officer, nor shall the presence or absence of an inspector relieve the Contractor from any requirements of the contract.

(End of clause)

7-602.44 Commencement, Prosecution and Completion of Work.

(a) In accordance with 18-105, insert the following clause (except this clause may be appropriately modified to accommodate the issuance of orders under Indefinite Delivery Type contracts).

COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (1965 JAN)

calendar

The Contractor will be required to commence work under this contract within days after the date of receipt by him of notice to proceed, to prosecute said work diligently, and to complete the entire work ready for use not later than The time stated for completion shall include final clean-up of the premises.

.................

(End of clause)

(b) When the completion date is expressed, not in a specified number of days after receipt of notice to proceed, but rather as a calendar day, which date is computed on the basis of the contractor receiving the notice to proceed by a certain day, add the following to the above clause:

The foregoing completion date is based on the assumption that the successful bidder will receive the notice to proceed by The Government will extend the completion date by

the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the bid. (1968 APR)

7-602.45 Contract Drawings, Maps and Specifications.

CONTRACT DRAWINGS, MAPS AND SPECIFICATIONS (1965 JAN)

(a)........... sets (five unless otherwise specified herein) of large scale contract drawings, maps and specifications will be furnished the Contractor without charge except applicable publications incorporated into the technical provisions by reference. Additional sets will be furnished on request at the cost of reproduction. The work shall conform to the following contract drawings and maps, all of which form a part of these specifications and are available in the office of

[blocks in formation]

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

(b) Omissions from the drawings or specifications or the misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work but they shall be performed as if fully and correctly set forth and described in the drawings and specifications.

(c) The Contractor shall check all drawings furnished him immediately upon their receipt and shall promptly notify the Contracting Officer of any discrepancies. Figures marked on drawings shall in general be followed in preference to scale measurements. Large scale drawings shall in general govern small scale drawings. The Contractor shall compare all drawings and verify the figures before laying out the work and will be responsible for any errors which might have been avoided thereby.

(End of clause)

7-602.46 Suspension of Work.

SUSPENSION OF WORK (1968 FEB)

(a) The Contracting Officer may order the Contractor in writing to suspend, delay, or interrupt all or any part of the work for such period of time as he may determine to be appropriate for the convenience of the Government.

(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted by an act of the Contracting Officer in the administration of this contract, or by his failure to act within the time specified in this contract (or if no time is specified, within a reasonable time), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by such unreasonable suspension, delay, or interruption and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent (1) that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor or (2) for which an equitable adjustment is provided for or excluded under any other provision of this contract.

(c) No claim under this clause shall be allowed (1) for any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order), and (2) unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of such suspension, delay, or interruption, but not later than the date of final payment under the contract.

(End of clause)

7-602.47 Rights in Shop Drawings. In accordance with 18-910.1(b), insert the following clause.

RIGHTS IN SHOP DRAWINGS (1966 APR)

(a) Shop drawings for construction means drawings, submitted to the Government by the Construction Contractor, subcontractor or any lower tier subcontractor pursuant to a construction contract, showing in detail (i) the proposed fabrication and assembly of structural elements and (ii) the installation (ie., form, fit, and attachment details) of materials or equipment. The Government may duplicate, use, and disclose in any manner and for any purpose shop drawings delivered under this contract.

(b) This clause, including this paragraph (b), shall be included in all subcontracts hereunder at any tier.

(End of clause)

7-602.47

ARMED SERVICES PROCUREMENT REGULATION

7:297

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

7-602.48 Minority Business Enterprises. In accordance with 1-332, insert the appropriate clause or clauses in 7-104.36.

7-602.49 Affirmative Action for Disabled Veterans and Veterans of the Vietnam Era. Insert the clause in 7-103.27.

7-602.50 Value Engineering (VE). Insert the following clause in all fixedprice type construction contracts of $100,000 or more.

VALUE ENGINEERING INCENTIVE (1977 AUG)

(a) Application. This clause applies to a Contractor developed and documented Value Engineering Change Proposal (VECP) which:

(i) requires a change to this contract to implement the VECP; and

(ii) reduces the contract price without impairing essential function or characteristics, provided that it is not based solely on a change in deliverable end item quantities. (b) Documentation. As a minimum, the following information shall be submitted by the Contractor with each VECP:

(i) a description of the difference between the existing contract requirement and the proposed change, and the comparative advantages and disadvantages of each; justification where function or characteristics of a work item is being altered; and the effect of the change on the performance of the end item;

(ii) an analysis and itemization of the requirements of the contract which must be changed if the VECP is accepted and a recommendation as to how to make each such change (e.g., a suggested specification revision);

(iii) a separate detailed cost estimate for both the existing contract requirement and the proposed change to provide an estimate of the reduction in costs, if any, that will result from acceptance of the VECP, taking into account the costs of development and implementation by the Contractor (including any amount attributable to subcontracts in accordance with paragraph (f) below);

(iv) a prediction of any effects the proposed change would have on related costs to the Military Department such as Government furnished property costs, and costs of maintenance and operation;

(v) a statement of the time by which a change order adopting the VECP must be issued so as to obtain the maximum cost reduction during the remainder of this contract, noting any effect on the contract completion time or delivery schedule; and

(vi) identification of any previous submission of the VECP, including the dates submitted, the agencies involved, the numbers of the Government contracts involved, and the previous actions by the Government, if known.

(c) Submission. To expedite a determination, VECPS shall be submitted to the Resident Engineer at the worksite with a copy to the Contracting Officer. Proposals shall be processed expeditiously; however, the Government shall not be liable for any delay in acting upon any proposal submitted pursuant to this clause. If the evaluation period is likely to exceed 45 calendar days, the PCO shall promptly notify the Contractor of the estimated decision date and provide the reasons for the additional time required. The Contractor has the right to withdraw, in whole or in part, any VECP not accepted by the Government within the period specified in the VECP.

(d) Acceptance. The Contracting Officer may accept, in whole or in part, by contract modification any VECP submitted pursuant to this clause. The Contracting Officer may accept the VECP even though an agreement on price reduction has not been reached, by issuing the Contractor a notice to proceed with the change. Until a notice to proceed is issued or a contract modification applies a VECP to this contract, the Contractor shall remain obligated to perform in accordance with this contract. Contract modifications made pursuant to this clause will so state. The decision of the Contracting Officer as to the acceptance of any VECP under this contract shall be final and shall not be subject to the “Disputes" clause of this contract.

(e) Sharing. If a VECP submitted by the Contractor pursuant to this clause is accepted, the contract price shall be adjusted without regard to profit in accordance with the following provisions:

7-602.50

ARMED SERVICES PROCUREMENT REGULATION

[blocks in formation]

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

(i) Definition:

(A) Instant contract savings to the Contractor (ICS) are the estimated reduction in the Contractor's cost of performance resulting from the acceptance of the VECP. The proposed cost reduction includes estimated allowable Contractor development and implementation costs (CC). The Contractor's development and implementation costs include any subcontractor development and implementation costs (see (f) below). For purposes of this clause, Contractor development costs are those costs incurred after the Contractor has identified a specific VE project and prior to acceptance and implementation by the Govern

ment.

(B) Government Costs (GC) are those DoD costs which directly result from development and implementation of the VECP, such as test and evaluation of the VECP.

(ii) Calculations and Actions. Multiply ICS by 45% and GC by 55%. Add these two results, e.g., (.45 ICS plus .55 GC) and subtract from the contract price.

(f) Subcontracts. The Contractor shall include appropriate VE arrangements in any subcontract of $50,000 or greater, and may include such arrangements in contracts of lesser value. To compute any adjustment in the contract price under paragraph (e) above, the Contractor's cost of development and implementation of a VECP which is accepted under this contract shall include any development and implementation costs of a subcontractor, which clearly pertains to such VECP, but shall exclude any VE incentive payments which the Contractor may make to a subcontractor. The Contractor may make whatever VE incentive payment arrangements he chooses with his subcontractors, provided that any payments to subcontractors under such arrangements are made from the Contractor's, and not the Government's, share of the savings resulting from the VECP.

(g) Data. The Contractor may restrict the Government's right to use any sheet of a VECP or of the supporting data, submitted pursuant to this clause, in accordance with the terms of the following legend if it is marked on such sheet:

“This data furnished pursuant to the Value Engineering Incentive clause of contract shall not be disclosed outside the Government, or duplicated, used, or disclosed, in whole or in part, for any purpose other than to evaluate a VECP submitted under said clause. This restriction does not limit the Government's right to use information contained in this data if it is or has been obtained, or is otherwise available, from the Contractor or from another source, without limitations."

In the event of acceptance of a VECP, the Contractor hereby grants to the Government unlimited rights, as defined in the clause of ASPR 7-104.9(a), in the VECP and supporting data, except that, with respect to data which qualifies as and is submitted as limited rights technical data in accordance with the clause of ASPR 7–104.9(a), the Government shall have the rights specified in the contract modification referred to in paragraph (d) hereof and the data shall be appropriately marked.

(End of clause)

7-602.51 Affirmative Action for Handicapped Workers. Insert the clause in

7-103.28.

7-602.52 Clean Air and Water. In accordance with 1-2302.2, insert the clause in 7-103.29.

7-602.53 Payment of Interest on Contractors' Claims. In accordance with 1-333, insert the clause in 7-104.82.

7-602.54 Shop Drawings.

(a) Insert the following clause, with the appropriate additions in (b) and (c) below.

SHOP DRAWINGS (1976 OCT)

(a) The term "shop drawings" includes drawings, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials furnished by the Contractor to explain in detail specific portions of the work required by the contract.

(b) If this contract requires shop drawings, the Contractor shall coordinate all such drawings, and review them for accuracy, completeness, and compliance with contract requirements and shall indicate his approval thereon as evidence of such coordination and review. Shop drawings submitted to the Contracting Officer without evidence of the Contractor's approval may be

7-602.54