Cases Decided in the Court of Claims of the United States, Volume 105U.S. Government Printing Office, 1946 - Law reports, digests, etc |
From inside the book
Results 1-5 of 100
Page xviii
... Interior shall decree that there shall be paid to the attor- ney or attorneys employed therein by said plaintiff ... Interior be in excess of the amount stipulated in the contracts ap- proved by the Commissioner of Indian Affairs and the ...
... Interior shall decree that there shall be paid to the attor- ney or attorneys employed therein by said plaintiff ... Interior be in excess of the amount stipulated in the contracts ap- proved by the Commissioner of Indian Affairs and the ...
Page xix
... Interior under which such suit , cause , or action is instituted and the tribal funds of the Ute Indians repre- sented in such suit , cause , or action are hereby made avail- able for expenditure for that purpose . ' Approved June 11 ...
... Interior under which such suit , cause , or action is instituted and the tribal funds of the Ute Indians repre- sented in such suit , cause , or action are hereby made avail- able for expenditure for that purpose . ' Approved June 11 ...
Page 36
... Interior , who was the head of the department which had made the contract , a number of claims for addi- tional compensation . These claims were referred by the head of the department to the contracting officer , to whom , under Article ...
... Interior , who was the head of the department which had made the contract , a number of claims for addi- tional compensation . These claims were referred by the head of the department to the contracting officer , to whom , under Article ...
Page 37
... Interior which contained the respective differing views of the parties as to the proper approach and speed for the consideration of the claims then pending before the contracting officers . In a letter dated August 11 , 1938 , from ...
... Interior which contained the respective differing views of the parties as to the proper approach and speed for the consideration of the claims then pending before the contracting officers . In a letter dated August 11 , 1938 , from ...
Page 38
... Interior , as follows : For and on behalf of Silas Mason Company , Inc. , Walsh Construction Company and Atkinson - Kier Com- pany , contractors for the first unit of the Grand Coulee Dam ( Symbol No. 12r - 4359 ) , appeal is hereby ...
... Interior , as follows : For and on behalf of Silas Mason Company , Inc. , Walsh Construction Company and Atkinson - Kier Com- pany , contractors for the first unit of the Grand Coulee Dam ( Symbol No. 12r - 4359 ) , appeal is hereby ...
Other editions - View all
Common terms and phrases
act of March additional agency agreed agreement amended amount appropriated April Article bands borrow pit building change order Cheyenne River Commissioner compensation completion construction contracting officer contractor Corporation cost December deductions defendant defendant's delay Department disbursements dredging entitled to recover excavation expenditures expense February February 28 filed follows furnished Government Grand Ronde Reservation installation Interior January July July 29 June 30 labor land letter liquidated damages Lower Brulé material ment Murch Company November Opinion oysters paid payment percent period permanent fund Pine Ridge Pine Ridge Reservation plaintiff plaster proceed proposal Quonset Point raw silk Rayon refund reimbursement Reporter's Statement requested Rogue River Tribe rolled fill Rosebud Scoton Sioux Tribe South Dakota south of Quonset specifications Standing Rock Reservation Stat stone submitted Surety thereof tion Treasury treaty TRIBE OF INDIANS Umpquas United within-city
Popular passages
Page 475 - Every claim against the United States cognizable by the Court of Claims, shall be forever barred unless the petition setting forth a statement thereof is filed in the court, or transmitted to it by the Secretary of the Senate or the Clerk of the House of Representatives, as provided by law, within six years after the claim first accrues...
Page 137 - ... unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, in either its sovereign or contractual capacity, a,cts of another contractor in the performance of a contract with the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather, or delays of subcontractors or suppliers due to such causes...
Page 138 - Contractor charged with liquidated or actual damages, as provided in paragraph (b) hereof because of any delays in the completion of the work due to unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government...
Page 635 - Where at any time the power to revest in the grantor title to any part of the corpus of the trust is vested — (1) in the grantor, either alone or in conjunction with any person not having a substantial adverse interest...
Page 100 - The delay in the completion of the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor...
Page 673 - Court to hear and determine the claims listed on page 678 of the hearings before the subcommittee of the House Committee on Appropriations on the...
Page 101 - Disputes. — Except as otherwise specifically provided in this contract, all disputes concerning questions of fact arising under this contract shall be decided by the contracting officer subject to written appeal by the contractor within 30 days to the head of the department concerned or his duly authorized representative, whose decision shall be final and conclusive upon the parties thereto. In the meantime the contractor shall diligently proceed with the work as directed.
Page 508 - Into lots, and assign the same to such individuals or families of the said confederated tribes as are willing to avail themselves of the privilege, and will locate on the same as a permanent home, on the same terms and subject to the same regulations...
Page 134 - ... the Government may, by written notice to the contractor, terminate his right to proceed with the work or such part of the work as to which there has been delay.
Page 793 - States, to admit amongst them; and the United States now solemnly agrees that no persons except those herein designated and authorized so to do, and except such officers, agents, and employees of the Government as may be authorized to enter upon Indian reservations in discharge of duties enjoined by law, shall ever be permitted to pass over, settle upon, or reside in the territory described in this article...