Contractor's own charges to date of termination (exclusive of claims of subcontractors)

Description

(The individual elements of costs should be detailed here in the manner set forth in the contractor's proposed

[blocks in formation]

1. Appropriate references should be made in each case to supporting exhibits and explanatory notes.

2. In the case of particular items on which the accountant has reason to believe that the contractor will not agree with his exceptions, he should include a concise statement of the contractor's position.

3. Items listed in the "Referred to negotiator" column should be of a type regarding which the accountant has satisfied himself that the expenditures have been made, but there is no accounting evidence for determining the amount applicable to the contract. Profit, if any, should also be shown in this column.

Referred to negotiator

Audited amount

a. Each item listed as "Referred to negotiator" should be supported by a statement of any pertinent facts or other considerations, together with any recommendations the accountant can make which will be useful to the contracting officer in negotiating a settlement.

b. So far as costs are concerned, the "Referred to negotiator" column should be used only in rare cases. It is not to be regarded as a substitute for accounting determinations which the accountant should properly make.

[blocks in formation]

APPENDIX I

Uniform Termination Articles for Fixed Price Supply Contracts As Set Forth in War Department Procurement Regulations Paragraphs 324 and 15–901

Article

UNIFORM TERMINATION ARTICLE FOR FIXED PRICE SUPPLY CONTRACTS

Termination at the Option of the Government. (a) The performance of work under this contract may be terminated by the Government in accordance with this Article in whole, or from time to time in part, whenever the contracting officer shall determine any such termination is for the best interests of the Government. Termination of work hereunder shall be effected by delivery to the contractor of a Notice of Termination specifying the extent to which performance of work under the contract shall be terminated, and the date upon which such termination shall become effective. If termination of work under this contract is simultaneous with, a part of, or in connection with, a general termination (1) of all or substantially all of a group or class of contracts made by the Department

for the same product or for closely related products, or (2) of war contracts at, about the time of, or following, the cessation of the present hostilities, or any major part thereof, such termination shall only be made in accordance with the provisions of this Article, unless the contracting officer finds that the contractor is then in gross or wilful default under this contract.

(b) After receipt of a Notice of Termination and except as otherwise directed by the contracting officer, the contractor shall (1) terminate work under the contract on the date and to the extent specified in the Notice of Termination; (2) place no further orders or subcontracts for materials, services of facilities except as may be necessary for completion of such portions of the work under the contract as may not be terminated; (3) terminate all orders and subcontracts to the extent that they relate to the performance of any work terminated by the Notice of Termination; (4) assign to the Government, in the manner and to the extent directed by the contracting officer, all of the right, title and interest of the contractor under the orders or subcontracts so terminated; (5) settle all claims arising out of such termination of orders and subcontracts with the approval or ratification of the contracting officer to the extent that he may require, which approval or ratification shall be final for all the purposes of this Article; (6) transfer title and deliver to the Government in the manner, to the extent and at the times di

rected by the contracting officer (i) the fabricated or unfabricated parts, work in process, completed work, supplies and other material produced as a part of, or acquired in respect of the performance of, the work terminated in the Notice of Termination, and (ii) the plans, drawings, information and other property which, if the contract had been completed, would be required to be furnished to the Government; (7) use his best efforts to sell in the manner, to the extent, at the time, and at the price or prices directed or authorized by the contracting officer any property of the types referred to in subdivision (6) of this paragraph provided, however, that the contractor (i) shall not be required to extend credit to any purchaser and (ii) may retain any such property at a price or prices approved by the contracting officer; (8) complete performance of such part of the work as shall not have been terminated by the Notice of Termination; and (9) take such action as may be necessary or as the contracting officer may direct for protection and preservation of the property, which is in the possession of the contractor and in which the Government has or may acquire an interest.

(c) The contractor and the contracting officer may agree upon the whole or any part of the amount or amounts to be paid to the contractor by reason of the total or partial termination of work pursuant to this Article, which amount or amounts may include a reasonable allowance for profit, and the Government shall pay the agreed amount or amounts. Nothing in paragraph (d) of this Article prescribing the amount to be paid to the contractor in the event of failure of the contractor and the contracting officer to agree upon the whole amount to be paid to the contractor by reason of the termination of work pursuant to this Article shall be deemed to limit, restrict or otherwise determine or affect the amount or amounts which may be agreed upon to be paid to the contractor pursuant to this paragraph (c).

(d) In the event of the failure of the contractor and contracting officer to agree as provided in paragraph (c) upon the whole amount to be paid to the contractor by reason of the termination of work pursuant to this Article, the

Government, but without duplication of any amounts agreed upon in accordance with paragraph (c), shall pay to the contractor the following amounts:

(1) For completed articles delivered to

and accepted by the Government (or sold or retained as provided in paragraph (b) (7) above) and not theretofore paid for, forthwith a sum equivalent to the aggregate price for such articles computed in accordance with the price or prices specified in the contract;

(2) In respect of the work under the

contract terminated as permitted by this Article, the total (without duplication of any items) of (i) the cost of such work exclusive of any cost attributable to articles paid or to be paid for under paragraph (d) (1) hereof; (ii) the cost of settling and paying claims arising out of the termination of work under subcontracts or orders as provided in paragraph (b) (5) above, exclusive of the amounts paid or payable on account of supplies or materials delivered by the subcontractor prior to the effective date of the notice of termination of this contract, which amounts shall be included in the cost on account of which payment is made under subdivision (i) above; and (iii) a sum equal to

-

--% 1 1 of the part of the amount determined under subdivision (i) which represents the cost of articles or materials not processed by the contractor, plus a sum equal to % of the remainder of such amount, but the aggregate of such sums shall not exceed 6% of the whole of the amount determined under subdivision (i), which for the purpose of this subdivision (iii) shall exclude any charges for interest on borrowings;

[blocks in formation]

(3) The reasonable cost of the preservation and protection of property incurred pursuant to paragraph (b) (9) hereof; and any other reasonable cost incidental to termination of work under this contract, including expense incidental to the determination of the amount due to the contractor as the result of the termination of work under this contract.

The total sum to be paid to the contractor under subdivisions (1) and (2) of this paragraph (d) shall not exceed the total contract price reduced by the amount of payments previously made for articles delivered prior to termination and by the Contract price of work not terminated. Except to the extent that the Government shall have otherwise expressly assumed the risk of loss, there shall be excluded from the amounts payable to the contractor as provided in paragraph (d) (1) and paragraph (d) (2) (i), all amounts allocable to or payable in respect of property, which is destroyed, lost, stolen or damaged so as to become undeliverable prior to the transfer of title to the Government or to a buyer pursuant to paragraph (b) (7) or prior to the 60th day after delivery to the Government of an inventory covering such property, whichever shall first occur.

(e) The obligation of the Government to make any payments under this article: (1) shall be subject to deductions in respect of (i) all unliquidated partial or progress payments, payments on account theretofore made to the contractor and unliquidated advance payments, (ii) any claim which the Government may have against the contractor in connection with this contract, and (iii) the price agreed upon or the proceeds of sale of any materials, supplies or other things retained by the contractor or sold, and not otherwise recovered by or credited to the Government, and (2) in the discretion of the contracting officer shall be subject to deduction in respect of the amount of any claim of any subcontractor or supplier whose subcontract or order shall have been terminated as provided in paragraph (b) (3) except to the extent that such claim covers (i) property or materials delivered to the contractor or (ii) services furnished to the contractor in connection with the production of completed articles under this contract.