CONTRACT CLAUSES AND SOLICITATION PROVISIONS

7-302.9 Default. In accordance with 8-710, insert the following clause.

(a) The following clause shall be used in all fixed-price research and development contracts as defined in 7-301, except:

(i) as provided in (b) below; and

(ii) contracts with educational or nonprofit institutions which are awarded on the basis of no profit.

DEFAULT (1969 AUG)

(a) The Government may, subject to the provisions of paragraph (c) of this clause, by written Notice of Defaults to the Contractor terminate the whole or any part of this contract in any one of the following circumstances:

(1) if the Contractor fails to perform the work called for by this contract within the time(s) specified herein or any extension thereof; or

(ii) if the Contractor fails to perform any of the other provisions of this contract, or so fails to prosecute the work as to endanger performance of this contract in accordance with its terms, and in either of these two circumstances does not cure such failure within a period of 10 days (or such longer period as the Contracting Officer may authorize in writing) after receipt of notice from the Contracting Officer specifying such failure. (b) In the event the Government terminates this contract in whole or in part as provided in paragraph (a) of this clause, the Government may procure, upon such terms and in such manner as the Contracting Officer may deem appropriate, work similar to the work so terminated and the Contractor shall be liable to the Government for any excess costs for such similar work; provided, that the Contractor shall continue the performance of this contract to the extent not terminated under the provisions of this clause.

(c) Except with respect to defaults of subcontractors, the Contractor shall not be liable for any excess costs if the failure to perform the contract arises out of causes beyond the control and without the fault or negligence of the Contractor. Such causes may include, but are not restricted to, acts of God or of the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather; but in every case the failure to perform must be beyond the control and without the fault or negligence of the Contractor. If the failure to perform is caused by the default of a subcontractor, and if such default arises out of causes beyond the control of both the Contractor and subcontractor, and without the fault or negligence of either of them, the Contractor shall not be liable for any excess costs for failure to perform, unless the supplies or service to be furnished by the subcontractor were obtainable from other sources in sufficient time to permit the Contractor to meet the required delivery schedule or other performance requirements.

(d) If this contract is terminated as provided in paragraph (a) of this clause, the Government, in addition to any other rights provided in this clause, may require the Contractor to transfer title and deliver to the Government, in the manner and to the extent directed by the Contracting Officer any of the completed or partially completed work not therefore delivered to, and accepted by, the Government and any other property, including contract rights, specifically produced or specifically acquired for the performance of such part of this contract as has been terminated; and the Contractor shall, upon the direction of the Contracting Officer, protect and preserve property in the possession of the Contractor in which the Government has an interest. The Government shall pay to the Contractor the contract price, if separately stated, for completed work accepted by the Government and the amount agreed upon by the Contractor and the Contracting Officer for (i) completed work for which no separate price is stated, (ii) partially completed work, (iii) other property described above which is accepted by the Government and, (iv) the protection and preservation of property. Failure to agree shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled “Disputes". The Government may withhold from amounts otherwise due the Contractor for such completed supplies or manufacturing materials such sum as the Contracting Officer determines to be necessary to protect the Government against loss because of outstanding liens or claims of former lien holders.

(e) If, after notice of termination of this contract under the provisions of this clause, it is determined for any reason that the Contractor was not in default under the provisions of this clause, or

7-302.9

ARMED SERVICES PROCUREMENT REGULATION

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

that the default was excusable under the provisions of this clause, the rights and obligations of the parties shall, if the contract contains a clause providing for termination for convenience of the Government, be the same as if the notice of termination had been issued pursuant to such clause. (f) The rights and remedies of the Government provided in this clause shall not be exclusive and are in addition to any other rights and remedies provided by law or under this contract. (g) As used in paragraph (c) of this clause, the terms “subcontractor" and "subcontractors" mean subcontractor(s) at any tier.

(End of clause)

(b) In contracts which do not contain a clause providing for termination for convenience of the Government, insert the following clause.

DEFAULT - ALTERNATE (1974 APR)

(a) The Government may, subject to the provisions of paragraph (c) of this clause, by written Notice of Defaults to the Contractor terminate the whole or any part of this contract in any one of the following circumstances:

(i) if the Contractor fails to perform the work called for by this contract within the time(s) specified herein or any extension thereof; or

(ii) if the Contractor fails to perform any of the other provisions of this contract, or so fails to prosecute the work as to endanger performance of this contract in accordance with its terms, and in either of these two circumstances does not cure such failure within a period of 10 days (or such longer period as the Contracting Officer may authorize in writing) after receipt of notice from the Contracting Officer specifying such failure.

(b) In the event the Government terminates this contract in whole or in part as provided in paragraph (a) of this clause, the Government may procure, upon such terms and in such manner as the Contracting Officer may deem appropriate, work similar to the work so terminated and the Contractor shall be liable to the Government for any excess costs for such similar work; provided, that the Contractor shall continue the performance of this contract to the extent not terminated under the provisions of this clause.

(c) Except with respect to defaults of subcontractors, the Contractor shall not be liable for any excess costs if the failure to perform the contract arises out of causes beyond the control and without the fault or negligence of the Contractor. Such causes may include, but are not restricted to, acts of God or of the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather; but in every case the failure to perform must be beyond the control and without the fault or negligence of the Contractor. If the failure to perform is caused by the default of a subcontractor, and if such default arises out of causes beyond the control of both the Contractor and subcontractor, and without the fault or negligence of either of them, the Contractor shall not be liable for any excess costs for failure to perform, unless the supplies or service to be furnished by the subcontractor were obtainable from other sources in sufficient time to permit the Contractor to meet the required delivery schedule or other performance requirements.

(d) If this contract is terminated as provided in paragraph (a) of this clause, the Government, in addition to any other rights provided in this clause, may require the Contractor to transfer title and deliver to the Government, in the manner and to the extent directed by the Contracting Officer any of the completed or partially completed work not therefore delivered to, and accepted by, the Government and any other property, including contract rights, specifically produced or specifically acquired for the performance of such part of this contract as has been terminated; and the Contractor shall, upon the direction of the Contracting Officer, protect and preserve property in the possession of the Contractor in which the Government has an interest. The Government shall pay to the Contractor the contract price, if separately stated, for completed work accepted by the Government and the amount agreed upon by the Contractor and the Contracting Officer for (1) completed work for which no separate price is stated, (ii) partially completed work, (iii) other property described above which is accepted by the Government and, (iv) the protection and preservation of property. Failure to agree shall be a dispute concerning a question

7-302.9

ARMED SERVICES PROCUREMENT REGULATION

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

of fact within the meaning of the clause of this contract entitled "Disputes". The Government may withhold from amounts otherwise due the Contractor for such completed supplies or manufacturing materials such sum as the Contracting Officer determines to be necessary to protect the Government against loss because of outstanding liens or claims of former lien holders.

(e) If, after notice of termination of this contract under the provisions of this clause, it is determined for any reason that the Contractor was not in default under the provisions of this clause, and if this contract does not contain a clause providing for termination for convenience of the Government, the contract shall be equitably adjusted to compensate for such termination and the contract modified accordingly; failure to agree to any such adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled “Disputes."

(f) The rights and remedies of the Government provided in this clause shall not be exclusive and are in addition to any other rights and remedies provided by law or under this contract. (g) As used in paragraph (c) of this clause, the terms "subcontractor" and "subcontractors" mean subcontractor(s) at any tier.

(End of clause)

7-302.10 Termination for Convenience of the Government.

(a) In accordance with 8-701, insert the clause in 7-103.21(b). (b) In accordance with 8-704.1(a), insert the following clause.

TERMINATION FOR THE CONVENIENCE OF THE GOVERNMENT (1973 APR)

(a) The performance of work under this contract may be terminated, in whole or from time to time in part, by the Government whenever for any reason the Contracting Officer shall determine that such termination is in the best interest of the Government. Termination of work hereunder shall be effected by delivery to the Contractor of a Notice of Termination specifying the extent to which performance of work under the contract is terminated and the date upon which such termination becomes effective.

(b) After receipt of the Notice of Termination the Contractor shall cancel his outstanding commitments hereunder covering the procurement of materials, supplies, equipment and miscellaneous items. In addition the Contractor shall exercise all reasonable diligence to accomplish the cancellation or diversion of his outstanding commitments covering personal services and extending beyond the date of such termination to the extent that they relate to the performance of any work terminated by the notice. With respect to such canceled commitments the Contractor agrees to (i) settle all outstanding liabilities and all claims arising out of such cancellation of commitments, with the approval or ratification of the Contracting Officer, to the extent he may require, which approval or ratification shall be final for all purposes of this clause, and (ii) assign to the Government, in the manner, at the time, and to the extent directed by the Contracting Officer, all of the right, title, and interest of the Contractor under the orders and subcontracts so terminated, in which case the Government shall have the right, in its discretion, to settle or pay any or all claims arising out of the termination of such orders and subcontracts.

(c) The Contractor shall submit his termination claim to the Contracting Officer promptly after receipt of a Notice of Termination, but in no event later than one year from the effective date thereof, unless one or more extensions in writing are granted by the Contracting Officer upon written request of the Contractor within such one year period or authorized extension thereof. Upon failure of the Contractor to submit his termination claim within the time allowed, the Contracting Officer may determine, on the basis of information available to him, the amount, if any, due to the Contractor by reason of the termination and shall thereupon pay to the Contractor the amount so determined.

(d) Any determination of costs under paragraph (c) shall be governed by the cost principles set forth in Section XV, Part 3, of the Armed Services Procurement Regulation, as in effect on the date of this contract.

(e) Subject to the provisions of paragraph (c) above, the Contractor and the Contracting Officer may agree upon the whole or any part of the amount or amounts to be paid to the Contractor by reason of the termination under this clause, which amount or amounts may include any reasonable cancellation charges thereby incurred by the Contractor and any reasonable loss upon

7-302.10

ARMED SERVICES PROCUREMENT REGULATION

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

outstanding commitments for personal services which he is unable to cancel; provided, however, that in connection with any outstanding commitments for personal services which the Contractor is unable to cancel, the Contractor shall have exercised reasonable diligence to divert such commitments to his other activities and operations. Any such agreement shall be embodied in an amendment to this contract and the Contractor shall be paid the agreed amount.

(f) The Government may from time to time, under such terms and conditions as it may prescribe, make partial payments against costs incurred by the Contractor in connection with the terminated portion of this contract, whenever, in the opinion of the Contracting Officer, the aggregate of such payments is within the amount to which the Contractor will be entitled hereunder. (g) The Contractor agrees to transfer title and deliver to the Government, in the manner, at the time, and to the extent, if any, directed by the Contracting Officer, such information and items which, if the contract had been completed, would have been required to be furnished to the Government, including:

(i) completed or partially completed plans, drawings and information; and

(ii) materials or equipment produced or in process or acquired in connection with the performance of the work terminated by the notice.

Other than the above, any termination inventory resulting from the termination of the contract may, with the written approval of the Contracting Officer, be sold or acquired by the Contractor under the conditions prescribed by and at a price or prices approved by the Contracting Officer. The proceeds of any such disposition shall be applied in reduction of any payments to be made by the Government to the Contractor under this contract or shall otherwise be credited to the price or cost of work covered by this contract or paid in such other manner as the Contracting Officer may direct. Pending final disposition of property arising from the termination, the Contractor agrees to take such action as may be necessary, or as the Contracting Officer may direct, for the protection and preservation of the property related to this contract which is in the possession of the Contractor and in which the Government has or may acquire an interest.

(h) Any disputes as to questions of fact which may arise hereunder shall be subject to the "Disputes" clause of this contract.

(End of clause)

(c) In accordance with 8-704.1(b), insert the following clause:

TERMINATION FOR THE CONVENIENCE OF THE GOVERNMENT ALTERNATE (1974

APR)

(a) The performance of work under this contract may be terminated, in whole or from time to time in part, by the Government whenever for any reason the Contracting Officer shall determine that such termination is in the best interest of the Government. Termination of work hereunder shall be effected by delivery to the Contractor of a Notice of Termination specifying the extent to which performance of work under the contract is terminated and the date upon which such termination becomes effective.

(b) After receipt of the Notice of Termination the Contractor shall cancel his outstanding commitments hereunder covering the procurement of materials, supplies, equipment and miscellaneous items. In addition the Contractor shall exercise all reasonable diligence to accomplish the cancellation or diversion of his outstanding commitments covering personal services and extending beyond the date of such termination to the extent that they relate to the performance of any work terminated by the notice. With respect to such canceled commitments the Contractor agrees to (i) settle all outstanding liabilities and all claims arising out of such cancellation of commitments, with the approval or ratification of the Contracting Officer, to the extent he may require, which approval or ratification shall be final for all purposes of this clause, and (ii) assign to the Government, in the manner, at the time, and to the extent directed by the Contracting Officer, all of the right, title, and interest of the Contractor under the orders and subcontracts so terminated, in which case the Government shall have the right, in its discretion, to settle or pay any or all claims arising out of the termination of such orders and subcontracts.

(c) The Contractor shall submit his termination claim to the Contracting Officer promptly after receipt of a Notice of Termination, but in no event later than one year from the effective date

7-302.10

ARMED SERVICES PROCUREMENT REGULATION

CONTRACT CLAUSES AND SOLICITATION PROVISIONS thereof, unless one or more extensions in writing are granted by the Contracting Officer upon written request of the Contractor within such one year period or authorized extension thereof. Upon failure of the Contractor to submit his termination claim within the time allowed, the Contracting Officer may determine, on the basis of information available to him, the amount, if any, due to the Contractor by reason of the termination and shall thereupon pay to the Contractor the amount so determined.

(d) Costs claimed, agreed to, or determined pursuant to (c) above and (e) below shall be in accordance with the Section XV Contract Cost Principles and Procedures of the Armed Services Procurement Regulation as in effect on the date of this contract.

(e) Subject to the provisions of paragraph (c) above, the Contractor and the Contracting Officer may agree upon the whole or any part of the amount or amounts to be paid to the Contractor by reason of the termination under this clause, which amount or amounts may include any reasonable cancellation charges thereby incurred by the Contractor and any reasonable loss upon outstanding commitments for personal services which he is unable to cancel, provided, however, that in connection with any outstanding commitments for personal services which the Contractor is unable to cancel, the Contractor shall have exercised reasonable diligence to divert such commitments to his other activities and operations. Any such agreement shall be embodied in an amendment to this contract and the Contractor shall be paid the agreed amount.

(f) The Government may from time to time, under such terms and conditions as it may prescribe, make partial payments against costs incurred by the Contractor in connection with the terminated portion of this contract, whenever, in the opinion of the Contracting Officer, the aggregate of such payments is within the amount to which the Contractor will be entitled hereunder. (g) The Contractor agrees to transfer title and deliver to the Government, in the manner, at the time, and to the extent, if any, directed by the Contracting Officer, such information and items which, if the contract had been completed, would have been required to be furnished to the Government, including:

(i) completed or partially completed plans, drawings and information; and

(ii) materials or equipment produced or in process or acquired in connection with the performance of the work terminated by the notice.

Other than the above, any termination inventory resulting from the termination of the contract may, with the written approval of the Contracting Officer, be sold or acquired by the Contractor under the conditions prescribed by and at a price or prices approved by the Contracting Officer. The proceeds of any such disposition shall be applied in reduction of any payments to be made by the Government to the Contractor under this contract or shall otherwise be credited to the price or cost of work covered by this contract or paid in such other manner as the Contracting Officer may direct. Pending final disposition of property arising from the termination, the Contractor agrees to take such action as may be necessary, or as the Contracting Officer may direct, for the protection and preservation of the property related to this contract which is in the possession of the Contractor and in which the Government has or may acquire an interest.

(h) Any disputes as to questions of fact which may arise hereunder shall be subject to the "Disputes" clause of this contract.

(End of clause)

(d) The clause in (b) above suitably altered to indicate the relationship between the prime contractor and subcontractor is suggested for use in subcontracts placed with educational institutions and when modified as prescribed in (c) above for use with other nonprofit institutions; provided, such subcontracts incorporate, or are negotiated on the basis of, the cost principles set forth in Section XV; and provided further, such subcontracts are placed on the no-fee or no-profit basis.

7-302.11 Disputes. In accordance with 7-103.12, insert the clause therein. 7-302.12 Renegotiation. In accordance with 7-103.13, insert the appropriate clause therein.