nomically feasible due to design or special circumstances.

[46 FR 59903, Dec. 7, 1981, as amended at 54 FR 52894, Dec. 22, 1989]

§ 503.11 Alternative sites-general requirement for permanent exemptions for new powerplants.

(a) Criteria. To qualify for permanent exemption due to lack of alternate fuel supply, site limitations, environmental requirements, or inadequate capital, section 212(a) of the Act requires a demonstration that one of these exemptions would be available for any reasonable alternative site for the facility.

(b) Evidence. The petition must include the following evidence in order to make the demonstration required by this section:

(1) Duly executed certifications to the criteria set forth in paragraph (a) of this section; and

(2) Exhibits containing the basis for the certifications submitted under this section (including those factual and analytical materials deemed by the petitioner to be sufficient to support its certifications to this general requirement).

[46 FR 59903, Dec. 7, 1981, as amended at 54 FR 52894, Dec. 22, 1989]

§ 503.12 Terms and conditions; compliance plans.

(a) Terms and conditions generally. A petitioner must comply with any terms and conditions imposed upon the grant of an exemption petition. OFE will limit any such terms and conditions to the unit(s) which is the subject of the petition.

(b) Compliance plans for temporary exemptions. (1) Any compliance plan required to accompany a petition for a temporary exemption shall include the following:

(i) A detailed schedule of progressive events and the dates upon which the events are to take place, indicating how compliance with the applicable prohibitions of the Act will occur;

(ii) Evidence of binding contracts for fuel, or for facilities for the production of fuel, which are required for compliance with the applicable prohibitions of the Act;

(iii) A schedule indicating how any necessary permits and approvals required to burn an alternate fuel will be obtained; and

(iv) Any other documentary evidence which indicates an ability to comply with the applicable prohibitions of the Act.

(2) Any exemption for which a compliance plan is required shall not be effective until the compliance plan is approved by DOE.

(3) If the petition is granted, an updated, duly executed plan must be submitted to OFE within one (1) month of an alteration of any milestone in the compliance plan, together with the reasons for the alteration and its impact upon the scheduling of all other milestones in the plan.

§ 503.13 Environmental impact analysis.

In order to enable OFE to comply with NEPA, a petitioner must include the information indicated in this section if a permanent exemption is requested. Material which has been prepared pursuant to any Federal, State or local requirement for environmental information for this unit or site may be incorporated by reference and appended to the petition. Guidelines issued by OFE for environmental reports should be used in preparing this analysis (44 FR 63740, November 5, 1979). These guidelines, which are also available in the OFE public document room, have been designed to insure that environmental reports follow the format prescribed by Council on Environmental Quality final regulations implementing NEPA. The guidelines are subject to discussion at a prepetition conference and to modification according to the facts of a particular case.

(a) All petitions for permanent exemptions must contain the following information:

(1) A description of the facility, including site location, and surroundings, alternative site(s), the facility's current proposed operations, its fuel capability, and its pollution abatement systems and equipment (including those systems and equipment necessary for all fuel scenarios considered);

(2) A description of the existing environment, including air, water, and land resources;

(3) Direct and indirect environmental impacts of the proposed action including impacts of alternative fuel scenarios, and no build alternatives.

(4) Regulatory requirements governing the facility, including a description of Federal, State and local requirements for air, water, noise and solid waste disposal which must be met for each fuel considered.

(b) For exemptions for cogeneration, the information enumerated below is to be submitted in lieu of the information required by paragraph (a) of this section. However, submission of the following information merely establishes a rebuttable presumption that the grant or denial of the exemption would have no significant environmental impact. OFE may, in individual cases, during the course of the administrative proceeding, determine that additional environmental information is required. In such cases, the petitioner will be required to submit the information described in paragraph (a) of this section.

(1) A certification that the petitioner will, prior to operating the unit under the exemption, secure all applicable environmental permits and approvals pursuant to, but not limited to, the following: Clean Air Act, Rivers and Harbors Act, Coastal Zone Management Act, Safe Drinking Water Act, Resource Conservation and Recovery Act; and

(2) Information required by the following environmental checklist must be provided and certified as accurate:

Environmental Checklist for FUA Certification Exemptions Instructions

All questions are to be answered by placing a check in the appropriate box. N/A represents (not applicable). Although it is not required, the petitioner may elaborate on any question in writing on a separate sheet of paper.

[blocks in formation]

(3) Will your facility affect a designated wild, scenic, or recreation river (Wild and Scenic Rivers Act)?

(4)(A) Is your facility located within a county in which critical habitat for threatened or endangered species are known to exist (Endangered Species Act)?

(4)(B) Has a qualified biologist determined that your facility will not affect any species on the Threatened and Endangered Species list?

(5) Is your facility located on, or will it affect land that has been classified as prime or unique farmland or rangeland by the U.S. Department of Agriculture?

(6) Is your facility located on, or will it affect, historical archaeological, or cultural resources that have been designated pursuant to the National Historic Preservation Act?

[blocks in formation]

[46 FR 59903, Dec. 7, 1981, as amended at 47 FR 15315, Apr. 9, 1982; 51 FR 18866, May 22, 1986; 52 FR 658, Jan. 7, 1987; 54 FR 52894, Dec. 22, 1989]

§ 503.14 Fuels search.

Prior to submitting a petition for a permanent exemption for lack of alternate fuel supply, site limitations, inadequate capital, or state or local requirements, a petitioner must examine the use of conventional solid coal as a primary energy source at the site under consideration, and at reasonable alternative sites. Where a petitioner believes that its use of such coal would be infeasible, however, and where OFE and the petitioner can reach accord, it may evaluate use of a different alternate fuel in lieu of solid coal. A petitioner of these exemptions must demonstrate for any fuel examined that he would qualify for an exemption.

[54 FR 52894, Dec. 22, 1989]

Subpart C-Temporary
Exemptions for New Facilities

§ 503.20 Purpose and scope.

(a) This subpart implements the provisions contained in section 211 of the Act with regard to temporary exemptions for new facilities.

(b) This subpart establishes the criteria and standards which owners or operators of new powerplants who petition for a temporary exemption must meet to sustain their burden of proof under the Act.

(c) All petitions for temporary exemptions shall be submitted in accordance with the procedures set out in part 501 of this chapter and the applicable requirements of part 503 of these regulations.

(d) The duration of any temporary exemption granted under this subpart shall be measured from the date that the facility is placed in service using petroleum or natural gas.

[46 FR 59903, Dec. 7, 1981, as amended at 54 FR 52894, Dec. 22, 1989]

§ 503.21 Lack of alternate fuel supply.

(a) Eligibility. Section 211(a)(1) of the Act provides for a temporary exemption due to the unavailability of an adequate and reliable supply of an alternate fuel at a cost which does not substantially exceed the cost of using imported petroleum. To qualify, a petitioner must certify that:

(1) A good faith effort has been to obtain an adequate and reliable supply of an alternate fuel of the quality necessary to conform to the design and operational requirements of the unit;

(2) For the period of the proposed exemption, the cost of using such alternate fuel would substantially exceed the cost of using imported petroleum as a primary energy source as defined in § 503.6 (Cost calculation) of these regulations;

(3) The petitioner will be able to comply with the applicable prohibitions of the Act at the end of the proposed exemption period; and

(4) No alternate power supply exists, as required under §503.8 of these regulations.

(b) Evidence required in support of a petition. The petition must include the following evidence in order to make the demonstration required by this section:

(1) Duly executed certifications required under paragraph (a) of this section;

(2) Exhibits containing the basis for the certifications required under paragraph (a) of this section (including

those factual and analytical materials deemed by the petitioner to be sufficient to support the granting of this exemption);

(3) All data required by §503.6 (cost calculation) of these regulations necessary for computing the cost calculation formula; and

(4) The anticipated duration of the lack of alternate fuel supply which constitutes the basis for the exemption.

(c) Duration. This temporary exemption, taking into account any extensions or renewals, may not exceed 10 years.

[46 FR 59903, Dec. 7, 1981, as amended at 47 FR 15315, Apr. 9, 1982; 54 FR 52894, Dec. 22, 1989]

§ 503.22 Site limitations.

(a) Eligibility. Section 211(a)(2) of the Act provides for a temporary exemption due to a site limitation. To qualify for such an exemption, a petitioner must certify that:

(1) One or more specific physical limitations relevant to the location or operation of the proposed facility exist which, despite diligent good faith efforts, cannot be overcome before the end of the proposed exemption period;

(2) The petitioner will be able to comply with the applicable prohibitions of the Act at the end of the proposed exemption period; and

(3) No alternate power supply exists, as required under §503.8 of these regulations.

NOTE: Examples of the types of site limitations to which a petitioner may certify in order to qualify for this exemption include:

(i) Inaccessability of alternate fuels as a result of a specific physical limitation;

(ii) Unavailability of transportation facilities for alternate fuels;

(iii) Unavailability of adequate land or facilities for handling, using, or storing an alternate fuel;

(iv) Unavailability of adequate land or facilities for controlling and disposing of wastes, including pollution control equipment or devices necessary to assure compliance with applicable environmental requirements;

(v) Unavailability of adequate and reliable supply of water, including water

for use in compliance with applicable environmental requirements; or

(vi) Other site limitations exist which will not permit the location or operation of the proposed unit using an alternate fuel.

(b) Evidence required in support of a petition. The petition must include the following evidence in order to make the demonstration required by this section:

(1) Duly executed certifications required under paragraph (a) of this section;

(2) Exhibits containing the basis for the certifications required under paragraph (a) of this section (including those factual and analytical materials deemed by the petitioner to be sufficient to support the granting of this exemption); and

(3) The anticipated duration of the site limitation which constitutes the basis for the exemption.

(c) Duration. This temporary exemption, taking into account any extensions and renewals, may not exceed five years.

[46 FR 59903, Dec. 7, 1981, as amended at 54 FR 52894, Dec. 22, 1989]

§ 503.23 Inability to comply with applicable environmental requirements. (a) Eligibility. Section 211(a)(3) of the Act provides for a temporary exemption due to an inability to comply with applicable environmental requirements. To qualify a petitioner must demonstrate that despite diligent good faith efforts:

(1) The petitioner will be unable, as of the projected date of commencement of operation, to comply with the applicable prohibitions of the Act without violating applicable Federal or State environmental requirements; and

(2) The petitioner will be able to comply with the applicable prohibitions of the Act and with applicable environmental requirements by the end of the temporary exemption period.

NOTE: (1) For purposes of considering an exemption under this section, OFE's decision will be based solely on an analysis of the petitioner's capacity to physically achieve applicable environmental requirements. The petition should be directed toward those conditions or circumstances which make it physically impossible to comply during the

temporary exemption period. The cost of compliance is not relevant, but cost-related considerations may be presented as part of a demonstration submitted under § 503.21.

(2) Prior to submitting an exemption petition, it is recommended that a meeting be requested with OFE and EPA or the appropriate State or local regulatory agency to discuss options for operating an alternate fuel fired facility in compliance with applicable environmental requirements.

(b) Evidence required in support of a petition. The petition must include the following evidence in order to make the demonstration required by this section:

(1) Where the petitioner has applied for a construction permit from EPA or an appropriate State agency prior to petitioning for an exemption under this section, a copy of that application and synopsis of supporting documents filed with or subsequent to that application must be submitted to OFE with the petition or at the time filed with the permitting agency;

(2) To the extent applicable, a copy of the EPA or State denial of the construction permit application;

(3) To the extent applicable, a synopsis of the administrative record of the EPA or State or local permit proceedings;

(4) To the extent applicable, a summary of the technology upon which the denial was based, including a performance comparison between the proposed technology and that technology which would provide the maximum possible reduction of pollution;

(5) An examination of the environmental compliance of the facility, including an analysis of its ability to meet applicable standards and criteria when using both the proposed fuel and the alternate fuel(s) which would provide the basis for exemption. All such analysis must be based on accepted analytical techniques, such as air quality modeling, and reflect current conditions of the area which would be affected by the facility. The petitioner is responsible for obtaining the necessary data to accurately characterize these conditions. Environmental compliance must be examined in the context of available pollution control equipment which would provide the maximum possible reduction of pollution. The analysis must contain: (i) Requests for bids

and other inquiries made and responses received by the petitioner concerning the availability and performance of pollution control equipment; (ii) contracts signed, if any, for an alternate fuel supply and for the purchase and installation of pollution control equipment; or (iii) other comparable evidence such as technical studies documenting the efficacy of equipment to meet applicable requirements;

(6) An examination of any regulatory options available to the petitioner in seeking to achieve environmental compliance (such as offsets, variances, and State Implementation Plan revisions);

(7) Any other documentation which demonstrates an inability to comply with applicable environmental requirements;

(8) No alternate power supply exists, as required under §503.8 of these regulations.

(c) Duration. This temporary exemption, taking into account any extension and renewals, may not exceed 5 years.

(d) Certification alternative. (1) To qualify for this exemption, in lieu of meeting the evidentiary requirements of paragraph (b) of this chapter, a petitioner may certify that, for the period of the exemption:

(i) The site for the facility is or will be located in a Class I area or Class II area in which the allowable increment established by law has been consumed, as defined in part C of the Clean Air Act; the use of an alternate fuel will cause or contribute to concentrations of pollutants which would exceed the maximum allowable increases in a Class I or Class II area even with the application of best available control technology; the site for the facility is or will be located in a non-attainment area as defined in part D of the Clean Air Act for any pollutant which would be emitted by the facility; or, even with the application of the lowest achievable emission rate, the use of an alternate fuel will cause or contribute to concentrations in an air quality control region, of a pollutant for which any national ambient air quality standard is or would be exceeded; and

(ii) No alternate power supply exists, as required under §503.8 of these regulations.

(2) A petition by certification under this paragraph must include:

(i) Duly executed certifications required under paragraph (d)(1) of this section;

(ii) Exhibits containing the basis for the certifications required under paragraph (d)(1) of this section (including those factual and analytical materials deemed by the petitioner to be sufficient to support the granting of this exemption); and

(iii) The anticipated duration of the circumstances which constitute the basis for the exemption.

[46 FR 59903, Dec. 7, 1981, as amended at 54 FR 52894, Dec. 22, 1989]

§ 503.24 Future use of synthetic fuels.

(a) Eligibility. Section 211(b) of the Act provides for a temporary exemption based upon the future use of synthetic fuels. To qualify, a petitioner must certify that:

(1) The petitioner will be able to comply with the applicable prohibitions imposed by the Act by the use of a synthetic fuel derived from coal or another alternate fuel as a primary energy source in the proposed facility by the end of the proposed exemption period;

(2) The petitioner will not be able to comply with the applicable prohibitions imposed by the Act by use of a synthetic fuel until the end of the proposed exemption period; and

(3) No alternate power supply exists, as required under §503.8 of these regulations.

(b) Evidence required in support of a petition. The petition must include the following evidence in order to make the demonstration required by this section:

(1) Duly executed certifications required under paragraph (a) of this section;

(2) Exhibits containing the basis for the certifications required under paragraph (a) of this section (including those factual and analytical materials deemed by the petitioner to be sufficient to support the granting of this exemption); and

(3) A preliminary compliance plan, including to the extent available, the information required under § 503.12.