 | United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1968
...writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor...receive and act upon any such claim asserted at any time/prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
 | United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1959
...in writing within 30 days from the date of receipt by the Contractor of the notification of extra or change : Provided, however, That the Contracting Officer,...upon any such claim asserted at any time prior to the date of final settlement of the contract. If the parties fail to agree upon the adjustment to be... | |
 | Administrative law - 1966
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meanIng... | |
 | Administrative law - 1978
...Any claim by the Contractor for adjustment under this clause must be asserted within 30 calendar days from the date of receipt by the Contractor of the...asserted at any time prior to final payment under the contract. Failure to agree to any adjustment shall be considered a dispute concerning a question... | |
 | Administrative law - 1992
...Any claim by the Contractor for adjustment under this clause must be asserted within 30 calendar days from the date of receipt by the Contractor of the...asserted at any time prior to final payment under the contract. Failure to agree to any adjustment shall be considered a dispute concerning a question... | |
 | Administrative law - 1983
...the Contractor for adjustment under this clause must be asserted within sixty (60) days from the dale of receipt by the Contractor of the notification of...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning... | |
 | Administrative law - 1970
...writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor...upon any such claim asserted at any time prior to ĞinĞi payment tinder this contract. Where the cost of property made obsolete or excess as a result... | |
 | Administrative law - 1971
...adjustment under this clauaeSmiwlie V-_ within 30 days from the date of receipt by the CctfijrWctor of the notification of change: Provided, however....any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's... | |
 | Administrative law - 1978
...of receipt by the Contractor of the notification Title 41 — Public Contracts, Property Management of change: Provided, however, that the Contracting...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact v.'ithin the meaning... | |
 | Administrative law - 1975
...Any claim by the Contractor for adjustment under this clause must be asserted within 30 calendar days from the date of receipt by the Contractor of the...justify such action, may receive and act upon any such Ğlaim asserted at any tune prior to final payment •under the contract. Failure to agree to any adjustment... | |
| |