staff Fire Protection Evaluation Report accepting or requiring such features.

(2) Those fire protection features involving installation of modifications not requiring prior approval or plant shutdown shall be implemented within 12 months after the date of the NRC staff Fire Protection Safety Evaluation Report accepting or requiring such features.

(3) Those fire protection features, including alternative shutdown capability, involving installation of modifications requiring plant shutdown shall be implemented before the startup after the earliest of the following events commencing 9 months or more after the date of the NRC staff Fire Protection Safety Evaluation Report accepting or requiring such features:

(i) The first refueling outage; (ii) Another planned outage that lasts for at least 60 days; or

(iii) An unplanned outage that lasts for at least 120 days.

(4) Those fire protection features involving dedicated shutdown capability requiring new buildings and systems shall be implemented within 30 months of NRC approval. Other modifications requiring NRC approval prior to installation shall be implemented within 6 months after NRC approval.

(e) Nuclear power plants licensed to operate after January 1, 1979, shall complete all fire protection modifications needed to satisfy Criterion 3 of Appendix A to this part in accordance with the provisions of their licenses.

(Sec. 161b, Pub. L. 83-703, 68 Stat. 948; sec. 201, Pub. L. 93-438, 88 Stat. 1242 (42 U.S.C. 2201(b), 5841))

[45 FR 76610, Nov. 19, 1980]

[blocks in formation]

ing such conditions and limitations including technical specifications, as it deems appropriate and necessary.

§ 50.51 Duration of license, renewal.

Each license will be issued for a fixed period of time to be specified in the license but in no case to exceed 40

years from the date of issuance. Where the operation of a facility is involved the Commission will issue the license for the term requested by the applicant or for the estimated useful life of the facility if the Commission determines that the estimated useful life is less than the term requested. Where construction of a facility is involved, the Commission may specify in the construction permit the period for which the license will be issued if approved pursuant to § 50.56. Licenses may be renewed by the Commission upon the expiration of the period.

§ 50.52 Combining licenses.

The Commission may combine in a single license the activities of an applicant which would otherwise be licensed severally.

§ 50.53 Jurisdictional limitations.

No license under this part shall be deemed to have been issued for activities which are not under or within the jurisdiction of the United States.

(Sec. 161, as amended, Pub. L. 83-703, 68 Stat. 948 (42 U.S.C. 2201); sec. 201, as amended, Pub. L. 93-438, 88 Stat. 1243 (42 U.S.C. 5841))

[21 FR 355, Jan. 19, 1956, as amended at 43 FR 6924, Feb. 17, 1978]

§ 50.54 Conditions of licenses.

Whether stated therein or not, the following shall be deemed conditions in every license issued:

(a) [Reserved]

(b) No right to the special nuclear material shall be conferred by the license except as may be defined by the license.

(c) Neither the license, nor any right thereunder, nor any right to utilize or produce special nuclear material shall be transferred, assigned, or disposed of in any manner, either voluntarily or involuntarily, directly or indirectly, through transfer of control of the li

cense to any person, unless the Commission shall, after securing full information, find that the transfer is in accordance with the provisions of the act and give its consent in writing.

(d) The license shall be subject to suspension and to the rights of recapture of the material or control of the facility reserved to the Commission under section 108 of the act in a state of war or national emergency declared by Congress.

(e) The license shall be subject to revocation, suspension, modification, or amendment for cause as provided in the act and regulations, in accordance with the procedures provided by the act and regulations.

(f) The licensee will at any time before expiration of the license, upon request of the Commission submit written statements, signed under oath or affirmation, to enable the Commission to determine whether or not the license should be modified, suspended or revoked.

(g) The issuance or existence of the license shall not be deemed to waive, or relieve the licensee from compliance with, the antitrust laws, as specified in subsection 105a of the Act. In the event that the licensee should be found by a court of competent jurisdiction to have violated any provision of such antitrust laws in the conduct of the licensed activity, the Commission may suspend or revoke the license or take such other action with respect to it as shall be deemed necessary.

(h) The license shall be subject to the provisions of the Act now or hereafter in effect and to all rules, regulations, and orders of the Commission. The terms and conditions of the license shall be subject to amendment, revision, or modification, by reason of amendments of the Act or by reason of rules, regulations, and orders issued in accordance with the terms of the act.

(i) Except as provided in § 55.9 of this chapter, the licensee shall not permit the manipulation of the controls of any facility by anyone who is not a licensed operator or senior operator as provided in Part 55 of this chapter.

(i-1) Within three (3) months after issuance of an operating license, the li

censee shall have in effect an operator requalification program which shall, as a minimum, meet the requirements of Appendix A of Part 55 of this chapter. Notwithstanding the provisions of § 50.59 the licensee shall not, except as specifically authorized by the Commission, make a change in an approved operator requalification program by which the scope, time allotted for the program or frequency in conducting different parts of the program is decreased. Holders of operating licenses in effect on September 17, 1973 shall implement an operator requalification program which, as a minimum, meets the requirements of Appendix A of Part 55 of this chapter which was submitted for approval by the Atomic Energy Commission.

(j) Apparatus and mechanisms other than controls, the operation of which may affect the reactivity or power level of a reactor shall be manipulated only with the knowledge and consent of an operator or senior operator licensed pursuant to Part 55 of this chapter present at the controls.

(k) An operator or senior operator licensed pursuant to Part 55 of this chapter shall be present at the controls at all times during the operation of the facility.

(1) The licensee shall designate individuals to be responsible for directing the licensed activities of licensed operators. These individuals shall be licensed as senior operators pursuant to Part 55 of this chapter.

(m) A senior operator licensed pursuant to Part 55 of this chapter shall be present at the facility or readily available on call at all times during its operation, and shall be present at the facility during initial start-up and approach to power, recovery from an unplanned or unscheduled shut-down or significant reduction in power, and refueling, or as otherwise prescribed in the facility license.

(n) The licensee shall not, except as authorized pursuant to a construction permit, make any alteration in the facility constituting a change from the technical specifications previously incorporated in a license or construction permit pursuant to § 50.36 of this part.

(0) Primary reactor containments for water cooled power reactors shall

be subject to the requirements set forth in Appendix J to this part.

(p) The licensee shall prepare and maintain safeguards contingency plan Procedures in accordance with Appendix C of 10 CFR Part 73 for effecting the actions and decisions contained in the Responsibility Matrix of the safeguards contingency plan. The licensee may make no change which would decrease the effectiveness of a security plan prepared pursuant to § 50.34(c) or Part 73 of this chapter, or of the first four categories of information (Background, Generic Planning Base, Licensee Planning Base, Responsibility Matrix) contained in a licensee safeguards contingency plan prepared pursuant to § 50.34(d) or Part 73, as applicable, without prior approval of the Commission. A licensee desiring to make such a change shall submit an application for an amendment to his license pursuant to § 50.90. The licensee may make changes to the security plan or to the safeguards contingency plan without prior Commission approval if the changes do not decrease the safeguards effectiveness of the plan. The licensee shall maintain records of changes to the plans made without prior Commission approval for a period of two years from the date of the change, and shall furnish to the Director of Nuclear Material Safety and Safeguards (for enrichment and reprocessing facilities) or to the Director of Nuclear Reactor Regulation (for nuclear reactors), U.S. Nuclear Regulatory Commission, Washington, D.C. 20555, with a copy to the appropriate NRC Regional Office specified in Appendix A of Part 73 of this chapter, a report containing a description of each change within two months after the change is made. Prior to the safeguards contingency plan being put into effect, the licensee shall have:

(1) All safeguards capabilities specified in the safeguards contingency plan available and functional,

(2) Detailed Procedures developed according to Appendix C to Part 73 available at the licensee's site, and

(3) All appropriate personnel trained to respond to safeguards incidents as outlined in the plan and specified in the detailed Procedures.

The licensee shall provide for the development, revision, implementation, and maintenance of his safeguards contingency plan. To this end, the licensee shall provide for a review at least every 12 months of the safeguards contingency plan by individuals independent of both security program management and personnel who have direct responsibility for implementation of the security program. The review shall include a review and audit of safeguards contingency procedures and practices, an audit of the security system testing and maintenance program, and a test of the safeguards system along with commitments establish for response by local law enforcement authorities. The results of the review and audit, along with recommendations for improvements, shall be documented, reported to the licensee's corporate and plant management, and kept available at the plant for inspection for a period of two years.

(q) A licensee authorized to possess and/or operate a nuclear power reactor shall follow and maintain in effect emergency plans which meet the standards in § 50.47(b) of this part and the requirements in Appendix E to this part. A licensee authorized to possess and/or operate a research reactor or a fuel facility shall follow and maintain in effect emergency plans which meet the requirements in Appendix E to this part. The nuclear power reactor licensee may make changes to these plans without Commission approval only if such changes do not decrease the effectiveness of the plans and the plans, as changed, continue to meet the standards of § 50.47(b) and the requirements of Appendix E to this part. The research reactor licensee and/or the fuel facility licensee may make changes to these plans without Commission approval only if such changes do not decrease the effectiveness of the plans and the plans, as changed, continue to meet the requirements of Appendix E to this part. Proposed changes that decrease the effectiveness of the approved emergency plans shall not be implemented without application to and approval by the Commission. The licensee shall furnish 3 copies of each proposed change for approval; and/or if a

change is made without prior approval, 3 copies shall be submitted within 30 days after the change is made or proposed to the Director of the appropriate NRC regional office specified in Appendix D, 10 CFR Part 20, with 10 copies to the Director of Nuclear Reactor Regulation, or, if appropriate, the Director of Nuclear Material Safety and Safeguards, U.S. Nuclear Regulatory Commission, Washington, D.C. 20555.

(r) Each licensee who is authorized to possess and/or operate a research or test reactor facility with an authorized power level greater than or equal to 500 kW thermal, under a license of the type specified in § 50.21(c), shall submit emergency plans complying with 10 CFR Part 50, Appendix E, to the Director of Nuclear Reactor Regulation for approval within one year from the effective date of this rule. Each licensee who is authorized to possess and/or operate a research reactor facility with an authorized power level less than 500 kW thermal, under a license of the type specified in § 50.21(c), shall submit emergency plans complying with 10 CFR Part 50, Appendix E, to the Director of Nuclear Reactor Regulation for approval within two years from the effective date of this amendment.

(s)(1) Each licensee who is authorized to possess and/or operate a nuclear power reactor shall submit to NRC within 60 days of the effective date of this amendment the radiological emergency response plans of State and local governmental entities in the United States that are wholly or partially within a plume exposure pathway EPZ, as well as the plans of State governments wholly or partially within an ingestion pathway EPZ. 2

Emergency Planning Zones (EPZs) are discussed in NUREG-0396; EPA 520/1-78016, "Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants," December 1978.

If the State and local emergency response plans have been previously provided to the NRC for inclusion in the facility docket, the applicant need only provide the appropriate reference to meet this requirement.

Ten (10) copies of the above plans shall be forwarded to the Director of Nuclear Reactor Regulation with 3 copies to the Director of the appropriate NRC regional office. Generally, the plume exposure pathway EPZ for nuclear power reactors shall consist of an area about 10 miles (16 km) in radius and the ingestion pathway EPZ shall consist of an area about 50 miles (80 km) in radius. The exact size and configuration of the EPZs for a particular nuclear power reactor shall be determined in relation to local emergency response needs and capabilities as they are affected by such conditions as demography, topography, land characteristics, access routes, and jurisdictional boundaries. The size of the EPZS also may be determined on a case-by-case basis for gas-cooled nuclear reactors and for reactors with an authorized power level less than 250 MW thermal. The plans for the ingestion pathway EPZ shall focus on such actions as are appropriate to protect the food ingestion pathway.

(2)(i) For operating power reactors, the licensee, State, and local emergency response plans shall be implemented by April 1, 1981, except as provided in Section IV.D.3 of Appendix E to this part.

(ii) If after April 1, 1981, the NRC finds that the state of emergency preparedness does not provide reasonable assurance that adequate protective measures can and will be taken in the event of a radiological emergency (including findings based on requirements of Appendix E, Section IV.D.3) and if the deficiencies (including deficiencies based on requirements of Appendix E, Section IV.D.3) are not corrected within four months of that finding, the Commission will determine whether the reactor shall be shut down until such deficiencies are remedied or whether other enforcement action is appropriate. In determining whether a shutdown or other enforcement action is appropriate, the Commission shall take into account, among other factors, whether the licensee can demonstrate to the Commission's satisfaction that the deficiencies in the plan are not significant for the plant in question, or that adequate interim compensating actions

have been or will be taken promptly, or that that there are other compelling reasons for continued operation.

(3) The NRC will base its finding on a review of the FEMA findings and determinations as to whether State and local emergency plans are adequate and capable of being implemented, and on the NRC assessment as to whether the licensee's emergency plans are adequate and capable of being implemented. Nothing in this paragraph shall be construed as limiting the authority of the Commission to take action under any other regulation or authority of the Commission or at any time other than that specified in this paragraph.

(t) A nuclear power reactor licensee shall provide for the development, revision, implementation, and maintenance of its emergency preparedness program. To this end, the licensee shall provide for a review of its emergency preparedness program at least every 12 months by persons who have no direct responsibility for implementation of the emergency preparedness program. The review shall include an evaluation for adequacy of interfaces with State and local governments and of licensee drills, exercises, capabilities, and procedures. The results of the review, along with recommendations for improvements, shall be documented, reported to the licensee's corporate and plant management, and retained for a period of five years. The part of the review involving the evaluation for adequacy of interface with State and local governments shall be available to the appropriate State and local governments.

(u) Within 60 days after the effective date of this amendment, each nuclear power reactor licensee shall submit to the NRC plans for coping with emergencies that meet standards in § 50.47(b) and the requirements of Appendix E to this part.

(v) Each licensee subject to the requirements of Part 73 of this chapter shall ensure that physical security, safeguards contingency and guard qualification and training plans and other related Safeguards Information are protected against unauthorized disclosure in accordance with the re

quirements of § 73.21 of this chapter, as appropriate.

(Pub. L. 93-377, 88 Stat. 475; Sec. 201, Pub. L. 93-438, 88 Stat. 1243 (42 U.S.C. 2201, 5841); sec. 161i, Pub. L. 83-703, 68 Stat. 948, sec. 204(b)(1), Pub. L. 93-438, 88 Stat. 1243, 1245 (42 U.S.C. 2201, 5844); sec. 161b., i., and o., Pub. L. 83-703, 68 Stat. 948 (42 U.S.C. 2201); sec. 201, as amended, Pub. L. 93-438, 88 Stat. 1242, Pub. L. 94-79, 89 Stat. 413 (42 U.S.C. 5341))

[21 FR 355, Jan. 19, 1956, as amended at 28 FR 3197, Apr. 3, 1963; 32 FR 2562, Feb. 7, 1967; 38 FR 4386, Feb. 14, 1973; 38 FR 22222, Aug. 17, 1973; 38 FR 26354, Sept. 20, 1973; 38 FR 30538, Nov. 6, 1973; 40 FR 8789, Mar. 3, 1975; 42 FR 10838, Feb. 24, 1977; 43 FR 11963, Mar. 23, 1978; 45 FR 55410, Aug. 19, 1980; 46 FR 51723, Oct. 22, 1981; 46 FR 63032, Dec. 30, 1981]

EFFECTIVE DATE NOTE: At 46 FR 51723, Oct. 22, 1981, § 50.54 (v) was added, effective Jan. 20, 1982.

§ 50.55 Conditions of construction permits.

Each construction permit shall be subject to the following terms and conditions:

(a) The permit shall state the earliest and latest dates for completion of the construction or modification.

(b) If the proposed construction or modification of the facility is not completed by the latest completion date, the permit shall expire and all rights thereunder shall be forfeited: Provided, however, That upon good cause shown the Commission will extend the completion date for a reasonable period of time. The Commission will recognize, among other things, developmental problems attributable to the experimental nature of the facility or fire, flood, explosion, strike, sabotage, domestic violence, enemy action, an act of the elements, and other acts beyond the control of the permit holder, as a basis for extending the completion date.

(c) Except as modified by this section and § 50.55a, the construction permit shall be subject to the same conditions to which a license is subject.

(d) At or about the time of completion of the construction or modification of the facility, the applicant will file any additional information needed to bring the original application for li

« PreviousContinue »