Military Construction Appropriations for 1982: Hearings Before a Subcommittee of the Committee on Appropriations, House of Representatives, Ninety-seventh Congress, First Session

Front Cover

From inside the book

Other editions - View all

Common terms and phrases

Popular passages

Page 539 - Disputes" clause of this contract. (e) If, after notice of termination of the Contractor's right to proceed under the provisions of this clause, it is determined for any reason that the Contractor was not in default under the provisions of this clause...
Page 539 - In the completion of the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, Including but not restricted to, acts of God, acts of the public enemy, acts of the Government In either Its sovereign or contractual capacity, acts of another contractor In the performance of a contract with the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, unusually severe weather, or delays of subcontractors or suppliers...
Page 539 - Officer grants a further period of time before the date of final payment under the contract) , notifies the Contracting Officer in writing of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of the delay and extend the time for completing the work when, in his judgment, the findings of fact justify such an...
Page 539 - If, after notice of termination of this contract under the provisions of this clause, it is determined for any reason that the Contractor was not in default under the provisions of this clause, or that the default was excusable under the provisions of this clause, the rights and obligations of the parties shall, if the contract contains a clause providing for termination for convenience of the Government, be the same as If the notice of termination had been issued pursuant to such clause.
Page 295 - Francis S. Greenlief , Executive Vice President of the National Guard Association of the United States. I appreciate the opportunity to present the views of our membership on military construction for the National Guard.
Page 539 - The delay in the completion of the work arises from unforseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, acts of the public enemy, acts of the Government in either its sovereign or contractual capacity, acts of another contractor in the performance of a contract with...
Page 539 - Officer shall grant a further period of time prior to the date of final settlement of the contract, notify the Contracting Officer in writing of the causes of delay.
Page 539 - Contractor's right to proceed, the resulting damage will consist of such liquidated damages until such reasonable time as mav be required for final completion of the work together with any increased costs occasioned the Government in completing the work. (c) If fixed and agreed liquidated damages are provided in the contract and if the Government does not so terminate the Contractor's right to proceed, the resulting damage will consist of such liquidated damages until the work is lornpit-ted or accepted.
Page 145 - Government agency, and shall be awarded, insofar as practicable, on a competitive basis to the lowest responsible bidder, if the national security will not be impaired and the award is consistent with chapter 137 of title 10, United States Code.
Page 293 - National Guard Bureau, on 3 November 1962. General Greenlief was appointed as Deputy Chief, National Guard Bureau, on 14 September 1963 and was promoted to major general on 9 February 1965. On 13 September 1967, he was extended for an additional four-year term. On 20 April 1970, he was appointed Director, Army National Guard in addition to his duties as Deputy Chief, National Guard Bureau.

Bibliographic information