| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1959 - 1028 pages
...in writing within 30 days from the date of receipt by the Contractor of the notification of extra or change : Provided, however, That the Contracting Officer,...receive, and act upon any such claim asserted at any time prior to the date of final settlement of the contract. If the parties fail to agree upon the adjustment... | |
| Administrative law - 1966 - 968 pages
...manufactured for the Government In accordance therewith; (11) method of shipment or packing; and (ill) place of delivery. If any such change causes an Increase...receive and act upon any such claim asserted at any time prior to final payment under this contract. Where the cost of property made obsolete or excess... | |
| Administrative law - 1982 - 532 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date or receipt by the Contractor...receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| Administrative law - 1974 - 1020 pages
...for adjustment under this clause must be asserted within sixty (60) days from the date of receipt b; the Contractor of the notification of change : Provided,...receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| Administrative law - 1971 - 668 pages
...adjustment under this clauaeSmiwlie V-_ within 30 days from the date of receipt by the CctfijrWctor of the notification of change: Provided, however....receive and act upon any such claim asserted at any time prior to final payment under this contract. Where the cost of property made obsolete or excess... | |
| Administrative law - 1975 - 252 pages
...Contractor for adjustment under this clause must be asserted within 30 calendar days from the date of receipt by the Contractor of the notification of change:...justify such action, may receive and act upon any such «laim asserted at any tune prior to final payment •under the contract. Failure to agree to any adjustment... | |
| Administrative law - 1978 - 188 pages
...of receipt by the Contractor of the notification Title 41 — Public Contracts, Property Management of change: Provided, however, that the Contracting...receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| Administrative law - 1978 - 944 pages
...clause must be asserted within 30 days from the date of receipt by the Contractor of the rectification of change, provided, however, that the Contracting...receive and act upon any such claim asserted at any tine prior to final payment under this contract. Where the cost of property made obsolete or excess... | |
| Administrative law - 1973 - 968 pages
...asserted within sixty (60) days from the date of receipt by the Contractor of the notification oí change : Provided, however, That the Contracting Officer,...receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| Administrative law - 1981 - 706 pages
...Contractor for adjustment under this clause must be asserted within sixty (60) days from the date of receipt of the notification of change: Provided, however,...justify such action, may receive and act upon any claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment... | |
| |