| United States. Court of Claims - Law reports, digests, etc - 1947 - 828 pages
...Government may, by written notice to the TO Reporter's Ststsment of the Case contractor, tenninate his right to proceed with the work or such part of...the same to completion by contract or otherwise, and the contractor and his sureties shall be liable to the Government for any excess cost occasioned the... | |
| United States. Court of Claims - Law reports, digests, etc - 1946 - 906 pages
...or any extension thereof, or fails to complete said work within such time, the Government, may, by written notice to the contractor, terminate his right...part of the work as to which there has been delay. * * * Provided, That the right of the contractor to proceed shall not be terminated or the contractor... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1958 - 1044 pages
...less than the rate of wages required by the contract to be paid as aforesaid, the Government may, by written notice to the contractor, terminate his right...or such part of the work as to which there has been a failure to pay said required wages and prosecute the work to completion by contract or otherwise,... | |
| United States. Court of Claims - Law reports, digests, etc - 1937 - 786 pages
...1, or any extension thereof, or fails to complete said work within such time, the Government may, by written notice to the contractor, terminate his right...work or such part of the work as to which there has Opinion of the Court been delay. In such event, the Government may take over the work and prosecute... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1962 - 712 pages
...right to proceed with the work or such part of the work as to which there has been 550 Findings of Fact delay. In such event the Government may take over...same to completion, by contract or otherwise, and the contractor and his sureties shall be liable to the Government for any excess cost occasioned the... | |
| United States. Court of Claims - Law reports, digests, etc - 1945 - 952 pages
...will insure its completion within the time specified in Article 1, * * * the Government may, * * * terminate his right to proceed with the work or such...part of the work as to which there has been delay." The Court interpreted the words "refuses or fails to prosecute the work" to mean that if the contractor... | |
| United States. Court of Claims - Law reports, digests, etc - 1940 - 772 pages
...1, or any extension thereof, or fails to complete said work within such time, the Government may, by written notice to the contractor, terminate his right...proceed with. the work or such part of the work as Reporter's Statement of the Case to which there has been delay. In such event, the Government may take... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1952 - 1040 pages
...contractor, terminate his right to proceed with the work or such part of the work as to which there lias been delay. In such event the Government may take...over the work and prosecute the same to completion, hy contract or otherwise, and the contractqr and his sureties shall be liable to the Government for... | |
| United States. Court of Claims - Law reports, digests, etc - 1943 - 904 pages
...there has been a failure to pay said prevailing wages. In such event, it is understood and agreed that the Government may take over the work and prosecute...the same to completion by contract or otherwise, and that the contractor and his sureties shall be liable to the Government for any excess cost occasioned... | |
| United States. Court of Claims - Law reports, digests, etc - 1948 - 974 pages
...would insure its completion within the time specified, and that in such event the Government might take over the work and prosecute the same to completion by contract or otherwise, making the contractor and his surety liable to the Government for any excess costs occasioned thereby.... | |
| |