Page images
PDF
EPUB

under $30.920. The State agency shall be concurrently notified in writing of any such action.

§35.955 Grant amendments to increase grant amounts.

Grant agreements may be amended under $30.900-1 of this chapter for project changes which have been approved under §§ 30.900 and 35.935-11 of this subchapter. However, no grant agreement may be amended to increase the amount of a grant unless the State agency has approved the grant increase from available State allotments and reallotments under § 35.915.

$35.960 Disputes.

Administrator's

(a) The Regional final determination on the ineligibility of a project (see §35.915(h)) or a grant applicant (see § 35.920-1), on the Federal share (see $35.930–5(b)), or on any dispute arising under a grant shall be final and conclusive unless the applicant or grantee appeals within 30 days from the date of receipt of the final determination. (See subpart J of part 30 of this subchapter.)

(b) The EPA General Counsel will publish periodically as a Notice document in the FEDERAL REGISTER a digest of grant appeals decisions.

$35.965 Enforcement.

If the Regional Administrator determines that the grantee has failed to comply with any provision of this subpart, he may impose any of the following sanctions:

(a) The grant may be terminated or annulled under $30.920 of this subchapter;

(b) Project costs directly related to the noncompliance may be disallowed; (c) Payment otherwise due to the grantee of up to 10 percent may be withheld (see §30.615-3 of this chapter); (d) Project work may be suspended under §30.915 of this subchapter;

(e) A noncomplying grantee may be found nonresponsible or ineligible for future Federal assistance or a noncomplying contractor may be found nonresponsible or ineligible for approval for future contract award under EPA grants;

(f) An injunction may be entered or other equitable relief afforded by a court of appropriate jurisdiction;

(g) Such other administrative or judicial action may be instituted if it is legally available and appropriate.

§ 35.970 Contract enforcement.

(a) Regional Administrator authority. At the request of a grantee, the Regional Administrator is authorized to provide technical and legal assistance in the administration and enforcement of any contract related to treatment works for which an EPA grant was made and to intervene in any civil action involving the enforcement of such contracts, including contract disputes which are the subject of either arbitration or court action. Any assistance is to be provided at the discretion of the Regional Administrator and in a manner determined to best serve the public interest. Factors which the Regional Administrator may consider in determining whether to provide assistance

are:

(1) Available agency resources.

(2) Planned or ongoing enforcement action.

(3) The grantee's demonstration of good faith to resolve contract matters at issue.

(4) The grantee's adequate documentation.

(5) The Federal interest in the contract matters at issue.

(b) Grantee request. The grantee's request for technical or legal assistance should be submitted in writing and be accompained by documentation adequate to inform the Regional Administrator of the nature and necessity of the requested assistance. A grantee may orally request assistance from the Regional Administrator on an emergency basis.

(c) Privity of contract. The Regional Administrator's technical or legal involvement in any contract dispute will not make EPA a party to any contract entered into by the grantee. (See § 35.936-8.)

(d) Delegation to States. The authority to provide technical and legal assistance in the administration of contract matters described in this section may be delegated to a State agency under subpart F of this part if the State

agency can demonstrate that it has the appropriate legal authority to undertake such functions.

APPENDIX A TO SUBPART E-COSTEFFECTIVENESS ANALYSIS GUIDELINES

1. Purpose. These guidelines represent Agency policies and procedures for determining the most cost-effective waste treatment management system or component part.

2. Authority. These guidelines are provided under sections 212(2)(C) and 217 of the Clean Water Act.

3. Applicability. These guidelines, except as otherwise noted, apply to all facilities planning under step grant assistance awarded after September 30, 1978. The guidelines also apply to State or locally financed facilities planning on which subsequent step 2 or step 3 Federal grant assistance is based.

4. Definitions. Terms used in these guidelines are defined as follows:

a. Waste treatment management system. Used synonymously with "complete waste treatment system" as defined in §35.905 of this subpart.

b. Cost-effectiveness analysis. An analysis performed to determine which waste treatment management system or component part will result in the minimum total resources costs over time to meet Federal, State, or local requirements.

c. Planning period. The period over which a waste treatment management system is evaluated for cost-effectiveness. The planning period begins with the system's initial operation.

d. Useful life. The estimated period of time during which a treatment works or a component of a waste treatment management system will be operated.

e. Disaggregation. The process or result of breaking down a sum total of population or economic activity for a State or other jurisdiction (i.e., designated 208 area or SMSA) into smaller areas or jurisdictions.

5. Identification, selection, and screening of alternatives. a. Identification of alternatives. All feasible alternative waste management systems shall be initially identified. These alternatives should include systems discharging to receiving waters, land application systems, on-site and other non-centralized systems, including revenue generating applications, and systems employing the reuse of wastewater and recycyling of pollutants. In identifying alternatives, the applicant shall consider the possibility of no action and staged development of the system.

b. Screening of alternatives. The identified alternatives shall be systematically screened to determine those capable of meeting the applicable Federal, State and local criteria.

c. Selection of alternatives. The identified alternatives shall be initially analyzed to de

termine which systems have cost-effective potential and which should be fully evaluated according to the cost-effectiveness analysis procedures established in the guidelines.

d. Extent of effort. The extent of effort and the level of sophistication used in the costeffectiveness analysis should reflect the project's size and importance. Where processes or techniques are claimed to be innovative technology on the basis of the cost reduction criterion contained in paragraph 6e(1) of appendix E to this subpart, a sufficiently detailed cost analysis shall be included to substantiate the claim to the satisfaction of the Regional Administrator.

6. Cost-effectiveness analysis procedures.

a. Method of analysis. The resources costs shall be determined by evaluating opportunity costs. For resources that can be expressed in monetary terms, the analysis will use the interest (discount) rate established in paragraph 6e. Monetary costs shall be calculated in terms of present worth values or equivalent annual values over the planning period defined in section 6b. The analysis shall descriptively present nonmonetary factors (e.g., social and environmental) in order to determine their significance and impact. Nonmonetary factors include primary and secondary environmental effects, implementation capability, operability, performance reliability and flexibility. Although such factors as use and recovery of energy and scarce resources and recycling of nutrients are to be included in the monetary cost analysis, the non-monetary evaluation shall also inIclude them. The most cost-effective alternative shall be the waste treatment management system which the analysis determines to have the lowest present worth or equivalent annual value unless nonmonetary costs are overriding. The most cost-effective alternative must also meet the minimum requirements of applicable effluent limitations, groundwater protection, or other applicable standards established under the Act.

b. Planning period. The planning period for the cost-effectiveness analysis shall be 20 years.

c. Elements of monetary costs. The monetary costs to be considered shall include the total value of the resources which are attributable to the waste treatment management system or to one of its component parts. To determine these values, all monies necessary for capital construction costs and operation and maintenance costs shall be identified.

(1) Capital construction costs used in a cost-effective analysis shall include all contractors' costs of construction including overhead and profit, costs of land, relocation, and right-of-way and easement acquisition; costs of design engineering, field exploration and engineering services during construction; costs of administrative and legal

services including costs of bond sales; startup costs such as operator training; and interest during construction. Capital construction costs shall also include contingency allowances consistent with the cost estimate's level of precision and detail.

(2) The cost-effectiveness analysis shall include annual costs for operation and maintenance (including routine replacement of equipment and equipment parts). These costs shall be adequate to ensure effective and dependable operation during the system's planning period. Annual costs shall be divided between fixed annual costs and costs which would depend on the annual quantity of waste water collected and treated. Annual revenues generated by the waste treatment management system through energy recovery, crop production, or other outputs shall be deducted from the annual costs for operation and maintenance in accordance with guidance issued by the Administrator.

d. Prices. The applicant shall calculate the various components of costs on the basis of market prices prevailing at the time of the cost-effectiveness analysis. The analysis shall not allow for inflation of wages and prices, except those for land, as described in paragraph 6h(1) and for natural gas. This stipulation is based on the implied assumption that prices, other than the exceptions, for resources involved in treatment works construction and operation, will tend to change over time by approximately the same percentage. Changes in the general level of prices will not affect the results of the costeffectiveness analysis. Natural gas prices shall be escalated at a compound rate of 4 percent annually over the planning period, unless the Regional Administrator determines that the grantee has justified use of a greater or lesser percentage based upon regional differentials between historical natural gas price escalation and construction cost escalation. Land prices shall be appreciated as provided in paragraph 6h(1). Both historical data and future projections support the gas and land price escalations relative to those for other goods and services related to waste water treatment. Price escalation rates may be updated periodically in accordance with Agency guidelines.

e. Interest (discount) rate. The rate which the Water Resources Council establishes annually for evaluation of water resource projects shall be used.

f. Interest during construction. (1) Where capital expenditures can be expected to be fairly uniform during the construction period, interest during construction may be calculated at I=1/2PCi where:

I=the interest accrued during the construction period,

P-the construction period in years,
C=the total capital expenditures,

i=the interest rate (discount rate in section 6e).

(2) Where expenditures will not be uniform, or when the construction period will be greater than 4 years, interest during construction shall be calculated on a year-byyear basis.

g. Useful life. (1) The treatment works' useful life for a cost-effectiveness analysis shall be as follows:

Land-permanent.

Waste water conveyance structures (includes collection systems, outfall pipes, interceptors, force mains, tunnels, etc.)-50 years. Other structures (includes plant building, concrete process tankage, basins, lift stations structures, etc.)-30-50 years. Process equipment-15-20 years. Auxiliary equipment-10-15 years.

(2) Other useful life periods will be acceptable when sufficient justification can be provided. Where a system or a component is for interim service, the anticipated useful life shall be reduced to the period for interim service.

h. Salvage value. (1) Land purchased for treatment works, including land used as part of the treatment process or for ultimate disposal of residues, may be assumed to have a salvage value at the end of the planning period at least equal to its prevailing market value at the time of the analysis. In calculating the salvage value of land, the land value shall be appreciated at a compound rate of 3 percent annually over the planning period, unless the Regional Administrator determines that the grantee has justified the use of a greater or lesser percentage based upon historical differences between local land cost escalation and construction cost escalation. The land cost escalation rate may be updated periodically in accordance with Agency guidelines. Right-of-way easements shall be considered to have a salvage value not greater than the prevailing market value at the time of the analysis.

(2) Structures will be assumed to have a salvage value if there is a use for them at the end of the planning period. In this case, salvage value shall be estimated using straight line depreciation during the useful life of the treatment works.

(3) The method used in paragraph 6h(2) may be used to estimate salvage value at the end of the planning period for phased additions of process equipment and auxiliary equipment.

(4) When the anticipated useful life of a facility is less than 20 years (for analysis of interim facilities), salvage value can be claimed for equipment if it can be clearly demonstrated that a specific market or reuse opportunity will exist.

7. Innovative and alternative wastewater treatment processes and techniques.

a. Beginning October 1, 1978, the capital costs of publicly owned treatment works which use processes and techniques meeting the criteria of appendix E to this subpart and which have only a water pollution control function, may be eligible if the present worth cost of the treatment works is not more than 115 percent of the present worth cost of the most cost-effective pollution control system, exclusive of collection sewers and interceptors common to the two systems being compared, by 115 percent, except for the following situation.

b. Where innovative or alternative unit processes would serve in lieu of conventional unit processes in a conventional waste water treatment plant, and the present worth costs of the nonconventional unit processes are less than 50 percent of the present worth costs of the treatment plant, multiply the present worth costs of the replaced conventional processes by 115 percent, and add the cost of nonreplaced unit processes.

c. The eligibility of multipurpose projects which combine a water pollution control function with another function, and which use processes and techniques meeting the criteria of appendix E to this subpart, shall be determined in accordance with guidance issued by the Administrator.

d. The above provisions exclude individual systems under § 35.918. The regional Administrator may allow a grantee to apply the 15percent preference authorized by this section to facility plans prepared under step 1 grant assistance awarded before October 1, 1978.

8. Cost-effective staging and sizing of treatment works.

a. Population projections. (1) The disaggregation of State projections of population shall be the basis for the population forecasts presented in individual facility plans, except as noted. These State projections shall be those developed in 1977 by the Bureau of Economic Analysis (BEA), Department of Commerce, unless, as of June 26, 1978, the State has already prepared projections. These State projections may be used instead of the BEA projections if the year 2000 State population does not exceed that of the BEA projection by more than 5 percent. If the difference exceeds this amount, the State must either justify or lower its projection. Justification must be based on the historical and current trends (e.g., energy and industrial development, military base openings) not taken into account in the BEA projections. The State must submit for approval to the Administrator the request and justification for use of State projections higher than the BEA projections. By that time, the State shall issue a public notice of the request. Before the Administrator's approval of the State projection, the Regional Administrator shall solicit public comments and hold a public hearing if important issues are raised about the State projection's validity.

State projections and disaggregations may be updated periodically in accordance with Agency guidelines.

(2) Each State, working with designated 208 planning agencies, organizations certified by the Governor under section 174(a) of the Clean Air Act, as amended, and other regional planning agencies in the State's nondesignated areas, shall disaggregate the State population projection among its designated 208 areas, other standard metropolitan statistical areas (SMSA's) not included in the 208 area, and non-SMSA counties or other appropriate jurisdictions. States that had enacted laws, as of June 26, 1978, mandating disaggregation of State population totals to each county for areawide 208 planning may retain this requirement. When disaggregating the State population total, the State shall take into account the projected population and economic activities identified in facility plans, areawide 208 plans and municipal master plans. The sum of the disaggregated projections shall not exceed the State projection. Where a designated 208 area has, as of June 26, 1978, already prepared a population projection, it may be used if the year 2000 population does not exceed that of the disaggregated projection by more than 10 percent. The State may then increase its population projection to include all such variances rather than lower the population projection totals for the other areas. If the 208 area population forecast exceeds the 10 percent allowance, the 208 agency must lower its projection within the allowance and submit the revised projection for approval to the State and the Regional Administrator.

(3) The State projection totals and the disaggregations will be submitted as an output of the statewide water quality management process. The submission shall include a list of designated 208 areas, all SMSA's, and counties or other units outside the 208 areas. For each unit the disaggregated population shall be shown for the years 1980, 1990, and 2000. Each State will submit its projection totals and disaggregations for the Regional Administrator's approval before October 1, 1979. Before this submission, the State shall hold a public meeting on the disaggregations and shall provide public notice of the meeting consistent with part 25 of this chapter. (See $35.917(e).)

(4) When the State projection totals and disaggregations are approved they shall be used thereafter for areawide water quality management planning as well as for facility planning and the needs surveys under section 516(b) of the Act. Within areawide 208 planning areas, the designated agencies, in consultation with the States, shall disaggregate the 208 area projections among the SMSA and non-SMSA areas and then disaggregate these SMSA and non-SMSA projections

among the facility planning areas and the remaining areas. For those SMSA's not included within designated 208 planning areas, each State, with assistance from appropriate regional planning agencies, shall disaggregate the SMSA projection among the facility planning areas and the remaining areas within the SMSA. The State shall check the facility planning area forecasts to ensure reasonableness and consistency with the SMSA projections.

(5) For non-SMSA facility planning areas not included in designated area wide 208 areas, the State may disaggregate population projections for non-SMSA counties among facility planning areas and remaining areas. Otherwise, the grantee is to forecast future population growth for the facility planning area by linear extrapolation of the recent past (1960 to present) population trends for the planning area, use of correlations of planning area growth with population growth for the township, county or other larger parent area population, or another appropriate method. A population forecast may be raised above that indicated by the extension of past trends where likely impacts (e.g., significant new energy developments, large new industries, Federal installations, or institutions) justify the difference. The facilities plan must document the justification. These population forecasts should be based on estimates of new employment to be generated. The State shall check individual population forecasts to insure consistency with overall projections for nonSMSA counties and justification for any difference from past trends.

(6) Facilities plans prepared under step 1 grant assistance awarded later than 6 months after Agency approval of the State disaggregations shall follow population forecasts developed in accordance with these guidelines.

b. Wastewater flow estimates. (1) In determining total average daily flow for the design of treatment works, the flows to be considered include the average daily base flows (ADBF) expected from residential sources, commercial sources, institutional sources, and industries the works will serve plus allowances for future industries and nonexcessive infiltration/inflow. The amount of nonexcessive infiltration/inflow not included in the base flow estimates presented herein, is to be determined according to the Agency guidance for sewer system evaluation or Agency policy on treatment and control of combined sewer overflows (PRM 75-34).

(2) The estimation of existing and future ADBF, exclusive of flow reduction from combined residential, commercial and institutional sources, shall be based upon one of the following methods:

(a) Preferred method. Existing ADBF is estimated based upon a fully documented analysis of water use records adjusted for con

[blocks in formation]

The preferred method shall be used wherever water supply records or wastewater flow data exist. Allowances for future increases of per capita flow over time will not be approved.

(b) Optional method. Where water supply and wastewater flow data are lacking, existing and future ADBF shall be estimated by multiplying a gallon per capita per day (gpcd) allowance not exceeding those in the following table, except as noted below, by the estimated total of the existing and future resident populations to be served. The tabulated ADBF allowances, based upon several studies of municipal water use, include estimates for commercial and institutional sources as well as residential sources. The Regional Administrator may approve exceptions to the tabulated allowances where large (more than 25 percent of total estimated ADBF) commercial and institutional flows are documented.

[blocks in formation]

c. Flow reduction. The cost-effectiveness analysis for each facility planning area shall include an evaluation of the costs, cost savings, and effects of flow reduction measures unless the existing ADBF from the area is less than 70 gpcd, or the current population of the applicant municipality is under 10,000, or the Regional Administrator exempts the area for having an effective existing flow reduction program. Flow reduction measures include public education, pricing and regulatory approaches or a combination of these. In preparing the facilities plan and included cost effectiveness analysis, the grantee shall, as a minimum:

(1) Estimate the flow reductions implementable and cost effective when the treatment works become operational and after 10 and 20 years of operation. The measures to be evaluated shall include a public information program; pricing and regulatory approaches; installation of water meters, and retrofit of toilet dams and low-flow showerheads for existing homes and other

« PreviousContinue »