| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1968 - 922 pages
...receive and act upon any such claim asserted at any time/prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute...Contractor from proceeding with the contract as changed. 5. Inspection (a) All supplies (which term throughout this clause includes without limitation raw materials,... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1962 - 784 pages
...receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute..."Disputes." However, nothing in this clause shall excuse the Con148 c. Os. Per Cariam tractor from proceeding with the contract as changed. * * * * * 12. DISPUTES... | |
| Administrative law - 1979 - 520 pages
...Contracting Officer may at any time, by written order, and without notice to the sureties, if any, make changes, within the general scope of this contract,...Contractor from proceeding with the contract as changed. § 15-7.150-2 Inspection of services. Insert the following clause only in service contracts other than... | |
| Administrative law - 1980 - 582 pages
...Contracting Officer may at any time, by written order, and without notice to the sureties, if any, make changes, within the general scope of this contract,...Contractor from proceeding with the contract as changed. § 15-7.150-2 Inspection of services. Insert the following clause only in service contracts other than... | |
| Administrative law - 1982 - 1316 pages
...the general scope of this contract, in the definition of services to be performed, and the time (ir , hours of the day, days of the week, etc.) and place...Contractor from proceeding with the contract as changed. In the foregoing clause, the period of "30 days" within which any claim for adjustment must be asserted... | |
| Administrative law - 1966 - 1420 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date or receipt by the Contractor of the notification of change,...Contractor from proceeding with the contract as changed. In the foregoing clause, the period of "30 days" within which any claim for adjustment must be asserted... | |
| Administrative law - 1970 - 984 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date or receipt by the Contractor of the notification of change,...entitled "Disputes". However, nothing In this clause •hall excuse the Contractor from proceeding with the contract as changed. In the foregoing clause,... | |
| Administrative law - 1964 - 432 pages
...prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's...excuse the Contractor from proceeding with the contract aa changed. 3. EXTRAS Except as otherwise provided in this contract, no payment for extras shall be... | |
| Administrative law - 1991 - 654 pages
...prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's...contract entitled "Disputes." However, nothing in this PHS 352.280-4 clause shall excuse the Contractor from proceeding with the contract as changed. (End... | |
| Administrative law - 1989 - 660 pages
...prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change Is Included in the Contractor's...contract entitled "Disputes." However, nothing in this PHS 352.280-4 clause shall excuse the Contractor from proceeding with the contract as changed. (End... | |
| |