" In the event that Governmentfurnished Property Is not delivered to the Contractor by such time or times, the Contracting Officer shall, upon timely written request made by the Contractor, make a determination of the delay occasioned the Contractor thereby,... "
The Code of Federal Regulations of the United States of America - Page 253
1965
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 148

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1962 - 784 pages
...or performance dates, or price, or both, and in any other contractual provision affected thereby, in accordance with the procedures provided for in the clause of this contract entitled "Changes". * * * * * 2. CHANGES The Contracting Officer may at any time, by a written order, and without notice...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1965 - 670 pages
...or modification to such items. The Schedule will identify the "Air Force equipment upon which work is to be performed" as distinct from Government-furnished...purposes of the clause set forth in paragraph (a) of this section, the paragraph (f ) of ! 13.502 of this title applicable to advertised procurements may be...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1964 - 676 pages
...contractual provision affected by such delay, in accordance with the procedures provided for in the clause ot this contract entitled "Changes." ** Change "contract...purposes of the clause set forth in paragraph (a) of this section, the paragraph (f ) of § 13.502 of this title applicable to advertised procurements may be...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1960 - 672 pages
...occasioned the Contractor thereby, and shall equitably adjust the delivery, performance, or completion dates or the contract price or both, and any other...In the clause of this contract entitled "Changes." In the event the Governmentfurnished Property Is received by the Contractor In a condition not suitable...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1982 - 400 pages
...of the delay occasioned the Contractor thereby, and shall equitably adjust the hours of operation or contract price or both and any other contractual provision...in the clause of this contract entitled "Changes." (b) Except for the fixtures and facilities listed in Attachment A, the Contractor, upon delivery to...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1965 - 1168 pages
...cost, fixed fee, or delivery or performance dates, or all of them, and any other contractual provisions affected by such delay. In accordance with the procedures...in the clause of this contract entitled "Changes." In the event that Government-furnished Property is received by the Contractor in a condition not suitable...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1968 - 456 pages
...delivery or performance dates, or all of them, and any other contractual provisions affected by any such delay, in accordance with the procedures provided...in the clause of this contract entitled "Changes." In the event that Government-furnished property is received by the Contractor in a condition not suitable...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1976 - 864 pages
...performance dates, or the contract price, or all of them, and any other contractual provision affected by any such delay. In accordance with the procedures provided...in the clause of this contract entitled "Changes". Except for Governmentfurnished property furnished "as IB", In the event the Government-furnished property...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1982 - 1316 pages
...performance dates or the contract price, or both, and any other contractual provision affected by any such delay, in accordance with the procedures provided for in the clause of this contract entitled "Chanfes." Except for Governmenrfurnished property furnished "as-is". in the event the Government-furnished...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1981 - 676 pages
...or • performance dates, or all of them, and any other contractual provisions affected by anysuch delay, in accordance with the procedures provided...in the clause of this contract entitled "Changes." In the event that Government-furnished property is received by the Contractor in a condition not suitable...