Cases Decided in the United States Court of Claims ... with Report of Decisions of the Supreme Court in Court of Claims Cases, Volumes 120-130The Court, 1955 - Law reports, digests, etc |
From inside the book
Results 1-5 of 100
Page 2
... entitled to recover on its claim for excess costs incurred in concrete operations where the liability of the Government in this matter was expressly excluded by the provisions of the contract . United States 70 ( 21 ) Same ; evidence ...
... entitled to recover on its claim for excess costs incurred in concrete operations where the liability of the Government in this matter was expressly excluded by the provisions of the contract . United States 70 ( 21 ) Same ; evidence ...
Page 6
... entitled to no additional allowance above the unit prices bid in the schedule by reason of the dimensions fixed by the con- tracting officer or by reason of any modifications or extensions . *** We hold that the provisions above quoted ...
... entitled to no additional allowance above the unit prices bid in the schedule by reason of the dimensions fixed by the con- tracting officer or by reason of any modifications or extensions . *** We hold that the provisions above quoted ...
Page 9
... entitled to recover the costs oc- casioned by the delay of the defendant in furnishing neces- sary reinforcement steel . The case is referred to a Commissioner of this court to determine the amount of such costs which plaintiff is entitled ...
... entitled to recover the costs oc- casioned by the delay of the defendant in furnishing neces- sary reinforcement steel . The case is referred to a Commissioner of this court to determine the amount of such costs which plaintiff is entitled ...
Page 30
... entitled to recover damages resulting from delayed delivery of reinforcing steel , and the plaintiff is not entitled to recover damages resulting from unavailability of adequate labor or damages for decreased concrete quantities . The ...
... entitled to recover damages resulting from delayed delivery of reinforcing steel , and the plaintiff is not entitled to recover damages resulting from unavailability of adequate labor or damages for decreased concrete quantities . The ...
Page 33
... entitled to pay and allowances of his higher ranks from the date of appointments , February 15 , 1945 , and October 5 , 1945. Plaintiff having received pay and allowances from these dates , it is held that plaintiff is not entitled to ...
... entitled to pay and allowances of his higher ranks from the date of appointments , February 15 , 1945 , and October 5 , 1945. Plaintiff having received pay and allowances from these dates , it is held that plaintiff is not entitled to ...
Other editions - View all
Common terms and phrases
Administration advised agent amended amount Army August authority British pounds building cents charges claim Commission Commissioner construction contracting officer contractor cost Court cubic yards damages December decision deduction defendant defendant's Defense Supplies Corporation delay delivered delivery Department Dutch guilders Eminent domain entitled to recover excavation excess profits tax exchange Fairmount Park February filed Findings of Fact follows franchise freight French francs furnished Glavish Government grade January jeeps Judge judgment July July 24 June 25 June 30 lease material ment Metals Reserve Company month November October October 16 operations Opinion paid payment petition plaintiff Potts pounds premises Premium Price Plan Production Board purchase pursuant Quota Committee raw silk Reduced Rates refund rental requested Rihm Section September shipments specifications Stat steel tank cars Tariff of Reduced termination thereof tiff tion Toledo United Veterans wage War Production Board Warren E zinc
Popular passages
Page 128 - to raise and support Armies" and "to provide and maintain a Navy.
Page 364 - From the moment of surrender the authority of the Emperor and the Japanese Government to rule the state shall be subject to the Supreme Commander of the Allied powers who will take such steps as he deems proper to effectuate the surrender terms.
Page 500 - ... unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, in either its sovereign or contractual capacity, a,cts of another contractor in the performance of a contract with the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather, or delays of subcontractors or suppliers due to such causes...
Page 503 - ... remedy shall be by action against the United States in the Court of Claims for the recovery of his reasonable and entire compensation for such use and manufacture.
Page 549 - ... the Government may, by written notice to the contractor, terminate his right to proceed with the work or such part of the work as to which there has been a failure to pay...
Page 363 - The several military missions have agreed upon future military operations against Japan. The Three Great Allies expressed their resolve to bring unrelenting pressure against their brutal enemies by sea, land, and air. This pressure is already rising. "The Three Great Allies are fighting this war to restrain and punish the aggression of Japan. They covet no gain for themselves and have no thought of territorial expansion.
Page 364 - The occupying forces of the Allies shall be withdrawn from Japan as soon as these objectives have been accomplished and there has been established in accordance with the freely expressed will of the Japanese people a peacefully inclined and responsible government.
Page 148 - To the extent of any interest therein of which the decedent has at any time made a transfer, by trust or otherwise, where the enjoyment thereof was subject at the date of his death to any change through the exercise of a power, either by the decedent alone or in conjunction with any person, to alter, amend? or revoke...
Page 162 - Officer shall determine that such termination is in the best interest of the Government. Any such termination shall be effected by delivery to the Contractor of a Notice of Termination specifying whether termination is for the default of the Contractor or...
Page 225 - To be dishonorably discharged from the service, to forfeit all pay and allowances due or to become due, and to be confined at hard labor at such place as the reviewing authority may direct for 10 years.