(5) The procurement is classified; or (6) Labor surplus area concerns are receiving a fair proportion of contracts. (c) Procurement of supplies which were developed and financed in whole or in part by Canadian sources under the U.S.-Canadian Defense Development

Sharing Program shall not be set aside for labor surplus areas. Identification of the supplies covered by the Program will be in accordance with Departmental procedures.

[25 F.R. 14098, Dec. 31, 1960, as amended at 26 F.R. 9633, Oct. 12, 1961; 30 F.R. 14706, Nov. 9, 1965]

§ 1.804-2 Set-aside procedures.

(a) Where a portion of a procurement is to be set aside pursuant to § 1.804-1, the procurement shall be divided into a non-set-aside portion and set-aside portion, each of which shall be not less than an economic production run or reasonable lot. Insofar as practical, the setaside portion will be such as to make the maximum use of the capacity of labor surplus area concerns. Delivery terms and other terms applicable to the setaside portion of an item and those applicable to the non-set-aside portion of that item shall be comparable.

(b) In advertised procurements involving set-asides pursuant to this subpart, each invitation for bids shall contain substantially the following notice. In negotiated procurements, the notice shall be appropriately modified for use with requests for proposals. The notice shall be made a part of each contract under the set-aside portion of the procurement.

NOTICE OF LABOR SURPLUS AREA SET-ASIDE (NOVEMBER 1964)

(a) General. A portion of this procurement, as identified elsewhere in the Schedule, has been set aside for award only to one or more labor surplus area concerns, and, to a limited extent, to small business concerns which do not qualify as labor surplus area concerns. Negotiations for award of the setaside portion will be conducted only with responsible labor surplus area concerns (and small business concerns to the extent indicated below) who have submitted responsive bids or proposals on the non-set-aside portion at a unit price no greater than 120 percent of the highest unit price at which an award is made on the non-set-aside portion. Negotiations for the set-aside portion will be conducted with such bidders in the following order of priority:

Group 1. Persistent labor surplus area concerns which are also small business concerns.

Group 2. Other persistent labor surpl

area concerns.

Group 3. Substantial labor surplus are concerns which are also small business co

cerns.

Group 4. Other substantial labor surplu

area concerns.

Group 5. Small business concerns whic are not labor surplus area concerns. Within each of the above groups, negotia tions with such concerns will be in the orde of their bids on the non-set-aside portion beginning with the lowest responsive bi The set-aside portion shall be awarded at th highest unit price awarded on the non-set aside portion, adjusted to reflect transpor tation and other cost factors which are con sidered in evaluating bids on the non-set aside portion except where a responsive bi has been submitted on the non-set-asid portion at a unit price which when so ad justed is lower than the adjusted highes unit price awarded on the non-set-asid portion but could not be accepted becaus of quantity limitations or other considera tion (such as the bidder's responsibility In the latter case if the quantity limitation or other considerations do not preclude con sideration of the unit price of such un accepted bid at the time of negotiation fo the set-aside portion, a quantity of the set aside portion equal to the quantity of such unaccepted bid shall be offered to eligibl concerns in their order of priority at the ad justed unit price of such unaccepted bid If no eligible bidder will take the entire quantity so offered at the adjusted unit price of the unaccepted bid, then all eligible concerns in their order of priority shall be offered any lesser portion at the same price (In the event more than one such unaccepted bid is involved, the same procedure shall be applied successively to each such bid on negotiation for the set-aside portion.) Subject to the conditions set forth below any remaining quantity of the set-aside portion shall be offered to eligible concerns in their order of priority at the adjusted highest unit price awarded on the non-set-aside portion. If such an unaccepted bid is submitted by a concern eligible to participate in the setaside, such concern must accept a quantity of the set-aside portion equal to the quantity of the unaccepted bid at the adjusted unit price of the unaccepted bid before any portion of the set-aside may be awarded to that concern at a higher price. If such an unaccepted bid is submitted by a concern not eligible to participate in the set-aside, a quantity of the set-aside portion equal to the quantity of the unaccepted bid must be awarded at the adjusted unit price of such unaccepted bid before any portion of the setaside is awarded to any eligible concern at a higher price. The Government reserves the right not to consider token bids or other devices designed to secure an unfair advantage over other bidders eligible for the setaside portion.

(b) Definitions. (1) The term "labor surplus area" means a geographical area which is a persistent labor surplus area or a substantial labor surplus area, or both, as defined below:

(1) "Persistent labor surplus area" means an area which (A) is classified by the Department of Labor as an "Area of Substantial and Persistent Labor Surplus" (also called "Area of Substantial and Persistent Unemployment") and is listed as such by that Department in conjunction with its publication "Area Labor Market Trends," or (B) is certified as an area of substantial and persistent labor surplus by the Department of Labor pursuant to a request by a prospective contractor.

(ii) "Substantial labor surplus area" means an area which (A) is classified by the Department of Labor as an "Area of Substantial Labor Surplus" (also called "Area of Substantial Unemployment") and which is listed as such by that Department in conjunction with its publication "Area Labor Market Trends," or (B) is certified as an area of substantial labor surplus by the Department of Labor pursuant to a request by a prospective contractor.

(2) The term “labor surplus area concern" includes persistent labor surplus area concerns and substantial labor surplus area concerns as defined below:

(1) "Persistent labor surplus area concern" means a concern that agrees to perform, or cause to be performed, a substantial proportion of a contract in persistent labor surplus areas. A concern shall be deemed to perform a substantial proportion of a contract in persistent labor surplus areas if the costs that the concern will incur on account of manufacturing or production performed in such areas (by itself or its first-tier subcontractors) amount to more than 50 percent of the contract price.

(ii) "Substantial labor surplus area concern" means a concern that agrees to perform, or cause to be performed, a substantial proportion of a contract in substantial labor surplus areas. A concern shall be deemed to perform a substantial proportion of a contract in substantial labor surplus areas if the costs that the concern will incur on account of manufacturing or production performed in substantial and persistent labor surplus areas (by itself or its first-tier subcontractors) amount to more than 50 percent of the contract price.

(3) A "small business concern" is a concern, including its affiliates, which is independently owned and operated, is not dominant in the field of operation in which it is bidding on Government contracts, and can > further qualify under the criteria set forth in regulations of the Small Business Administration (Code of Federal Regulations, Title 13, Section 121.3-8). In addition to meeting these criteria, a manufacturer or a regular dealer submitting bids or proposals in his own name must agree to furnish in the performance of the contract end items manu

factured or produced in the United States, its possessions, or Puerto Rico, by small business concerns: Provided, That this additional requirement does not apply in connection with construction or service contracts.

(4) "Unit price" shall include evaluation factors added for the rent-free use of Government property.

(c) Identification of areas of performance. Each bidder desiring to be considered for award as a labor surplus area concern on the set-aside portion of this procurement shall identify in his bid the geographical areas in which he proposes to perform, or cause to be performed, a substantial proportion of the production of the contract. If the Department of Labor classification of any such area changes after the bidder has submitted his bid, the bidder may change the areas in which he proposes to perform, provided, that he so notifies the Contracting Officer before award of the set-aside portion. Priority for negotiation will be based upon the labor surplus classification of the designated production areas as of the time of the proposed award.

(d) Agreement. The bidder agrees that, if awarded a contract as a persistent labor surplus area concern under the set-aside portion of this procurement, he will perform, or cause to be performed, a substantial proportion of the production in areas classified at the time of award, or at the time of performance of the contract, as persistent labor surplus areas; and that if awarded a contract as a substantial labor surplus area concern under the set-aside portion of this procurement, he will perform, or cause to be performed, a substantial proportion of the production in areas classified at the time of award, or at the time of performance of the contract, as substantial or persistent labor surplus areas.

(c) (1) After the award price for the non-set-aside portion has been determined, negotiations may be conducted for the set-aside portion. Procurement of the set-aside portion shall in all instances be effected by negotiation. Negotiations shall be conducted only with those bidders or offerors who have submitted responsive bids or proposals on the non-set-aside portion at a unit price no greater than 120 percent of the highest award made or to be made on the non-set-aside portion (taking into account the evaluation factors for rent-free use of Government property pursuant to Subpart E, Part 13 of this chapter) and who are determined to be responsible prospective contractors for the set-aside portion of the procurement. Negotiations shall be conducted in the order of priority indicated in the foregoing notices: Provided, That, where equal low bids are received on the non-set-aside

portion from concerns which are equally eligible for the set-aside portion, the concern which is awarded the non-set-aside portion (under the equal low bid procedures of § 2.407-6 of this chapter) shall have first priority with respect to negotiations for the set-aside portion. The set-aside portion shall be awarded at the highest unit price awarded or to be awarded for the non-set-aside portion. A bidder or offeror entitled to receive the award for quantities of an item under the non-set-aside portion and who accepts the award of additional quantities under the set-aside portion shall not be requested to accept a lower price because of the increased quantities of the award, nor shall negotiation be conducted with a view to obtaining such a lower price based solely upon receipt of award of both portions of the procurement. This does not prevent acceptance by the contracting officer of voluntary reductions in price prior to award, acceptance of refunds, or the change of prices after award by negotiation of a contract modification. If the entire set-aside portion cannot be awarded by the method described herein, any unawarded portion may be procured by advertising or negotiations, as appropriate, in accordance with existing regulations (see §§ 3.201-2 (b) (1) and 3.210-3 of this chapter as to negotiation).

(2) When the award price for a nonset-aside portion has been determined and where an award will be made to a labor surplus area concern and the same labor surplus area concern is entitled to receive a set-aside portion of the solicitation, the set-aside portion may be added to the basic contract by supplemental agreement. The supplemental agreement shall include the Examination of Records clause, applicable to the setaside portion only.

[25 F.R. 14098, Dec. 31, 1960, as amended at 29 F.R. 2818, Feb. 29, 1964; 30 F.R. 1731, Feb. 9, 1965; 30 F.R. 14706, Nov. 9, 1965]

§ 1.804-3 Withdrawal of set-asides.

If, prior to the award of a contract involving a labor surplus set-aside, the contracting officer considers that the set-aside is detrimental to the public interest, e.g., because of unreasonable prices, the contracting officer shall withdraw the set-aside and complete the procurement by advertising or negotiation as appropriate in accordance with existing regulations. A signed memorandum setting forth the basis of the

withdrawal of any set-aside shall be made and retained.

[25 F.R. 14100, Dec. 31, 1960]

§ 1.804-4 Contract authority.

Contracts for set-asides made under this Subpart H shall cite as authority 10 U.S.C. 2304(a)(1). For reporting purposes, see §3.201-2(b) (1) of this chapter for contracts awarded to labor surplus area concerns and §3.201-2 (b) (2) for contracts awarded to small business concerns which are not labor surplus area concerns.

[25 F.R. 14100, Dec. 31, 1960]

§ 1.805

Subcontracting with labor surplus area concerns.

[27 F.R. 3445, Apr. 11, 1962]

§ 1.805-1 General policy.

It is the policy of the Government to promote equitable opportunities for labor surplus area concerns to compete for defense subcontracts and to encourage placement of subcontracts with concerns which will perform such contracts substantially in areas of persistent or substantial labor surplus, in the order of priority described in § 1.802 where this can be done, consistent with efficient performance of contracts, at prices no higher than are obtainable elsewhere. [27 F.R. 3445, Apr. 11, 1962]

§ 1.805-2 Labor surplus area subcontracting program.

The Government's labor surplus area subcontracting program requires Government prime contractors to assume an affirmative obligation with respect to subcontracting with labor surplus area concerns. In contracts which range from $5,000 to $500,000, the contractor undertakes the simple obligation of using his best efforts to place his subcontracts with concerns which will perform such subcontracts substantially in areas of persistent or substantial labor surplus where this can be done, consistent with the efficient performance of the contract, at prices no higher than are obtainable elsewhere. This undertaking is set forth in the contract clause prescribed in § 1.805-3(a). In contracts which may exceed $500,000, the contractor is required, pursuant to the clause set forth in § 1.805-3 (b), to undertake a number of specific responsibilities designed to insure achievement of the objectives referred to above and to impose

[blocks in formation]

(a) The "Utilization of Concerns in Labor Surplus Areas" clause set forth below shall be inserted in all contracts in amounts which may exceed $5,000, except:

(1) Contracts with foreign contractors which, including all subcontracts thereunder, are to be performed entirely outside the United States, its possessions, and Puerto Rico;

(2) Contracts for services which are personal in nature; and

(3) Contracts for construction.

UTILIZATION OF CONCERNS IN LABOR SURPLUS AREAS (FEB. 1962)

It is the policy of the Government to place contracts with concerns which will perform such contracts substantially in areas of persistent or substantial labor surplus where this can be done, consistent with the efficient performance of the contract, at prices no higher than are obtainable elsewhere. The Contractor agrees to use his best efforts to place his subcontracts in accordance with this policy. In complying with the foregoing and with paragraph (b) of the clause of this contract entitled "Utilization of Small Business Concerns," the Contractor in placing his subcontracts shall observe the following order of preference: (1) Persistent labor surplus area concerns which are also small business concerns; (ii) other persistent labor surplus area concerns; (iii) substantial labor surplus area concerns which are also small business concerns; (iv) other substantial labor surplus area concerns; and (v) small business concerns which are not labor surplus area concerns.

(b) The "Labor Surplus Area Subcontracting Program" clause below shall be included in all contracts which may exceed $500,000, but which contain the s clause required by paragraph (a) of this section and which, in the opinion of the purchasing activity, offer substantial subcontracting possibilities. Prime contractors who are to be awarded con=tracts that do not exceed $500,000, which in the opinion of the purchasing activity offer substantial subcontracting possibilities, shall be urged to accept the following clause:

LABOR SURPLUS AREA SUBCONTRACTING PRO-
GRAM (FEB. 1962)

(a) The Contractor agrees to establish and conduct a program which will encourage labor surplus area concerns to compete for

91

subcontracts within their capabilities. In this connection, the Contractor shall:

(1) Designate a liaison officer who will (1) maintain liaison with duly authorized representatives of the Government on labor surplus area matters, (11) supervise compliance with the "Utilization of Concerns in Labor Surplus Areas" clause, (iii) administer the Contractor's Labor Surplus Area Subcontracting Program;

(2) Provide adequate and timely consideration of the potentialities of labor surplus area concerns in all "make-or-buy" decisions;

(3) Assure that labor surplus area concerns will have an equitable opportunity to compete for subcontracts, particularly by arranging solicitations, time for the preparation of bids, quantities, specifications, and delivery schedules so as to facilitate the participation of labor surplus area concerns;

(4) Maintain records showing procedures which have been adopted to comply with the policies set forth in this clause; and

(5) Include the "Utilization of Concerns in Labor Surplus Areas" clause in subcontracts which offer substantial labor surplus area subcontracting opportunities.

(b) A "labor surplus area concern" is a concern which will perform, or cause to be performed, a substantial proportion of any contract awarded to it in "Areas of Substantial and Persistent Labor Surplus" or in "Areas of Substantial Labor Surplus," as designated by the Department of Labor. A concern shall be deemed to perform a substantial proportion of a contract in a labor surplus area if the costs that the concern will incur on account of manufacturing or production (by itself or its first-tier subcontractors) in such areas amount to more than 50 percent of the price of such contract.

(c) The Contractor further agrees, with respect to any subcontract hereunder which is in excess of $500,000 and which contains the clause entitled "Utilization of Concerns in Labor Surplus Areas," that he will insert provisions in the subcontract which will conform substantially to the language of this clause, including this paragraph (c), and that he will furnish the names of such subcontractors to the Contracting Officer. [27 F.R. 3445, Apr. 11, 1962]

§ 1.805-4 Responsibility for reviewing subcontracting program.

Only one Department shall be responsible for reviewing a contractor's labor Surplus Area Subcontracting Program. Departmental responsibility shall be assigned and carried out in accordance with § 1.707-4.

[27 F.R. 3445, Apr. 11, 1962]

§ 1.806 Depressed industries. [25 F.R. 14100, Dec. 31, 1960]

[blocks in formation]

If the entire set-aside portion is not procured by the method set forth in § 1.706-5, as to total set-asides, or in § 1.706-6, as to partial set-asides, the determination referred to in § 1.706-1 is automatically dissolved as to the unawarded portion of the set-aside and such unawarded portion may be procured by advertising or negotiation as appropriate in accordance with existing regulations (see §§3.201–2(b) (2) 3.210-3 of this chapter as to negotiation). [28 FR. 12547, Nov. 23, 1963]

§ 1.707

and

Subcontracting with small busi

ness concerns.

[27 FR. 3443, Apr. 11, 1962]

§ 1.707-1 General.

(a) It is the policy of the Government to enable small business concerns to be considered fairly as subcontractors to contractors performing work or rendering services as prime contractors or subcontractors under Government procurement contracts, and to assure that prime contractors and subcontractors having small business subcontracting programs will consult through the purchasing activity with the SBA at its request.

(b) The SBA is not authorized, however, to prescribe the extent to which any contractor or subcontractor shall subcontract or specify the concerns to which subcontracts shall be granted, nor does it vest in SBA authority respecting the administration of individual prime contracts or subcontracts.

[27 F.R. 3443, Apr. 11, 1962]

[blocks in formation]

In contracts which range from $5,000 to $500,000, the contractor undertakes the obligation of accomplishing the maximum amount of small business subcontracting which is consistent with the efficient performance of the contract. This undertaking is set forth in the contract clause prescribed in § 1.707-3(a). In contracts which may exceed $500,000, the contractor is required, pursuant to the clause set forth in § 1.707-3 (b) to undertake a number of specific responsibilities designed to assure that small business concerns are considered fairly in the subcontracting role and to impose similar responsibilities on major subcontractors. (The liaison officer required by the latter clause may also serve as liaison officer for labor surplus area matters.) [27 F.R. 3443, Apr. 11, 1962]

§ 1.707-3 Required clauses.

(a) The "Utilization of Small Business Concerns" clause below shall be included in all contracts in amounts which may exceed $5,000 except (1) contracts which, including all subcontracts thereunder, are to be performed entirely outside the United States, its possessions, and Puerto Rico; and (2) contracts for services which are personal in nature: UTILIZATION OF SMALL BUSINESS CONCERNS (JAN. 1958)

(a) It is the policy of the Government as declared by the Congress that a fair proportion of the purchases and contracts for supplies and services for the Government be placed with small business concerns.

(b) The Contractor agrees to accomplish the maximum amount of subcontracting to small business concerns that the Contractor finds to be consistent with the efficient performance of this contract.

(b) The "Small Business Subcontracting Program" clause below shall be included in all contracts (except maintenance, repair and construction contracts) which may exceed $500,000, which contain the clause required by paragraph (a) of this section and which, in the opinion of the contracting officer, offer substantial subcontracting possibilities. Prime contractors who are to be awarded contracts that do not exceed $500,000 but which, in the opinion of the contracting officer, offer substantial subcontracting possibilities, shall be urged to accept the clause.

SMALL BUSINESS SUBCONTRACTING PROGRAM (JUNE 1965)

(a) The Contractor agrees to establish and conduct a small business subcontracting pro

« PreviousContinue »