" Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however, That the Contracting Officer, if he decides that the facts justify... "
The Code of Federal Regulations of the United States of America - Page 386
1972
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 154

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1968 - 922 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the...receive and act upon any such claim asserted at any time/prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 141

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1959 - 1028 pages
...in writing within 30 days from the date of receipt by the Contractor of the notification of extra or change : Provided, however, That the Contracting Officer,...upon any such claim asserted at any time prior to the date of final settlement of the contract. If the parties fail to agree upon the adjustment to be...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1972 - 914 pages
...cost or delivery schedule, or both, (2) In the amount of any fee to be paid to the Contractor, and (3) In such other provisions of the contract as may be...to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of thla contract entitled "Disputes". However, nothing...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1972 - 914 pages
...cost or delivery schedule, or both, (2) in the amount of any fee to be paid to the Contractor, and (3) in such other provisions of the contract as may be...contract. Failure to agree to any adjustment shall bea dispute concerning a question of fact within the meaning of the clause of this contract entitled...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1971 - 850 pages
...cost or delivery schedule, or both, (2) In the amount of any fee to be paid to the Contractor, and (3) in such other provisions of the contract as may be...asserted at any time prior to final payment under thla contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1975 - 172 pages
...order, an equitable adjustment shall be made (1) In the price or delivery schedule, or both and (2) in such other provisions of the contract as may be...receive and act upon any such claim asserted at any tune prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1975 - 1236 pages
...claims by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor of the...to any adjustment shall be a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract However, nothing in this...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1982 - 532 pages
...Contractor for adjustment under this clause must be asserted within thirty (30) days from the date or receipt by the Contractor of the notification of change;...to any adjustment shall be a dispute concerning a question of fact within, the meaning of the "Disputes" clause of this contract. However, nothing in...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1983 - 1974 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within thirty (3U) days from the date of receipt by the Contractor of the...contract. Failure to agree to any adjustment shall he a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract....
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1964 - 676 pages
...writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within (60) days from the date of receipt by the Contractor...final payment under this contract. Failure to agree at any adjustment shall be a dispute concerning a question of fact within the meaning of the clause...