and after January 1, 1978, and only during such time, the Commission may review any such project which has been identified by the Executive Director as having special flood hazards, and:

(1) Is located along the mainstem Delaware River or a major tributary thereof, or

(2) An agency of a signatory party requests such review.

$415.41 Special permits.

A special permit may be granted, or granted on stated conditions, provided:

(a) There is a clear balance in favor of the public interest in terms of the following environmental criteria:

(1) The importance of a facility to the community.

(2) The availability of alternative locations not subject to flooding for the proposed use.

(3) The compatibility of the proposed use with existing development and development anticipated in the foreseeable future.

(4) The relationship of the proposed use to any applicable comprehensive plan or flood plain management program for the area.

(5) The safety of access to the property in times of flood for ordinary and emergency vehicles.

(6) The expected heights, velocity, duration, rate of rise and sediment transport of the flood water expected at the site.

(7) The degree to which the proposed activity would alter natural water flow or water temperature.

(8) The degree to which archaeological or historic sites and structures, endangered or rare species of animals or plants, high quality wildlife habitats, scarce vegetation types, and other irreplaceable land types would be degraded or destroyed.

(9) The degree to which the natural, scenic and aesthetic values at the proposed activity site could be retained. (b) The project shall not: (1) Endanger human life.

(2) Have high flood damage potential. (3) Obstruct flood flows nor increase flood heights or velocities unduly whether acting alone or in combination with other uses.

(4) Degrade significantly the water carrying capacity of any delineated floodway or channel.

(5) Increase significantly the rate of local runoff, erosion, or sedimentation. (6) Degrade significantly the quality of surface water or the quality or quantity of ground water.

(7) Be susceptible to flotation.

(8) Have service facilities installed below the elevation of the regulatory flood without being adequately flood proofed.

$415.42 Technical standards.

(a) Standards used by state and local governments shall conform in principle to Commission standards but may vary in detail provided that resulting flood plain use will not be less restrictive than would result from the application of Commission standards. The Commission will review proposed state and local flood plain regulations to determine their compliance with Commission standards.

(b) Because of the variety and diversity of presently recognized hydrologic procedures, no one procedure or method is prescribed for determining the peak flow in cubic feet per second for the 100-year storm (Q 100) on which profiles for the delineation of flood hazard areas are based. The following may be used:

(1) A uniform Technique for Determining Flood Flow Frequencies-Bulletin No. 15-Water Resources Council, December 1967.

(2) Basin-Wide Program for Flood Plain Delineation-Delaware River Basin Commission-Anderson-Nichols & Co., Inc., June 1973.

(3) Magnitude and Frequency of Floods in New Jersey with Effects of Urbanization-Special Report 38 U.S.G.S.-New Jersey Department of Environmental Protection, 1974.

(4) Guidelines for Determining Flood Flow Frequency-Bulletin No. 17— Water Resources Council, March 1976. State and local agencies may use methods resulting in Q 100s which are in reasonable agreement with those of the Commission. Any significant difference shall be reviewed with and subject to approval by the Executive Director.

(c) Methods and procedures shall be uniform, so far as practicable, within

sub-basins which have a major effect on the larger basins of which they are a part. To assist in achieving this objective the Commission staff will periodically provide to the various interested governmental agencies and others Q 100 data as developed by the Delaware River Basin Commission Hydrology Coordinating Committee for key locations in the Delaware River Basin. These will be based on a Log Pearson Type 3 analysis of data from the U.S.G.S. gaging stations using station skew, regional skew, or weighted skew, depending on the scope of data at each station.

§ 415.43 Mapped and unmapped delineations.

(a) Whenever an official flood plain map providing the pertinent information is available with respect to a given project, the map shall be used for the delineation of the flood hazard area, floodway, flood fringe and determination of flood protection elevation.

(b) Whenever an official flood plain map providing the required information is not available with respect to a given project, the administrative agency shall require the project landowner to submit details concerning the proposed uses as needed to determine the floodway and flood fringe limits at the proposed site, including: cross-sections of the stream channel and overbanks, stream profile, and factors involved in determining obstructions to flow. From the data submitted, soil surveys, historic flood maps, high water marks and other empirical data, the applicant, subject to verification by the administrative agency, shall calculate flood hazard areas, and establish the flood protection elevation for the particular site.

(c) Pending the preparation and completion of flood plain mapping, a “general flood plain" area shall be prescribed by the administrative agency to delineate for public guidance the areal limits of site locations which are required to be submitted for review under this regulation.

[blocks in formation]

(a) The flood hazard at the site is clear, present and significant, or the local government having jurisdiction has special flood hazard areas identified pursuant to the National Flood Insurance Act; and

(b) The site is not subject to an approved state or municipal regulatory system having the same or similar effect on the flood hazard as this regulation, the Commission may condition its approval on any local governmental project under section 3.8 of the Compact upon the adoption and enforcement of flood plain regulations, approved hereunder, by the state or local government having jurisdiction.

§ 415.51 Prior non-conforming structures.

A structure which was lawful before the adoption of this regulation but which is not in conformity with the provisions hereof, shall be subject to the following conditions (to be enforced by the appropriate authority as to Class I and Class II projects, respectively, under §§ 415.40 through 415.43 of this part):

(a) A non-conforming structure in the floodway may not be expanded, except that it may be modified, altered or repaired to incorporate flood proofing measures provided such measures do not raise the level of the 100-year flood.

(b) A non-conforming structure in the floodway which is destroyed or damaged by any means, including a flood, to the extent of 50 percent or more of its market value at that time may not be restored, repaired, reconstructed or improved except in conformity with the provisions of these regulations.

[blocks in formation]

420.22 Prohibition; sanctions.

420.23 Exempt uses under the Compact. 420.24 Effective date of rates.

ENTITLEMENT; MEASUREMENT; BILLING

420.31 Certificate of entitlement. 420.32 Measurement and billing of water

taken.

420.33 Payment of bills.

CHARGES; EXEMPTIONS

420.41 Schedule of water charges. 420.42 Contracts; minimum charge.

420.43 Exempt use.

420.44 Cooling water.

420.45 Historical use.

HYDROELECTRIC POWER WATER USE CHARGES 420.51 Hydroelectric power plant water use

charges.

AUTHORITY: Delaware River Basin Compact, 75 Stat. 688.

SOURCE: 42 FR 13544, Mar. 11, 1977, unless otherwise noted.

GENERAL

§ 420.1 Definitions.

For the purposes of this part 420, except as otherwise required by the context:

Person means any person, corporation, partnership, association, trust, or other entity, public or private.

Water user means any person who uses, takes, withdraws or diverts surface waters within the Delaware River Basin.

Executive Director means the Executive Director of the Delaware River Basin Commission.

Consumptive use means the water lost due to transpiration from vegetation in the building of plant tissue, incorporated into products during their manufacture, lost to the atmosphere from cooling devices, evaporated from water surfaces, exported from the Delaware River Basin, or any other water use for which the water withdrawn is not returned to the surface waters of the basin undiminished in quantity.

WATER SUPPLY POLICY

§ 420.21 Policy.

The provisions of this part 420 implement Commission Resolution No. 71-4 (Comprehensive Plan) relating to water supply charges.

§ 420.22 Prohibition; sanctions.

or

Any person, firm, corporation other entity, including a public corporation, body or agency, who shall use, withdraw or divert surface waters of the basin, shall pay such charges therefor as may be required by this resolution. Any violation of this resolution shall be subject to penalty as prescribed under Article 14.17 of the Compact. The Commission may also recover the value (according to the established water pricing schedules of the Commission) of any such use, withdrawal or diversion, and invoke the jurisdiction of the courts to enjoin any further use, withdrawal or diversion, unless all charges under this resolution are paid in full when due.

§ 420.23 Exempt uses under the Compact.

(a) Section 15.1(b) of the Delaware River Basin Compact provides that "no provision of section 3.7 of the Compact shall be deemed to authorize the Commission to impose any charge for water withdrawals or diversions from the basin if such withdrawals or diversions could lawfully have been made without charge on the effective date of the

Compact; * * *'' In compliance with this provision: There shall be no charge for water withdrawn or diverted in quantities not exceeding the legal entitlement of the user, determined as of October 27, 1961. Each water user may submit proof satisfactory to the Commission of the factors constituting legal entitlement, as defined in paragraph (b) thereof. In the absence of such proof of these conditions as of October 27, 1961, the quantity of water exempt from charge to each user will be the legal entitlement of the user determined as of March 31, 1971.

(b) For the purposes of paragraph (a) of this section:

(1) Legal entitlement means the quantity or volume of water expressed in million gallons per month determined by the lesser of the following conditions:

(i) A valid and subsisting permit, issued under the authority of one of the signatory parties, if such permit was required as of October 27, 1961, or thereafter;

(ii) Physical capability as required for such taking; or

(iii) The total allocable flow without augmentation by the Commission, using a seven-day, ten-year, low-flow criterion measured at the point of withdrawal or diversion.

(2) Physical capability means the capacity of pumps, water lines and appurtenances installed and operable, determined according to sound engineering principles. The physical capability specifically includes plant facilities actually using water, but excludes facilities which may have been installed in anticipation of future plant expansion not yet realized.

(c) Whenever adequate records of legal entitlement for agricultural irrigation purposes are not available to the Commission, such legal entitlement shall be measured by the maximum number of acres under irrigation by the water user at any time during the year ending March 31, 1971, allowing one acre-foot of surface water annually per acre irrigated.

(d) Notwithstanding the provisions of paragraphs (a), (b) and (c) of this section, there shall be no charge for water made available from storage where:

(1) The cost of the storage facility has or will be otherwise paid for by the user,

(2) Such storage controls a drainage area, and

(3) The use does not exceed the yield of such storage without augmentation from other surface water of the basin.

$420.24 Effective date of rates.

Rates and charges shall apply to all water users not exempt hereunder on and after the date of the first impoundment of water for water supply purposes at the Beltzville Reservoir (February 8, 1971), or the effective date hereof, whichever is later.

ENTITLEMENT; MEASUREMENT; BILLING

§ 420.31 Certificate of entitlement.

(a) The Executive Director will issue to each known water user a certificate of entitlement within 30 days after the effective date of these regulations subject to the provisions of paragraph (b). In addition, any other water user may apply for a certificate of entitlement

at any time. A preliminary notice of entitlement shall be issued to each user. Such entitlement shall become final and take effect, unless the user shall file with the Commission, within 20 days after the service of the notice of entitlement, a request for hearing by the Commission. At such hearing the water user may show cause why the proposed entitlement shall not take effect.

(b) The Executive Director shall schedule a hearing to be held not less than ten days after receipt of a request for a hearing by the Commission. Hearings shall be conducted and the results thereof subject to review in accordance with Article 5 of the Commission's rules of practice and procedure.

(c) A final certificate of entitlement will be issued either upon expiration of the time to request a hearing, where there has been no request, or in accordance with the determination of a hearing where one is held.

(d) A certificate of entitlement is not transferable, except as provided in paragraphs (e) and (f) of this section. For the purposes of this section, transfer shall mean any sale or other conveyance by a holder of a certificate of entitlement involving a specific facility and shall include any transfer which results in a change of ownership and/or control of the facility or of the stock, or other indicia of ownership of a corporation which holds title to the facility.

(e) Whenever ownership or possession of land in agricultural use is transferred, a certificate of entitlement with respect to such land shall be deemed to run with the land, so long as the water use continues to be for agricultural irrigation. Upon any such land transfer, the Executive Director will reissue a certificate of entitlement to the new user.

(f) A certificate of entitlement may be transferred in connection with a corporate reorganization within any of the following categories:

(1) Whenever property is transferred to a corporation by one or more persons solely in exchange for stock or securities of the same corporation, provided that immediately after the exchange the same person or persons are

in control of the transferee corporation; that is, they own 80 percent of the voting stock and 80 percent of all other stock of the corporation; or

(2) Where such transfer is merely a result of a change of the name, identify, internal corporate structure or place of organization of a corporate holder of a certificate of entitlement and does not affect ownership and/or control.

[42 FR 13544, Mar. 11, 1977, as amended at 59 FR 64571, Dec. 15, 1994]

§ 420.32 Measurement and billing of water taken.

(a) The quantity and volume of waters used by each person shall be determined by meters, or other methods approved by the Commission, installed, maintained and read by or on behalf of the taker. Meters or other methods of measurement shall be subject to approval and inspection by the Commission as to installation, maintenance and reading.

(b) Each user of surface water who is not exceeding the quantity specified in his "certificate of entitlement" shall annually, on or before January 31, file with the Commission, on a form to be prescribed by the Executive Director, a report of the user's physical capability, as defined, permit limitations, and the volume of water used during the preceding year.

(c) Each user of surface water who is taking a quantity of water greater than the amount specified in his "certificate of entitlement" shall report his usage to the Commission on or before April 30, July 31, October 31 and January 31, of each year covering the next preceding calendar quarter, respectively, on forms to be prescribed by the Executive Director. The amount due for water usage in excess of the legal entitlement for each of the first three quarters of a calendar year shall be computed and paid by the user, together with the report.

(d) The Commission will render a statement of the net amount due based on the fourth quarter report, including a negative or positive adjustment, so that the net total billing and payment for four quarters will equal the total water used during the four quarters

less the user's legal entitlement, if any.

§ 420.33 Payment of bills.

The amount due for each quarter shall bear interest at the rate of 1 percent per month for each day it is unpaid beginning 30 days after the due date of the quarterly report for the first three quarters and 30 days after the bill is rendered for the fourth quarter.

CHARGES; EXEMPTIONS

§ 420.41 Schedule of water charges.

The Commission will from time to time, after public notice and hearing, make, amend and revise a schedule of water charges. Until changed, the charge for water shall be as follows:

(a) Six cents per thousand gallons for consumptive use; and

(b) Six-tenths of a mill per thousand gallons for nonconsumptive use.

[42 FR 13544, Mar. 11, 1977, as amended at 43 FR 56655, Dec. 4, 1978]

§ 420.42 Contracts; minimum charge.

Subject to the exclusions for certificates of entitlement and exempt uses, the Executive Director may require contracts for any taking, use, withdrawal or diversion of waters of the basin. Each contract shall provide for a minimum annual payment in accordance with an estimated annual demand schedule, regardless of use, withdrawal or diversion. The failure of any person to execute a contract under this section shall not affect the application of other requirements of this resolution. § 420.43 Exempt use.

The following uses shall be exempt from charge:

(a) Non-consumptive uses of less than 1,000 gallons during any day, and less than 100,000 gallons during any quarter. (b) Ballast water used for shipping purposes.

(c) Water taken, withdrawn or diverted from streams tributary to the river master's gauging station at Montague.

(d) Water taken, withdrawn or diverted below R.M. 38 (the mouth of the Cohansey River) and such proportion of waters taken, diverted or withdrawn