Implementation of Subcontracting Provisions of Public Law 95-507: Hearing Before the Subcommittee on General Oversight and Minority Enterprise of the Committee on Small Business, House of Representatives, Ninety-sixth Congress, First Session ...U.S. Government Printing Office, 1980 - Minority business enterprises |
From inside the book
Results 1-5 of 100
Page 4
... determine whether a sec- tion 211 - type subcontracting program is appropriate for these contracts . The second problem area , Mr. Chairman , concerns what constitutes an adequate goal . Public Law 95-507 requires a percentage goal for ...
... determine whether a sec- tion 211 - type subcontracting program is appropriate for these contracts . The second problem area , Mr. Chairman , concerns what constitutes an adequate goal . Public Law 95-507 requires a percentage goal for ...
Page 5
... determine whether or not they could or should be modified . Of the contracts on which review and action is complete , it appears that some- what over fifty percent are being modified to include the provisions . I must add a note of ...
... determine whether or not they could or should be modified . Of the contracts on which review and action is complete , it appears that some- what over fifty percent are being modified to include the provisions . I must add a note of ...
Page 7
... determine whether a section 211 type subcon- tracting program is appropriate for those contracts . What constitutes ... determines in writing that such clause would be inappropriate . However , the procuring agencies ' ability to ...
... determine whether a section 211 type subcon- tracting program is appropriate for those contracts . What constitutes ... determines in writing that such clause would be inappropriate . However , the procuring agencies ' ability to ...
Page 8
... determine which will be modified 671 , $ 5,000,000,000 . Policy letter 80-1 . ATTACHMENT EXECUTIVE OFFICE OF THE PRESIDENT , OFFICE OF MANAGEMENT AND BUDGET , Washington , D.C. , January 24 , 1980 . To the heads of executive departments ...
... determine which will be modified 671 , $ 5,000,000,000 . Policy letter 80-1 . ATTACHMENT EXECUTIVE OFFICE OF THE PRESIDENT , OFFICE OF MANAGEMENT AND BUDGET , Washington , D.C. , January 24 , 1980 . To the heads of executive departments ...
Page 16
... determine the extent of subcontracting program compliance . The following addition should therefore be made : " and ( iv ) conduct such studies or surveys as may be necessary to determine the extent of contractor or subcontractor ...
... determine the extent of subcontracting program compliance . The following addition should therefore be made : " and ( iv ) conduct such studies or surveys as may be necessary to determine the extent of contractor or subcontractor ...
Other editions - View all
Common terms and phrases
accordance adjustment agency amended amount AMSL applicable approval ASPR Block Business and Small changes CLIN Code compliance computer software concerns and small Cont'd CONTINUATION SHEET Contracting Officer contracts awarded controlled by socially Cost Accounting Standards Data Item DATE DD Form Defense delivery digital processor Disadvantaged Business Utilization DITEG dollar economically disadvantaged individuals equipment evaluation furnished goals Government HUGHES AIRCRAFT COMPANY identified implementation Interface LAFALCE List maintenance Minority Business Enterprises modification NADC negotiated OFFEROR OR CONTRACTOR operation paragraph performance Prime Contractor prior procedures production progress payments proposed Public Law purchase pursuant QUANTITY regulations requested Revision schedule Section 211 Small and Disadvantaged Small Business Act Small Business Administration small business concerns small disadvantaged business socially and economically solicitations specific subcontracting plan Subcontracting Program submitted supplies target cost TITLE tooling Utilization of Small
Popular passages
Page 583 - Officer, if he decides that the facts justify such action, may receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes.
Page 143 - Which is at least 51 percent owned by one or more socially and economically disadvantaged individuals; or, in the case of any publicly owned business, at least 51 per centum of the stock of which is owned by one or more socially and economically disadvantaged individuals; and (2) Whose management and daily business operations are controlled by one or more of such individuals.
Page 776 - Socially disadvantaged individuals are those who have been subjected to racial or ethnic prejudice or cultural bias because of their identity as a member of a group without regard to their individual qualities.
Page 562 - In the event of the contractor's noncompliance with the requirements of this clause, actions for noncompliance may be taken in accordance with the rules, regulations and relevant orders of the Secretary of Labor issued pursuant to the Act.
Page 121 - (B) The contractor hereby agrees to carry out this policy in the awarding of subcontracts to the fullest extent consistent with the efficient performance of this contract.
Page 276 - CONCERNS (a) It Is the policy of the Government as declared by the Congress that a fair proportion of the purchases and contracts for supplies and services for the Government be placed with small business concerns. (b) The Contractor agrees to accomplish the maximum amount of subcontracting to small business concerns that the Contractor finds to be consistent with the efficient performance of this contract. [End of Clause] (b) The Small Business Subcontracting Program...
Page 586 - Officer may have the Invoices or vouchers and statements of cost audited. Each payment theretofore made shall be subject to reduction for amounts Included In the related Invoice or voucher which are found by the Contracting Officer, on the basis of such audit, not to constitute allowable cost. Any payment may be reduced for overpayments, or Increased for underpayments, on preceding Invoices or vouchers.
Page 560 - The decision of the Contracting Officer shall be final and conclusive and not subject to review by any forum, tribunal, or Government agency unless an appeal or action is timely commenced within the times specified by the Contract Disputes Act of 1978.
Page 122 - Americans, and other minorities, or any other individual found to be disadvantaged by the Small Business Administration pursuant to section 8(a) of the Small Business Act.
Page 589 - Contractor's business; or (B) all or substantially all of the Contractor's operations at any one plant or separate location, in which this contract is being performed...