| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1962 - 712 pages
...submit its termination claim within the time allowed, the Contracting Officer may determine, on the basis of information available to him, the amount,...pay to the Contractor the amount so determined. d. Subject to the provisions of paragraph c, the Contractor and the Contracting Officer may agree upon... | |
| Administrative law - 1971 - 668 pages
...Government whenever for any reason the Contracting Officer shall determine that such termination Is In the best Interest of the Government. Termination...1-15.3 of the Federal Procurement Regulations (41 CPB 1-15.3) as In effect on the date of this contract, except that If the Contractor Is not an educational... | |
| Administrative law - 1969 - 640 pages
...Government whenever for any reason the Contracting Officer shall determine that such termination is in the best interest of the Government. Termination...1-15.3 of the Federal Procurement Regulations (41 CPR 1-15.3) as in effect on the date of this contract, except that if the Contractor is not an educational... | |
| Administrative law - 1972 - 684 pages
...Government whenever for any reason the Contracting Officer shall determine that such termination is In the best Interest of the Government. Termination...governed by the cost principles set forth in Subpart 1-16.3 of the Federal Procurement Regulations (41 CFR 1-15.3) as in effect on the date of this contract,... | |
| Administrative law - 1982 - 690 pages
...Government whenever for any reason the Contracting Officer shall determine that such termination is in the best interest of the Government. Termination...costs under paragraph (c) shall be governed by the contract cost principles and procedures in Subpart 1-15.3 of the Federal Procurement Regulations (41... | |
| Administrative law - 1984 - 720 pages
...Government whenever for any reason the Contracting Officer shall determine that such termination is in the best interest of the Government. Termination...costs under paragraph (c) shall be governed by the contract cost principles and procedures in Subpart 1-15.3 of the Federal Procurement Regulations (41... | |
| Administrative law - 1981 - 676 pages
...Contractor of a Notice of Termination specifying the extent to which performance of work under trie contract is terminated and the date upon which such...costs under paragraph (c) shall be governed by the contract cost principles and procedures in Subpart 1-15.3 of the Federal Procurement Regulations (41... | |
| Administrative law - 1969 - 628 pages
...and subcontracts. (c) The Contractor shall submit his termination claim to the Contracting Oflicer promptly after receipt of a Notice of Termination,...the cost principles set forth in Subpart 1-15.3 of theFederal Procurement Regulations (41 CFR 1-15.3) as In effect on the date of this contract, except... | |
| Administrative law - 1973 - 740 pages
...action, he may receive and act upon any such termination claim at any time after such one-year period or extension thereof. Upon failure of the Contractor...pay to the Contractor the amount so determined. (d) Subject to the provisions of paragraph (c), and subject to any review required by the contracting agency's... | |
| Administrative law - 1971 - 850 pages
...he may receive and act upon any such termination claim at any time after such 1 year period or any extension thereof. Upon failure of the Contractor...pay to the Contractor the amount so determined. (d) Subject to the provisions of paragraph (c) , and subject to any review required by the contracting... | |
| |