Sluice about 14 miles below dam.

Estimate for construction of all-American canal of capacity to serve the Imperial irrigation district and additional mesa lands with 1,600 second-feet additional capacity for Yuma project down to siphon drop

LAGUNA DAM TO SIPHON DROP, CANAL CAPACITY OF 10,600 SECOND-FEET

Excavation:

Earth, 5,045,000 cubic yards, at 20 cents.
Rock, 754,600 cubic yards, at 75 cents. -

Total...

15 per cent contingency._

Structures:

Alterations at Laguna Dam___

[blocks in formation]

Turnout reservation canal..

Check below turnout reservation canal.

10, 500

Picacho road bridge.

27,500

Raising siphon drop

34, 000

Walapai lateral turnout_

Check below siphon drop.

Paved overflow for receiving storm waters into the

canal__

10 miles of telephone line..

Total__

20, 000

7, 100 22, 000

20,000
2,250

1, 128, 350

15 per cent contingency.

169, 252

Cost of connecting with Laguna Dam (estimated
under contract of Oct. 23, 1918)...

1,297, 602

1,900,000

Total_--

5, 008, 794

SIPHON DROP TO ARAZ, 9,000 SECOND-FEET CANAL

Earth, 2,600,000 cubic yards, at 20 cents.

Earth fill (raising railroad grade), 30,000 cubic yards, at

$520,000

30 cents...

Raising and ballasting track 1 mile..

9, 000

Concrete lining 4,400 feet of canal along railroad track 4 inches thick, 950,000 square feet, at 17 cents...

6, 000

[blocks in formation]

Paved overflow for receiving storm waters into the
canal..

34, 000

[blocks in formation]

ARAZ TO UPPER POWER SITE, PILOT KNOB, OPPOSITE ROCKWOOD GATE, 9,000 SECONDFOOT CANAL

Excavation:

Earth, 805,000 cubic yards, at 20 cents_

$161, 000

Rock, 145,000 cubic yards, at 75 cents.

108, 750

Concrete lining 400 feet canal, 86,400 square feet, at

17 cents..

14, 688

[blocks in formation]

UPPER POWER SITE, PILOT KNOB, OPPOSITE ROCKWOOD GATES, TO PILOT KNOB, 9,000 SECOND-FOOT CANAL

[blocks in formation]

PILOT KNOB TO EAST SIDE MESA CANAL NO. 1 (STATION 1525) 9,000 SECOND FOOT CANAL
Excavation:

Earth, 46,736,000 cubic yards, at 30 cents.
Earth, 1,770,000 cubic yards, at 20 cents..
Blow sand, 500,000 cubic yards, at 30 cents..
Rock, 312,000 cubic yards, at 75 cents.

Total___

15 per cent contingency.

Structures:

East mesa canal No. 1 turnout.

$14, 020, 800

354, 000

150, 000

234, 000

[blocks in formation]

Drop and check___

26 miles telephone line.

Total

15 per cent contingency..

Total

$16, 972, 620

24, 000

52, 000

5, 850

81, 850

12, 277

94, 127

17, 066, 747

3 Structures to be located at place selected for power site or permanent wasteway (see Power develop¡ment, p. 97).

Estimate of amount of sand that will blow in during construction.

MESA CANAL NO. 1 TO MESA CANAL NO. 2, 6,000 SECOND-FOOT CANAL

[blocks in formation]

MESA CANAL NO. 2 TO WEST-SIDE MAIN CANAL, 5,500 TO 1,500 SECOND-FOOT CANAL Excavation:

[blocks in formation]

DIVISION OF COST

1. Between the Yuma project for power development
and the Imperial irrigation district, including the new
lands:

Laguna Dam to siphon drop - -
Siphon drop to Araz...

[blocks in formation]
[blocks in formation]

Estimate for construction of all-American canal of capacity to serve the Imperial irrigation district with 1,600 second-feet additional capacity for Yuma project down to siphon drop

FIRST ALTERNATIVE: PILOT KNOB TO MESA CANAL NO. 1, 9,000 SECOND-FOOT CANAL

A first alternative estimate was made to provide a concrete-lined section through the sand hills. The concrete lining is to be 4 inches thick and extend 2 feet above the high-water line. The following are the principal hydraulic functions:

[blocks in formation]
[blocks in formation]

SECOND ALTERNATIVE: PILOT KNOB TO MESA CANAL NO. 1, 10,600 SECOND-FOOT

CANAL

A second alternative estimate was made to provide a concrete-lined section through the sand hills, but with a deeper section than the first alternative estimate, in order to give an additional capacity of 1,600 second-feet. The concrete lining is to be 4 inches thick and extend 2 feet above the high-water line. following are the principal hydraulic functions:

The

[blocks in formation]

The above alternative estimates include the extra excavation from the west side of the sand hills to station 1575, due to the canal being in deeper cut because of the increased slope of the concrete-lined section. The 6-foot drop at station 1575 will just be eliminated by the greater gradient. This, however, will lower the elevation of the east mesa canal No. 1, 6 feet, and thus eliminate a certain acreage on the east-side mesa that can not be served by gravity. It will also reduce the possible head at mesa power station No. 1 from 30 to 24 feet. Alternative No. 1 decreases the cost, $120,451 over a canal built in an earth section. Alternative No. 2 increases the cost $969,841 over a canal built in an earth section. The estimated cost of the other sections of the canal will remain

Estimated amount of sand that will blow in during construction.