where a portion of the risk has been shifted to the Government through cost-reimbursement provisions, unusual contingency provisions, or other risk-reducing measures, the amount of profit should be less than where the contractor assumes all the risk.

(A) In developing the prenegotiation profit objective, the contracting officer will need to consider the type of contract anticipated to be negotiated and the contractor risk associated therewith when selecting the position in the weight range for profit that is appropriate for the risk to be borne by the contractor. This factor should be one of the most important in arriving at prenegotiation profit objective. Evaluation of this risk requires a determination of the degree of cost responsibility the contractor assumes; the reliability of the cost estimates in relation to the task assumed; and the complexity of the task assumed by the contractor. This factor is specifically limited to the risk of contract costs. Thus, risks on the part of the contractor such as reputation, losing a commercial market, risk of losing potential profits in other fields, or any risk which falls on the contracting office, such as the risk of not acquiring a satisfactory report, are not within the scope of this factor.

(B) The first and basic determination of the degree of cost responsibility assumed by the contractor is related to the sharing of total risk of contract cost by the Government and the contractor through the selection of contract type. The extremes are a costplus-a-fixed-fee contract requiring the contractor to use its best efforts to perform a task and a firm fixed-price contract for a service or a complex item. A cost-plus-a-fixed-fee contract would reflect a minimum assumption of cost responsibility, whereas a firmfixed-price contract would reflect a complete assumption of cost responsibility. Where proper contract selection has been made, the regard for risk by contract type would usually fall into the following percentage ranges:

(C) The second determination is that of the reliability of the cost estimates. Sound price negotiation requires welldefined contract objectives and reliable cost estimates. Prior experience assists the contractor in preparing reliable cost estimates on new acquisitions for similar related efforts. An excessive cost estimate reduces the possibility that the cost of performance will exceed the contract price, thereby reducing the contractor's assumption of contract cost risk.

(D) The third determination is that of the difficulty of the contractor's task. The contractor's task can be difficult or easy, regardless of the type of contract.

(E) Contractors are likely to assume greater cost risk only if contracting officers objectively analyze the risk incident to proposed contracts and are willing to compensate contractors for it. Generally, a cost-plus-fixed fee contract will not justify a reward for risk in excess of 0.5 percent, nor will a firm fixed-price contract justify a reward of less than the minimum in the structured approach. Where proper contracttype selection has been made, the reward for risk, by contract type, will usually fall into the following percentage ranges:

(1) Type of contract and percentage ranges for profit objectives developed by using the structured approach for research and development and manufacturing contracts:

[blocks in formation]

Cost-reimbursement type contracts Fixed-price type contracts

Percent

0-3

2-7

Cost-plus-fixed-fee Cost-plus-incentive fee

Fixed-price incentive

Firm fixed-price

Percent

0 to 0.5

1 to 2

2 to 3

3 to 4

(F) These ranges may not be appropriate for all acquisitions. For instance, a fixed-price-incentive contract that is closely priced with a low ceiling price and high incentive share may be tantamount to a firm fixed-price contract. In this situation, the contracting officer may determine that a basis exists for high confidence in the reasonableness of the estimate and that little opportunity exists for cost reduction without extraordinary efforts. On the other hand, a contract with a high ceiling and low incentive formula can be considered to contain cost-plus incentive-fee contract features. In this situation, the contracting officer may determine that the Government is retaining much of the contract cost responsibility and that the risk assumed by the contractor is minimal. Similarly, if a cost-plus-incentive-fee contract includes an unlimited downward (negative) fee adjustment on cost control, it could be comparable to a fixed-price-incentive contract. In such a pricing environment, the contracting officer may determine that the Government has transferred a greater amount of cost responsibility to the contractor than is typical under a normal cost-plus-incentive-fee contract.

(G) The contractor's subcontracting program may have a significant impact on the contractor's acceptance or risk under a contract form. It could cause risk to increase or decrease in terms of both cost and performance. This consideration should be a part of the contracting officer's overall evaluation in selecting a factor to apply for cost risk. It may be determined, for instance, that the prime contractor has effectively transferred real cost risk to a subcontractor and the contract cost risk evaluation may, as a result, be below the range which would otherwise apply for the contract type being proposed. The contract cost risk evaluation should not be lowered, however, merely on the basis that a substantial portion of the contract costs represents subcontracts without any substantial transfer of contractor's risk.

(H) In making a contract cost risk evaluation in an acquisition action that involves definitization of a letter contract, unpriced change orders, and unpriced orders under basic ordering

agreements, consideration should be given to the effect on total contract cost risk as a result of having partial performance before definitization. Under some circumstances it may be reasoned that the total amount of cost risk has been effectively reduced. Under other circumstances it may be apparent that the contractor's cost risk remained substantially unchanged. To be equitable, the determination of profit weight for application to the total of all recognized costs, both those incurred and those yet to be expended, must be made with consideration to all attendant circumstances— not just the portion of costs incurred or percentage of work completed prior to definitization.

(I) Time and material and labor hour contracts will be considered to be costplus-a-fixed-fee contracts for the purpose of establishing profit weights unless otherwise exempt under paragraph (b)(1)(ii) of this section in the evaluation of the contractor's assumption of contract cost risk.

(ii) Investment. HHS encourages its contractors to perform their contracts with the minimum of financial, facilities, or other assistance from the Government. As such, it is the purpose of this factor to encourage the contractor to acquire and use its own resources to the maximum extent possible. The evaluation of this factor should include an analysis of the following:

(A) Facilities. (Including equipment). To evaluate how this factor contributes to the profit objective requires knowledge of the level of facilities utilization needed for contract performance, the source and financing of the required facilities, and the overall cost effectiveness of the facilities offered. Contractors who furnish their own facilities which significantly contribute to lower total contract costs should be provided with additional profit. On the other hand, contractors who rely on the Government to provide or finance needed facilities should receive a corresponding reduction in profit. Cases between these examples should be evaluated on their merits with either positive or negative adjustments, as appropriate, in profit being made. However, where a highly facilitized contractor is to perform a contract which does not

benefit from this facilitization or where a contractor's use of its facilities has a minimum cost impact on the contract, profit need not be adjusted. When applicable, the prospective contractor's computation of facilities capital cost of money for pricing purposed under CAS 414 can help the contracting officer identify the level of facilities investment to be employed in contract performance.

(B) Payments. In analyzing this factor, consideration should be given to the frequency of payments by the Government to the contractor. The key to this weighting is to give proper consideration to the impact the contract will have on the contractor's cash flow. Generally, negative consideration should be given for advance payments and payments more frequent than monthly with maximum reduction being given as the contractor's working capital approaches zero. Positive consideration should be given for payments less frequent than monthly with additional consideration given for a capital turn-over rate on the contract which is less than the contractor's or the industry's normal capital turn-over rate.

(iii) Performance. (Cost-control and other past accomplishments.) The contractor's past performance should be evaluated in such areas as quality of service or product, meeting performance schedules, efficiency in cost control (including need for and reasonableness of cost incurred), accuracy and reliability of previous cost estimates, degree of cooperation by the contractor (both business and technical), timely processing of changes and compliance with other contractual provisions, and management of subcontract programs. Where a contractor has consistently achieved excellent results in these areas in comparison with other contractors in similar circumstances, this performance merits a proportionately greater opportunity for profit. Conversely, a poor record in this regard should be reflected in determining what constitutes a fair and reasonable profit.

(iv) Federal socioeconomic programs. This factor, which may apply to special circumstances or particular acquisitions, relates to the extent of a con

tractor's successful participation in Government sponsored programs such as small business, small disadvantaged business, women-owned small business, and energy conservation efforts. The contractor's policies and procedures which energetically support Government socioeconomic programs and achieve successful results should be given positive considerations. Conversely, failure or unwillingness on the part of the contractor to support Government socioeconomic programs should be viewed as evidence of poor performance for the purpose of establishing a profit objective.

(v) Special situations (A) Inventive and developmental contributions. The extent and nature of contractor-initiated and financed independent development should be considered in developing the profit objective, provided that the contracting officer has made a determination that the effort will benefit the contract. The importance of the development in furthering health and human services purposes, the demonstrable initiative in determining the need and application of the development, the extent of the contractor's cost risk, and whether the development cost was recovered directly or indirectly from Government sources should be weighed.

(B) Unusual pricing agreements. Occasionally, unusual contract pricing arrangements are made with the contractor wherein it agrees to cost ceilings, e.g., a ceiling on overhead rates for conditions other than those discussed at FAR 42.707. In these circumstances, the contractor should receive favorable consideration in developing the profit objective.

(C) Negative factors. Special situations need not be limited to those which only increase profit levels. A negative consideration may be appropriate when the contractor is expected to obtain spin-off-benefits as a direct result of the contract (e.g., products or services with commercial application).

(4) Facilities capital cost of money. When facilities capital cost of money (cost of capital committed to facilities) is included as an item of cost in the contractor's proposal, a reduction in the profit objective shall be made in an

amount equal to the amount of facilities capital cost of money allowed in accordance with the Facilities Capital Cost-of Money Cost Principal. If the contractor does not propose this cost, a provision must be inserted in the contract that facilities capital cost of money is not an allowable cost.

Subpart 315.6-Unsolicited
Proposals

315.605 Content of unsolicited proposals.

(d) Certification by offeror-To ensure against contacts between Department employees and prospective offerors which would exceed the limits of advance guidance set forth in FAR 15.604 resulting in an unfair advantage to an offeror, the contracting officer shall ensure that the following certification is furnished to the prospective offeror and the executed certification is included as part of the resultant unsolicited proposal:

UNSOLICITED PROPOSAL

Certification by Offeror

This is to certify, to the best of my knowledge and belief, that:

(a) This proposal has not been prepared under Government supervision.

(b) The methods and approaches stated in the proposal were developed by this offeror.

(c) Any contact with employees of the Department of Health and Human Services has been within the limits of appropriate advance guidance set forth in FAR 15.604.

(d) No prior commitments were received from departmental employees regarding acceptance of this proposal. Date:

Organization:

Name:

Title:

(This certification shall be signed by a responsible official of the proposing organization or a person authorized to contractually obligate the organization.)

315.606 Agency procedures.

(a) The HCA is responsible for establishing procedures to comply with FAR 15.606(a).

(b) The HCA or his/her designee shall be the point of contract for coordinating the receipt and handling of unsolicited proposals.

315.606-1 Receipt and initial review.

(d) An unsolicited proposal shall not be refused consideration merely because it was initially submitted as a grant application. However, contracts shall not be awarded on the basis of unsolicited proposals which have been rejected for grant support on the grounds that they lack scientific merit.

315.609 Limited use of data.

The legend, Use and Disclosure of Data, prescribed in FAR 15.609(a) is to be used by the offeror to restrict the use of data for evaluation purposes only. However, data contained within the unsolicited proposal may have to be disclosed as a result of a request submitted pursuant to the Freedom of Information Act. Because of this possibility, the following notice shall be furnished to all prospective offerors of unsolicited proposals whenever the legend is provided in accordance with FAR 15.604(a)(7):

The Government will attempt to comply with the "Use and Disclosure of Data" legend.

However, the Government may not be able to withhold a record (data, document, etc.) nor deny access to a record requested by an individual (the public) when an obligation is imposed on the Government under the Freedom of Information Act, 5 U.S.C. 552, as amended. The Government determination to withhold or disclose a record will be based upon the particular circumstances involving the record in question and whether the record may be exempted from disclosure under the Freedom of Information Act. Records which the offeror considers to be trade secrets and commercial or financial information and privileged or confidential must be identified by the offeror as indicated in the referenced legend.

PART 316-TYPES OF CONTRACTS

Subpart 316.3-Cost-Reimbursement Contracts

Sec.

316.307 Contract clauses.

Subpart 316.6-Time-and-Materials, LaborHour, and Letter Contracts

316.603 Letter contracts. 316.603-3 Limitations.

316.603-70 Information to be furnished when requesting authority to issue a letter contract.

[blocks in formation]

(g) Estimated total amount of definitized contract.

(h) Type of definitive contract to be executed (fixed price, cost-reimbursement, etc.)

(i) Statement of the necessity and advantage to the Government of the use of the proposed letter contract.

(j) Statement of percentage of the estimated cost that the obligation of funds represents. In rare instances where the obligation represents 50 percent or more of the proposed estimated cost of the acquisition, a justification for that obligation must be included which would indicate the basis and necessity for the obligation (e.g., the contractor requires a large initial outlay of funds for major subcontract awards or an extensive purchase of materials to meet an urgent delivery requirement). In every case, documentation must assure that the amount to be obligated is not in excess of an amount reasonably required to perform the work.

(k) Period of effectiveness of a proposed letter contract. If more than 180 days, complete justification must be given.

(1) Statement of any substantive matters that need to be resolved.

316.603-71 Approval for modifications to letter contracts.

All letter contract modifications (amendments) must be approved one level above the contracting officer. Request for authority to issue letter contract modifications shall be processed in the same manner as requests for authority to issue letter contracts and shall include the following:

(a) Name and address of the contractor.

(b) Description of work and services. (c) Date original request was approved and indicate approving official.

(d) Letter contract number and date issued.

(e) Complete justification as to why the letter contract cannot be definitized at this time.

(f) Complete justification as to why the level of funding must be increased. (g) Complete justification as to why the period of effectiveness is increased beyond 180 days, if applicable.