Air Force Intercontinental Ballistics Missile Base Construction Program: Hearings ... 87th Congress, 1st Session1961 - 310 pages |
From inside the book
Results 1-5 of 100
Page 2
... problems , maybe you know some of the solutions . I want the discussion on the point of the contractors to be frank , free , and open , with no information what- soever being withheld from the committee . You may be assured that the ...
... problems , maybe you know some of the solutions . I want the discussion on the point of the contractors to be frank , free , and open , with no information what- soever being withheld from the committee . You may be assured that the ...
Page 9
... problem lies in the principle of the Government being willing to pay for the cost that it is incurring in this experimental wartime missile base construction contract . All of the other major participants in the program , except the ...
... problem lies in the principle of the Government being willing to pay for the cost that it is incurring in this experimental wartime missile base construction contract . All of the other major participants in the program , except the ...
Page 10
... problems on four missile bases in widely scattered parts of the country . Contracts were awarded to Morrison - Knudsen & Associates for the Titan I facilities at Lowry AFB in April and June of 1959. These contracts had an original value ...
... problems on four missile bases in widely scattered parts of the country . Contracts were awarded to Morrison - Knudsen & Associates for the Titan I facilities at Lowry AFB in April and June of 1959. These contracts had an original value ...
Page 11
... problems inherent in this crash construction program . As a result of these changes in contract procedure , the Government's estimates of the costs of performing modification work are completely unrealistic as is its refusal to ...
... problems inherent in this crash construction program . As a result of these changes in contract procedure , the Government's estimates of the costs of performing modification work are completely unrealistic as is its refusal to ...
Page 21
... problems we have since encountered , I am not at all certain that we would have been able to make a reasonable estimate of the added cost which should have been included in the bid price . Our contract is approximately 50 percent ...
... problems we have since encountered , I am not at all certain that we would have been able to make a reasonable estimate of the added cost which should have been included in the bid price . Our contract is approximately 50 percent ...
Contents
145 | |
146 | |
147 | |
148 | |
164 | |
191 | |
198 | |
208 | |
130 | |
133 | |
134 | |
137 | |
138 | |
139 | |
140 | |
142 | |
143 | |
216 | |
242 | |
253 | |
258 | |
268 | |
280 | |
281 | |
282 | |
304 | |
Other editions - View all
Common terms and phrases
acceleration additional adjustment administration agencies Air Force Air Force Base amount approval architect-engineer area engineer ATLAS ATLAS missile authority ballistic missile basis BOSCHEN Cable tray CEBMCO change orders CHARYK claims Colonel WHITESELL Colonel WOODBURY committee completion dates construction contract construction program contracting officer contractor CORNWALL Corps of Engineers correct cost cost-plus decision determination directed drawings equitable EVERIST excusable delays fact fixed-price contract funds furnish GERRITY Government estimate HARDEMAN ICBM impact inspection installation involved ITSCHNER JONAS KAISER LEAVELL LESTER MACDONALD ment million MINTON missile program missile silo modifications negotiations operational original contract PAUL payment percent performance Plattsburgh powerhouse present prime contractor problems procedure question representative responsibility result SATAF schedule SHEPPARD shop drawings SIKES specifications standardized equipment statement subcontractors submitted suppliers supply contracts things tion TITAN valves weapons system WHITTEN
Popular passages
Page 284 - The Contractor warrants that no person or selling agency has been employed or retained to solicit or secure this contract upon an agreement or understanding for a commission, percentage, brokerage, or contingent fee...
Page 17 - Officer in writing of: (1) subsurface or latent physical conditions at the site differing materially from those indicated in this contract, or (2) unknown physical conditions at the site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in this contract.
Page 281 - The decision of the Secretary or his duly authorized representative for the determination of such appeals shall be final and conclusive unless determined by a court of competent jurisdiction to have been fraudulent, or capricious, or arbitrary, or so grossly erroneous as necessarily to imply bad faith, or not supported by substantial evidence.
Page 281 - In connection with any appeal proceeding under this clause, the Contractor shall be afforded an opportunity to be heard and to offer evidence in support of his appeal.
Page 197 - Government, to enter into contracts or into amendments or modifications of contracts heretofore or hereafter made and to make advance payments thereon, without regard to other provisions of law relating to the making, performance, amendment, or modification of contracts, whenever he deems that such action would facilitate the national defense.
Page 197 - ... the Secretary of Defense, the Secretary of the Army, the Secretary of the Navy, or the Secretary of the Air Force, or the...
Page 281 - DISPUTES [Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Contracting Officer, who shall reduce his decision to writing and mail or otherwise furnish a copy thereof to the Contractor.
Page 284 - States, or if articles, materials, or supplies of the class or kind to be used or the articles, materials, or supplies from which they are manufactured are not mined, produced, or manufactured, as the case may be, in the United States in sufficient and reasonably available commercial quantities and of a satisfactory quality.
Page 281 - Contractor shall be afforded an opportunity to be heard and to offer evidence in support of its appeal. Pending final decision of a dispute hereunder, the Contractor shall proceed diligently with the performance of the contract and in accordance with the Contracting Officer's decision. b. This "Disputes...
Page 284 - ... articles, materials, and supplies as have been mined or produced in the United States, and only such manufactured articles, materials, and supplies as have been manufactured in the United States substantially all from articles, materials, or supplies mined, produced, or manufactured, as the case may be, in the United States, shall be acquired for public use.