Contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, in either its sovereign or contractual capacity, a,cts of another contractor in the performance of a contract with the Government, fires, floods,... Code of Federal Regulations: Containing a Codification of Documents of ... - Page 2241979Full view - About this book
| United States. Court of Claims - Law reports, digests, etc - 1948 - 974 pages
...restricted to, acts of God, or of the public enemy, acts of the Government, acts of another contractor in the performance of a contract with the Government,...unusually severe weather or delays of subcontractors due to such causes, if the contractor shall within 10 days from the beginning of any such delay (unless... | |
| United States. Court of Claims - Law reports, digests, etc - 1946 - 906 pages
...God, or of the public enemy, acts of the Government, acts of another contractor in the perfonnance of a contract with the Government, fires, floods,...unusually severe weather or delays of subcontractors due to such causes, if the contractor shall within 10 days from the beginning of any such delay (unless... | |
| United States. Court of Claims - Law reports, digests, etc - 1944 - 656 pages
...negligence of the contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine...unusually severe weather or delays of subcontractors due to such causes: Provided further, That the contractor shall within ten days from the beginning... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1956 - 1104 pages
...(including, but not restricted to, any preference, priority or allocation order), acts of another contractor in the performance of a contract with the Government,...quarantine restrictions, strikes, freight embargoes, and unusuallv severe weather or delays of subcontractors due to such causes, if the contractor shall within... | |
| United States. Court of Claims - Law reports, digests, etc - 1948 - 886 pages
...Governmental preferences, priorities or allocations of equipment or material) , acts of another Contractor in the performance of a contract with the Government,...quarantine restrictions, strikes, freight embargoes, unusually severe weather, or delays of subcontractors or material suppliers due to such causes (unless... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1952 - 1040 pages
...allocation order, acts of another contractor In the performance of a contract with the Government, flres, floods, epidemics, quarantine restrictions, strikes,...unusually severe weather or delays of subcontractors due to such causes, if the contractor shall within 10 days from the beginning of any such delay (unless... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1950 - 1004 pages
...(including, but not restricted to, any preference, priority or allocation order), acts of another contractor in the performance of a contract with the Government,...floods, epidemics, quarantine restrictions, strikes * * *. ARTICLE 13. Other contracts. — The Government may award other contracts for additional work,... | |
| United States. General Accounting Office - Finance, Public - 1950 - 710 pages
...restricted to, acts of God, or of the public enemy, acts of the Government, acts of another contractor in the performance of a contract with the Government,...unusually severe weather or delays of subcontractors due to such causes, if the contractor shall within 10 days from the beginning of any such delay (unless... | |
| United States. General Accounting Office - Finance, Public - 1944 - 1220 pages
...These it describes as "including, but not restricted to, acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine...unusually severe weather, or delays of subcontractors due to such causes." The purpose of the proviso to protect the contractor against the unexpected, and... | |
| United States. Congress. House. Committee on Appropriations - 1928 - 970 pages
...of the contractor, including, "but not restricted to. acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine...unusually severe weather or delays of subcontractors due to such causes: Provided, That the contractor shall within ten days from the beginning of any such... | |
| |