material. Improved methods and techniques will be sought for the analysis and application of new products, including the use of radio- isotopes, X-ray diffraction spectographs, and chemical methods.
The Greater Wenatchee division of the Chief Joseph Dam project, consisting of 4 units- East, Brays Landing, Howard Flat, and Moses Coulee was authorized on May 5, 1958. The 4 units total some 8,661 acres, of which 7,221 are nonirrigated. The development of an irriga- tion water supply for the division is urgently needed to replace land that will be or has been lost through subdivision of apple orchards for housing areas, the construction of a new high- way through the division, and the potential construction of Rocky Reach and Wells Dams. The development of new agriculture land will also serve as the primary factor in the expansion of the economics of the area. A definite plan report will be completed in fiscal year 1959. Advance planning studies to be initiated after fiscal year 1960.
Advance planning studies to be initiated or re- sumed after fiscal year 1960.
The Washoe project will provide supplemental water for irrigation to 44,500 acres of land in need of dependable late season water supply and a full supply for some 5,100 acres of pres- ently undeveloped arable land. Control of the high spring runoff will reduce flood damage and with project drainage will improve 30,900 acres of presently waterlogged land. The project also will produce 28,000 kilowatts of hydroelec- tric power greatly needed in western Nevada. The fiscal year 1959 Appropriation Act pro- vided funds for initiation of construction on Prosser Creek Dam and Reservoir of this proj- ect and these general investigation funds will finance continuation of detailed preconstruc- tion studies on the balance of the project. The definite plan report is scheduled to be com- pleted in fiscal year 1960.
Schedule of general investigations program-Continued
ADVANCE PLANNING-Continued
Advance planning studies to be initiated after fiscal year 1960.
Detailed preconstruction studies were interrupted in 1954 by a decision by local interests to explore possibility of proceeding with private financing. These efforts were unsuccessful and the local interests have since expressed interest in a Federal development and have contributed funds toward completing the preconstruction work. A definite plan report is to be com- pleted in fiscal year 1960.
Detailed preconstruction studies were underway at the end of fiscal year 1958. The fiscal year 1959 program provided for the continuation of this work until about September 1958 when an allotment of construction funds was made available by the 1959 Public Works Appro- priation Act. The funds programed for fiscal year 1959 provided for the continuation until about September 1958 of detailed preconstruction studies which were financed with appropriated funds and funds contributed by local interests. Work under the general investigation activity was terminated last September when an allotment of construction funds was made available. 2,290,000 Advance planning studies to be initiated after fiscal year 1960.
Investigation of irrigation features of a multiple- purpose project proposed by the Corps of Engineers to be constructed primarily for flood control and irrigation. Authorizing legislation was passed by the 85th Cong. and signed by the President July 23, 1958. The project is urgently needed to provide protection from a
serious and longstanding flood problem and for regulation and conservation of waters of the Purgatoire River for more beneficial and efficient irrigation use. During fiscal year 1959 a detailed report will be drafted on irriga- tion and repayment phases of the project. After completion of the report in August 1959, the program will be limited to cooperation with the Corps of Engineers and water users in the area.
Investigation should be made in fiscal year 1959 to determine means and probable cost of in- creasing the capacity of the Payette division irrigation system to deliver more water to project lands.
Many of the structures of this project have deteriorated over the more than 40 years that the project has been in operation to the point where they are in immediate danger of failure or the cost of maintenance is prohibitively high. Replacement of these structures is be- yond the financial ability of the water users. A study is to be made in fiscal year 1960 to determine the project needs and develop a rehabilitation program to place the project in a satisfactory and safe operating condition. The existing Vermejo diversion dam was con- structed about 1914, is of questionable struc- tural stability, and has its crest about 2 feet lower than required to permit diversion of flows to the capacity of the main canal. Fiscal year 1960 funds scheduled would be used to initiate and complete a study of the feasibility of plans for raising the crest of the Vermejo diversion dam 2 feet by modification or replace- ment of the existing dam.
10,000 Reports on field reclassification of class 5 lands in Malta, Glasgow, and Chinook divisions, as provided for in Public Law 402, 82d Congress, 2d session, will be completed, Miscellaneous related work will be continued in connection with the terms of the amendatory contracts. This study is to be completed in fiscal year 1960. Investigation for determining the cost of increasing the storage capacity of Fresno Dam and Reservoir is scheduled in future years.
Schedule of general investigations program-Continued INVESTIGATIONS OF EXISTING PROJECTS-Continued
This investigation is required to enable compli- ance with article 5B on repayment contract No. 14-06-600-67 requiring disposition of 9,474 acres of class 5 lands in Midvale irrigation district prior to 1962.
Investigations to determine the disposition of 8,043 acres of class 5 land as required by art. 12 of the repayment contract No. I14-15-56.
Matanuska Valley project..
Funds programed to accomplish reconnaissance investigations, studies, etc., on items of a general nature or items which cannot be fore- seen at this time and scheduled separately. Devil Canyon project is a potential source for a large block of power (450,000 kilowatts ulti- mate) that could serve the railbelt area from Seward to Fairbanks. Ample available energy would stimulate and afford an opportunity for industrial development and related growth throughout this section of Alaska. Studies are underway, in cooperation with the U.S. Department of Agriculture and the Alaska Agriculture Experimental Station in conjunc- tion with the Soil Conservation Service, to determine crop-yield benefits that may be derived through irrigation as a basis for es- tablishing feasibility for developing an irriga- tion system to serve the Matanuska area.
« PreviousContinue » |