" ... the Government may, by written notice to the contractor, terminate his right to proceed with the work or such part of the work as to which there has been a failure to pay said required wages and to prosecute the work to completion by contract or otherwise,... "
The Code of Federal Regulations of the United States of America - Page 20
1949
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 109

United States. Court of Claims - Law reports, digests, etc - 1948 - 974 pages
...to Executive Order Number 9250 and the General Orders and Regulations issued thereunder) regardless of any contractual relationship which may be alleged...the contractor and his sureties shall be liable to trie Government for any excess costs occasioned the Government thereby. 4. Before bidding, plaintiff...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 115

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1950 - 940 pages
...contracting officer shall have the right to withhold from the contractor Reporter's Statement of Ihe Case so much of accrued payments as may be considered necessary...any excess costs occasioned the Government thereby. 3. In conformity with the act of August 30, 1935, 49 Stat. 1011, as amended by the act of June 15,...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 123

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1958 - 1044 pages
...such laborers and mechanics and not refunded to the contractor, subcontractors, or their agents. (6) In the event it is found by the contracting officer...any excess costs occasioned the Government thereby. 7. On October 22, 1940, the Elmira business agent of the United Brotherhood of Carpenters and Joiners...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 116

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1950 - 1004 pages
...subcontractor directly on the site of the work covered by the contract has been or is being paid at a rate of wages less than the rate of wages required...any excess costs occasioned the Government thereby. ARTICLE 24. Payment and Performance Bonds. — The contractor shall furnish Performance and Payment,...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 128

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1954 - 918 pages
...which there has been delay. In such event the Government may take over the work and prosecute the same to completion, by contract or otherwise, and the contractor...sureties shall be liable to the Government for any excess cost occasioned the Government thereby. If the contractor's right to proceed is so terminated, the...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 101

United States. Court of Claims - Law reports, digests, etc - 1944 - 960 pages
...to proceed and in this connection the contract provided that the Government might complete the work, by contract or otherwise, "and the contractor and...sureties shall be liable to the Government for any excess cost occasioned the Government thereby." By terminating the contractor's right to proceed the Government...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 148

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1962 - 784 pages
...market or secure the manufacture and delivery of the materials and supplies by 49 Finding* of Fact contract or otherwise, and the contractor and his...sureties shall be liable to the Government for any excess cost occasioned the Government thereby : * * * 41. Prior to termination of the contract, a representative...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volumes 120-130

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1955 - 1002 pages
...which there has been delay. In such event the Government may take over the work and prosecute the same to completion, by contract or otherwise, and the contractor and his sureties shall be liable to the Qovernment for any excess cost occasioned the Government thereby. If the contractor's right to proceed...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 111

United States. Court of Claims - Law reports, digests, etc - 1948 - 886 pages
...or supplies in the open market or secure the manufacture and delivery of the materials and supplies by contract or otherwise, and the contractor and his sureties shall be liable to the Government thereby; Provided, that the contractor shall not be charged with any excess cost occasioned the Government...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 83

United States. Court of Claims - Law reports, digests, etc - 1937 - 786 pages
...work the Government has the right to terminate the contract, take over the work and prosecute the same to completion by contract or otherwise and the contractor and his sureties shall be liable for any excess cost occasioned the Government thereby. The second course the Opinion of the Court Government...
Full view - About this book