" Contractor shall not be liable for any excess costs if the failure to perform the contract arises out of causes beyond the control and without the fault or negligence of the Contractor. Such causes may include, but are not restricted to, acts of God or... "
The Code of Federal Regulations of the United States of America - Page 79
2005
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 111

United States. Court of Claims - Law reports, digests, etc - 1948 - 886 pages
...unforeseeable causes beyond the control and without the fault or negligence of the contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 92

United States. Court of Claims - Law reports, digests, etc - 1941 - 708 pages
...contractor, including, but not restricted to, acts of God or the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions,...freight embargoes, and unusually severe weather but not including delays caused by subcontractors: Provided furthei\ That the contractor shall, within...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 132

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1955 - 936 pages
...component parts listed in Part IV of Exhibit A are omitted only because of circumstances (including but not restricted to acts of God or of the public enemy, acts or orders of Government, floods, fire, strikes, freight embargoes, or unavailability or delay in delivery...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 118

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1951 - 840 pages
...of the Government, acts of another Contractor in the performance of a contract with the Government, fires, floods, epidemics, quarantine restrictions,...strikes, freight embargoes, and unusually severe weather or delays of subcontractors due to such causes, if the Contractor shall within 10 days from the beginning...
Full view - About this book

Decisions of the Comptroller General of the United States, Volume 29

United States. General Accounting Office - Finance, Public - 1950 - 710 pages
...unforeseeable causes beyond the control and without the fault or negligence of the contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics,...
Full view - About this book

Treasury Department Appropriation Bill for 1929: Hearing Before the ...

United States. Congress. House. Committee on Appropriations - 1928 - 970 pages
...unforeseeable causes beyond the control and without the fault or negligence of the contractor, including, "but not restricted to. acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe...
Full view - About this book

To Establish Uniform Requirements for Government Contracts: Hearing Before ...

United States. Congress. House. Committee on the Judiciary - Government purchasing - 1928 - 228 pages
...unforeseeable causes beyond the control and without the fault or negligence of the contractor, including, but not restricted to, acts of God or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe...
Full view - About this book

Hearings, Volume 2

United States. Congress. House. Committee on Appropriations - 1970 - 1848 pages
...unforeseeable causes beyond the control and without the fault or negligence of such party, Including, but not restricted to, acts of God, or of the public enemy, acts of the Government of the United States or the Government of American Samoa, in either sovereign or contractual capacity,...
Full view - About this book

Specifications, Schedule, and Drawings: Hoover Dam, Power Plant and ...

United States. Bureau of Reclamation - Hoover Dam (Ariz. and Nev.) - 1930 - 132 pages
...unforeseeable causes beyond the control and without the fault or negligence of the contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe...
Full view - About this book

Decisions of the Comptroller General of the United States, Volume 9

United States. General Accounting Office - Finance, Public - 1930 - 608 pages
...contractor, including, but not restricted to, acts of God or the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions,...freight embargoes, and unusually severe weather, but not including delays caused by subcontractors: Provided furthei; That the contractor shall, within...
Full view - About this book