" The Contractor shall promptly, and before such conditions are disturbed, notify the Contracting Officer In writing of: (1) subsurface or latent physical conditions at the site differing materially from those Indicated in this contract, or (2) unknown... "
The Code of Federal Regulations of the United States of America - Page 168
1967
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1981
...shall be allowed if asserted after final payment under this contract. 4. DIFFERING SITE CONDITIONS (a) The Contractor shall promptly, and before such conditions...indicated in this contract, or (2) unknown physical condition* at the site, of an tin* usual nature, differing materially from those ordinarily encountered...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1976
...4-18.5104 Differing site condition*. (a) Contract provisions. Clause 4 of Standard Form 23A provides that the contractor shall promptly, and before such conditions...site differing materially from those indicated in the contract, or (2) unknown physical conditions at the site of an unusual nature, differing materially...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1978
...payment under this contract. 1-7.602-4 Differing site conditions. DIFFERING SITE CONDITIONS (a) The Contractor shall promptly, and before such conditions...conditions at the site differing materially from those indiTitle 41 — Public Contracts, Property Management rated in this contract, or (2) unknown physical...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1969
...construction contracts. (a) Contract provisions. Cause 4 of Standard Form 23A provides that the sontractor shall promptly, and before such conditions are disturbed,...site differing materially from those Indicated in the contract, or (2) unknown physical conditions at the site of an unusual nature, differing materially...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1982
...subagreements.) (a) The contractor shall promptly, and before such conditions are disturbed, notify the recipient in writing of: (1) subsurface or latent physical conditions...differing materially from those indicated in this subagreement, or (2) unknown physical conditions at the site, of an unusual nature, differing materially...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1994
...to the Contracting Officer of (1) subsurface or latent physical conditions at the site which differ materially from those Indicated In this contract,...physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering In work...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1996
...to the Contracting Officer of (1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract,...physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1964
...physical conditions at the tite differ* inf materially from those indicated in this contract, or (b) unknown physical conditions at the site, of an unusual...differing materially from those ordinarily encountered and Cencnliy recognized as inhering in work of the character provided for in this contract. The Contracting...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1969
...provided in this contract, no charge for any extra work or material will be allowed. 4. CHANGED CONDITIONS The Contractor shall promptly, and before such conditions...disturbed, notify the Contracting Officer in writing of: (a) subsurface or latent physical conditions at the site differing materially from those indicated...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1969
...promptly, and before such conditions are disturbed, notify the Contracting Officer in writing of: (a) subsurface or latent physical conditions at the site...materially from those indicated in this contract, or (b) unknown physical conditions at the site, of an unusual nature, differing materially from those...