DEFINITIONS (APR 1984) The terms “Administration" and “Seryice" as used in this contract shall mean the General Services Administration (GSA) and the Public Buildings Service (PBS), respectively.

(End of Clause)

or firm of established reputation (or, if newly organized, whose personnel have previously established a reputation in the same field), which is regularly engaged in, and which maintains a regular force of workmen skilled in either (as applicable) manufacturing or fabricating items required by the contract, installing items required by the contract, or otherwise performing work required by the contract. Where the contract specification requires installation by a specialist, that term shall also be deemed to mean either the manufacturer of the item, an individual or firm licensed by the manufacturer, or an individual or firm who will perform the work under the manufacturer's direct supervision.

552.236-71 Authorities and limitations.

As prescribed in 536.570–2, insert the following clause:

(End of Clause)

552.236-73 Basis of award-construc

tion contract. As prescribed in 536.570-4, insert the following provision or the appropriate Alternate:

AUTHORITIES AND LIMITATIONS (APR 1984) (a) All work shall be performed under the general direction of the Contracting Officer, who alone shall have the power to bind the Government and to exercise the rights, responsibilities, authorities and functions vested in him by the contract documents, except that he shall have the right to designate authorized representatives to act for him. Wherever any provision in this contract specifies an individual (such as, but not limited to, Construction Engineer, Resident Engineer, Inspector or Custodian) or organization, whether Governmental or private, to perform any act on behalf of or in the interests of the Government, that individual or organization shall be deemed to be the Contracting Officer's authorized representative under this contract but only to the extent so specified. The Contracting Officer may, at any time during the performance of this contract, vest in any such authorized representatives additional power and authority to act for him or designate additional representatives, specifying the extent of their authority to act for him; a copy of each document vesting additional authority in an authorized representative or designating an additional authorized representative shall be furnished to the Contractor.

(b) The Contractor shall perform the contract in accordance with any order (including but not limited to instruction, direction, interpretation, or determination) issued by an authorized representative in accordance with his authority to act for the Contracting Officer; but the Contractor assumes all the risk and consequences of performing the contract in accordance with any order (including but not limited to instruction, direction, interpretation, or determination) of anyone not authorized to issue such order.

BASIS OF AWARD-CONSTRUCTION CONTRACT

(APR 1985) (a) The low bidder for purposes of award is the responsible bidder offering the lowest price for the base bid (consisting of the lump sum bid and any associated unit price bids extended by the applicable number of units shown on the bid form). See Standard Form 1442, Solicitation, Offer, and Award and the provision entitled “Contract Award-Sealed Bidding."

(b) A bid may be rejected as nonresponsive if the bid is materially unbalanced as to bid prices. A bid is unbalanced when the bid is based on prices significantly less than cost for some work and significantly overstated for other work.

(End of Provision)

Alternate 1

(End of Clause)

If the solicitation includes a base bid and options, the Contracting Officer shall delete paragraph (a) of the basic provision and insert paragraph (a) substantially as follows:

(a) The low bidder for purposes of award is the responsible bidder offering the lowest aggregate price for (1) the base bid (consisting of the lump sum bid and any associated unit price bids extended by the applicable number of units shown on the bid form) plus (2) all options designated to be evaluated. The evaluation of options will not obligate the Government to exercise the options. See Standard form 1442, Solicitation, Offer, and Award and

the provision entitled “Contract Award-Sealed Bidding."

552.236-72 Specialist.

As prescribed in 536.570-3, insert the following clause:

SPECIALIST (APR 1984) The term "Specialist," as used in the contract specification, shall mean an individual

Alternate II If the solicitation includes a base bid and alternates, the Contracting Officer shall delete paragraph (a) of the basic provision and insert paragraphs (a), (c), and (d) substantially as follows:

(a) The low bidder for purposes of award is the responsible bidder offering the lowest aggregate price for (1) the base bid (consisting of the lump sum bid and any associated unit price bids extended by the applicable number of units shown on the bid form) plus (2) those alternates in the order of priority listed in the solicitation that provide the most features of work within the funds available at bid opening. See the provision entitled “Contract Award-Sealed Bidding."

(c) Alternates will be added to the base bid in the order listed in the solicitation (see Standard Form 1442, Solicitation, Offer, and Award). If the addition of an alternate would make all bids exceed the funds available at bid opening, that alternate shall be skipped and the next subsequent alternate in a lower amount shall be added, provided that the aggregate of base bid and the selected alternates do not exceed the funds available at bid opening. For example, when the amount available is $100,000 and a bidder's base bid is $85,000, with its separate bids on four successive alternates being $10,000, $8,000, $6,000, and $4,000, the aggregate amount of the bid for purposes of selecting the alternates would be $99,000 (base bid plus the first and fourth alternates). The second and third alternates are skipped because each of them would cause the aggregate of the base bid and alternates to exceed the $100,000 amount available when considered with the first alternate. All bids shall be evaluated on the basis of the same alternates.

(d) After the low bidder has been determined in accordance with paragraph (a), an award may be made to that low bidder on the base bid, plus any combination of alternates for which funds are available at the time of award, but only if the award amount does not exceed the amount offered by any other responsible bidder. If the base bid plus the proposed combination of alternates exceed the amount offered by any other responsible bidder for the same combination of alternates, the award cannot be made on that combination of alternates.

of units shown on the bid form) plus (2) those alternates in the order of priority listed in the solicitation that provide the most features of work within the funds available at bid opening plus (3) all options designated to be evaluated except those options associated with alternates which are skipped during the selection process outlined in paragraph (c) below. The evaluation of options will not obligate the Government to exercise the options. See the provision entitled “Contract Award-Sealed Bidding."

(c) Alternates will be added to the base bid in the order listed in the solicitation (see Standard Form 1442, Solicitation, Offer, or Award). If the addition of an alternate would make all bids exceed the funds available at bid opening, that alternate shall be skipped and the next subsequent alternate in a lower amount shall be added, provided that the aggregate of base bid and the selected alternates do not exceed the funds available at bid opening. For example, when the amount available is $100.000 and a bidder's base bid is $85,000, with its separate bids on four successive alternates being $10,000, $8,000, $6,000, and $4,000, the aggregate amount of the bid for purposes of selecting the alternates would be $99,000 (base bid plus the first and fourth alternates). The second and third alternates are skipped because each of them would cause the aggregate of the base bid and alternates to exceed the $100,000 amount available when considered with the first alternate. All bids shall be evaluated on the basis of the same alternates.

(d) After the low bidder has been determined in accordance with paragraph (a), award may be made to that low bidder on the base bid and evaluated options plus any combination of alternates for which funds are available at the time of award, but only if that low bidder is still low on the sum thereof plus any previously unevaluated options designated to be evaluated which are associated with proposed alternates that were skipped during the selection under paragraph (c). If that low bidder is not still low, award cannot be made on the proposed combination of alternates. (54 FR 26558, June 23, 1989, as amended at 54 FR 40061, Sept. 29, 1989)

Alternate III If the solicitation includes a base bid, alternates, and options, the Contracting Officer shall delete paragraph (a) of the basic provision and insert paragraphs (a), (c), and (d) substantially as follows:

(a) The low bidder for purposes of award is the responsible bidder offering the lowest aggregate price for (1) the base bid (consisting of the lump sum bid and any associated unit price bids extended by the applicable number

552.236-74 Working hours.

As prescribed in 536.570-5, insert the following clause:

WORKING HOURS (APR 1984) (a) It is contemplated that all work will be performed during the customary working hours of the trades involved unless otherwise specified in this contract. Work performed by the Contractor at his own volition outside such customary working hours shall be at no additional expense to the Government.

(b) Any requests received by the Contractor from occupants of existing buildings to change the hours of work shall be referred to the Contracting Officer for determination.

(End of Clause)

552.236–75 Use of premises.

As prescribed in 536.570-6, insert the following clause:

USE OF PREMISES (APR 1984) (a) If the premises are occupied, the Contractor, his subcontractors, and their employees shall comply with the regulations governing access to, operation of, and conduct while in or on the premises and shall perform the work required under this contract in such a manner as not to unreasonably interrupt or interfere with the conduct of Government business.

(b) Any request received by the Contractor from occupants of existing buildings to change the sequence of work shall be referred to the Contracting Officer for determination.

(c) If the premises are occupied, the Contractor, his subcontractors and their employees shall not have access to or be admitted into any building outside the scope of this contract except with official permission.

tract drawing. On any of the drawings where a portion of the work is detailed or drawn out and the remainder is shown in outline, the parts detailed or drawn out shall apply also to all other like portions of the work.

(b) Where the word "similar" occurs on the drawings, it shall have a general meaning and not be interpreted as be identical, and all details shall be worked out in relation to their location and their connection with other parts of the work.

(c) Standard Details or Specification Drawings are applicable when listed, bound with the specifications, noted on the drawings or referenced elsewhere in the specifications. Where the notes on the drawings indicate modifications, such modifications shall govern.

(d) In case of difference between Standard Details or Specification Drawings and the specifications, the specifications will govern. In case of difference between the Standard Details or Specification Drawings and the drawings prepared specifically for this contract, the later shall govern.

(End of Clause)

(End of Clause)

552.236-76 Measurements.

As prescribed in 536.570–7, insert the following clause:

MEASUREMENTS (APR 1984) All dimensions shown of existing work and all dimensions required for work that is to connect with work now in place, shall be verified by the Contractor by actual measurement of the existing work. Any discrepancies between the contract requirements and the existing conditions shall be referred to the Contracting Officer before any work affected thereby has been performed.

552.236-78 Shop drawings, coordina

tion drawings, and schedules. As prescribed in 536.570-9, insert the following clause: SHOP DRAWINGS, COORDINATION DRAWINGS,

AND SCHEDULES (APR 1984) The requirements, of the clause entitled “Specifications and Drawings" at FAR 52.236-21, are supplemented as follows:

(a) The Contractor shall submit shop drawings, coordination drawings, and schedules for approval as required by the specifications or requested by the Contracting Officer as follows:

(b) Shop drawings shall include fabrication, erection and setting drawings, schedule drawings, manufacturers' scale drawings, wiring and control diagrams, cuts or entire catalogs, pamphlets, descriptive literature, and performance and test data.

(c) Drawings and schedules, other than catalogs, pamphlets and similar printed material, shall be submitted in reproducible form with two prints made by a process ap proved by the Contracting Officer. Upon approval, the reproducible form will be returned to the Contractor who shall then furnish the number of additional prints, not to exceed 10, required by the specifications. The Contractor shall submit shop drawings in catalog, pamphlet and similar printed form in a minimum of four copies plus as many additional copies as the Contractor may desire or need for his use or use by subcontractors.

(d) Before submitting shop drawings on the mechanical and electrical work, the Contrac

(End of Clause)

552.236–77 Specifications and Draw

ings. As prescribed in 536.570-8, insert the following clause:

SPECIFICATIONS AND DRAWINGS (APR 1984) The requirements of the clause entitled “Specifications and Drawings" at FAR 52.236-21, are supplemented as follows:

(a) In case of difference between small and large-scale drawings, the large-scale drawings shall govern. Schedules on any contract drawing shall take precedence over conflicting information on that or any other con

tor shall submit and obtain the Contracting Officer's approval of such lists of mechanical and electrical equipment and materials as may be required by the specifications.

(e) Each shop drawing or coordination drawing shall have a blank area 5 by 5 inches, located adjacent to the title block. The title block shall display the following: Number and title of drawing Date of drawing or revision Name of project building or facility Name of contractor and (if appropriate)

name of subcontractor submitting drawing Clear identity of contents and location on

the work Project title and contract number

(f) Unless otherwise provided in this contract, or otherwise directed by the Contracting Officer, shop drawings, coordination drawings and schedules shall be submitted to the Contracting Officer, with a letter in triplicate, sufficiently in advance of construction requirements to permit no less than 10 working days for checking and appropriate action.

(g) Approval of drawings and schedules will be general and shall not be construed as permitting any departure from the contract requirements, or as approving departures from full-size details furnished by the Contracting Officer.

information required in paragraph (b) of this clause. He shall enclose a copy of this letter with the shipment and send a copy to the Government representative on the project. Approval of a sample shall be only for the characteristics or use named in such approval and shall not be construed to change or modify any contract requirement. Substitutions will not be permitted unless they are approved in writing by the Contracting Officer.

(d) Approved samples not destroyed in testing will be sent to the Government rep resentative at the project. Approved samples of hardware in good condition will be marked for identification and may be used in the work. Materials and equipment, incorporated in the work shall match the ap proved sainples. Other samples not destroyed in testing or not approved will be returned to the Contractor at his expense if so requested at time of submission.

(e) Failure of any material to pass the specified tests will be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make

that material or equipment which previously has proved unsatisfactory in service.

(f) Samples of various materials or equipment delivered on the site or in place may be taken by the Government representative for testing. Samples failing to meet contract requirements will automatically void previous approvals of the items tested. The Contractor shall replace such materials or equipment found not to have met contract requirements, or there shall be a proper adjustment of the contract price as determined by the Contracting Officer.

(g) Unless otherwise specified, when tests are required only one test of each sample proposed for use will be made at the expense of the Government. Samples which do not meet specification requirements will be rejected. Testing of additional samples will be made by the Government at the expense of the Contractor.

(End of Clause)

(End of Clause)

552.236–79 Samples.

As prescribed in 536.570–10, insert the following clause:

SAMPLES (APR 1984) (a) After the award of the contract, the Contractor shall furnish for the approval of the Contracting Officer samples required by the specifications or by the Contracting Officer. Samples shall be delivered to the Contracting Officer or to the Architect as specified or as directed. The Contractor shall prepay all shipping charges on samples. Materials or equipment for which samples are required shall not be used in the work until approved in writing by the Contracting Officer.

(b) Each sample shall have a label indicating:

(1) Name of project building or facility, project title and contract number

(2) Name of Contractor and, if appropriate, name of subcontractor

(3) Identification of material or equipment with specification requirement

(4) Place of origin
(5) Name of producer and brand (if any)

Samples of finished materials shall have additional markings that will identify them under the finish schedules.

(c) The Contractor shall mail under separate cover a letter in triplicate submitting each shipment of samples and containing the

552.236-80 Heat.

As prescribed in 536.570–11, insert the following clause:

HEAT (APR 1984) Unless otherwise specified or unless already provided by the Government the Contractor shall;

(a) Provide heat, as necessary to protect all work, materials, and equipment against injury from dampness and cold;

(b) Protect, cover and/or heat as may be necessary, to produce and maintain a temperature of not less than 50 degrees Fahrenheit (1) in the concrete during the placing, setting and curing of concrete, and (2) in the (End of Clause)

plaster during the application, setting and curing of plaster; and

(c) Provide heat as necessary in the area where work is to be done to provide the minimum temperature recommended by the supplier or manufacturer of the material, but in no case less than 50 degrees Fahrenheit, for a period beginning 10 days before placing of interior finishes and finish materials and continuing until completion or beneficial occupancy of the area, whichever is earlier.

552.236-83 Furnishing information

and records. As prescribed in 536.570–14, insert the following clause:

(End of Clause)

552.236-81 Use of equipment by the

Government. As prescribed in 536.570-12, insert the following clause:

USE OF EQUIPMENT BY THE GOVERNMENT (APR

1984) (a) The Government may take over and operate, with Government employees, such equipment as is necessary for heating or cooling such areas of the building as require the service, as soon as the installation is sufficiently complete.

(b) The Contracting Officer will advise the Contractor by letter, prior to the use of equipment, which items of equipment will be operated, and the date and time such operation will begin.

(C) Government operation of equipment will not relieve the Contractor of the oneyear guarantee on materials and workmanship elsewhere provided for in this contract.

(d) The guarantee period, elsewhere provided for in this contract, for each piece of equipment shall be in accordance with the "Guarantees" clause of this contract.

FURNISHING INFORMATION AND RECORDS (APR

1984) (a) If the Contractor or any subcontractor under this contract or the officers or agents of the Contractor or any subcontractor, refuses, except as provided by the terms of this contract, to furnish to any Government agency or any establishment in the legislative or judicial branch of the Government information or records reasonably pertinent to this contract, the following actions may be taken:

(1) In the case of a refusal by the Contractor, its officers or agents, the Government may, after affording an opportunity to explain or justify such refusal, terminate the Contractor's right to proceed with the work. The rights and remedies provided in this clause are in addition to those outlined in paragraph (a) of the Default (Fixed-Price Construction) clause at FAR 52.249–10, paragraph (b) of the Liquidated Damages—Construction clause at FAR 52.212-5 and to any other rights and remedies provided by law or under this contract;

(2) In the case of a refusal by a subcontractor, its officers or agents, the Government may, after affording an opportunity to explain or justify such refusal, require the Contractor to terminate the subcontract without cost to the Government, or if the Contractor fails or refuses to effect such termination, the Government may terminate the Contractor's right to proceed with the work under this contract and thereupon the Government may avail itself of the rights and remedies referred to in subparagraph (a)(1) of this clause.

(b) The term "subcontract” as used in this paragraph means any contract entered into or any purchase order issued by a prime contractor under a contract with the Government in connection with the performance of the prime contractor's obligations under this contract.

(c) The term "subcontractor" as used in this paragraph means a party to a subcontract other than the prime contractor under this contract.

(End of Clause)

552.236-82 Subcontracts.

As prescribed in 536.570–13, insert the following clause:

SUBCONTRACTS (APR 1984) (a) Nothing contained in the contract shall be construed as creating any contractual relationship between any subcontractor and the Government. The divisions or sections of the specifications are not intended to control the Contractor in dividing the work among subcontractors, or to limit the work performed by any trade.

(b) The Contractor shall be responsible to the Government for acts and omissions of his own employees and of subcontractors and their employees. He shall also be responsible for the coordination of the work of the trades, subcontractors and suppliers.

(c) The Government will not undertake to settle any differences between or among the Contractor, subcontractors, or suppliers.

(End of Clause)

552.237-70 Qualifications of offerors.

As prescribed in 537.110(a), insert the following provision:

« PreviousContinue »