VCR-78-123 2.15.4 Open Issues 2.16 2.16.1 Open issues pertaining to the VAFB Launch Processing System Station Set are listed below. Resolution of these issues is planned during the integration contract. a. The remaining VLPS procurements must be finalized for NASA incorporation into their vendor contracts. The agreed to date for data delivery to NASA is 1 September 1978. b. The quantity and use of Type III consoles is to be based on an approved operations concept. This is driven by 2.1.4.1. c. The quantity and type of engineering terminals is complete for the software development phase, however, the need during the operational phase is not yet complete. The current estimate is that these will be available by relocating selected terminals originally used for software development. Station Set V86, Utilities Current Baseline The Utilities Station Set primarily provides the STS Program at VAFB with electrical power from the existing VAFB power system as modified by the Utilities Station Set. The modifications provide a 69 KV loop transmission system through substation "B" on North VAFB and duplex 12.47 KV distribution feeders to the Orbiter processing area and to Building 8510. A similar loop is provided to South VAFB with duplex transformers at substation "N" and in addition power line to SLC-6 area for duplex service to V23 and V28. Implementation alterations will encompass relocation of power lines, addition of protections and disconnect circuitry to maximize system reliability and enable line disconnect in event of overload or circuit malfunction on one of two feeder circuits. This station set also provides a sewage lift station, connections to VCR-78-123 2.16.2 Utilities Station Set Significant Changes/Accomplishments Significant changes implemented in the Utilities Station Set (V86) during the FY 76/78 GSS contract are presented in Table 2.16.2. Baseline documentation representing the allocated requirements baseline for V86 is presented in Table 2.16.3. 2.17 2.17.1 VCR-78-123 Open issues pertaining to the Utilities Station Set (V86) are listed below. Resolution of these issues is planned during the integration contract. a. Resolution of reliability requirements. Station Set V88, Logistics (Supply and Maintenance) Current Baseline The Logistics Station Set provides material management and Line The Logistics Station Set uses facilities on North VAFB as the cen- |