| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1959 - 1028 pages
...Contractor shall be afforded an opportunity to be heard and to offer evidence in support of its appeal. Pending final decision of a dispute hereunder, the...accordance with the Contracting Officer's decision. 7. On or about March 10, 1952, plaintiff ordered Hatheway to proceed with its subcontract and, under... | |
| United States. Congress. House. Committee on Armed Services - Legislative hearings - 1960 - 1930 pages
...heard and to offer evidence in support of its appeal. Pending final decision of a dispute hereumler, the Contractor shall proceed diligently with the performance...accordance with the Contracting Officer's decision. (b) This "Disputes" clause does not preclude consideration of law questions in connection with decisions... | |
| Administrative law - 1972 - 684 pages
...fraudulent, or capricious, or arbitrary, or so grossly erroneous as necessarily to imply bad faith, or not supported by substantial evidence. Pending...Contracting Officer's decision. 4. RESPONSIBILITY OF CONTRACTOR sary licenses and permits; (hi provide competent superintendence; (c) take precautions... | |
| Administrative law - 1971 - 668 pages
...fraudulent, or capricious, or arbitrary, or so grossly erroneous as necessarily to imply bad faith, or not supported by substantial evidence. Pending...Contracting Officer's decision. 4. RESPONSIBILITY OF CONTRACTOR At his own expense the Contractor shall: (a) obtain any necessary licenses and permits:... | |
| Administrative law - 1972 - 862 pages
...fraudulent, or capricious, or arbitrary, or so grossly erroneuus as necessarily to imply bad fttth. or not supported by substantial evidence. Pending...contract and in accordance with the Contracting Officer's de4. RESPONSIBILITY OF CONTRACTOR At his own expense the Contractor shall: (a) obtain any necesence:... | |
| Administrative law - 1968 - 1348 pages
...shall be final and conclusive unless fraudulent. apm illy jarily'to imply bad faith, or not sunported by substantial evidence. Pending final decision of...contract and in accordance with the Contracting Officer's de4. RESPONSIBILITY OF CONTRACTOR At his own expense the Contractor shall: (a) obtain any necessary... | |
| Administrative law - 1979 - 1186 pages
...Contractor shall be afforded an opportunity to be heard and to offer evidence in support of his appeal. Pending final decision of a dispute hereunder, the...accordance with the Contracting Officer's decision. (b) This "Disputes" clause does not preclude consideration of questions of law in connection with decisions... | |
| United States. Marine Corps - 1949 - 858 pages
...Contractor shall be afforded an opportunity to be heard and to offer evidence in support of its appeal, pending final decision of a dispute hereunder, the...accordance with the Contracting Officer's decision. 18. DEFINITIONS. (a) The term "head of the department" as used herein shall mean the head or any assistant... | |
| Administrative law - 1982 - 520 pages
...contractor shall be afforded an opportunity to be heard and to offer evidence in support of his appeal. Pending final decision of a dispute hereunder, the...accordance with the contracting officer's decision. (b) This "Disputes" clause does not preclude consideration of law questions in connection with decisions... | |
| Administrative law - 1974 - 686 pages
...Contractor shall be afforded an opportunity to be heard and to offer evidence in support of its appeal. Pending final decision of a dispute hereunder, the...accordance with the Contracting Officer's decision. (b) This "Disputes" clause does not preclude consideration of law questions in connection with decisions... | |
| |