(3) The total final price of the items referred to in paragraph (a) above shall be evidenced by a modification to this contract signed by the Contractor and the Contracting Officer. Such price shall not be subject to revision notwithstanding any changes in the cost of performing the contract, with the following exceptions:

(i) insofar as the parties may agree in writing, prior to the determination of the total final price, (A) to exclude any specific elements of cost from the total final price and (B) to a procedure to provide subsequent disposition of such elements; and

(ii) to the extent any adjustment or credit is explicitly permitted or required by this or any other clause of this contract.

(e) Subcontracts. No subcontract placed under this contract shall provide for payment on a cost-plus-a-percentage-of-cost basis.

(1) Adjust:nent of Payments. Pending execution of the contract modification referred to in subparagraph (d)(3) above, the Contractor shall submit invoices or vouchers in accordance with billing prices as provided in this paragraph. The billing prices shall be the target prices set forth in this contract; provided, that if at any time it appears that the then current billing prices will be substantially greater than the estimated final price in light of information provided by the Contractor in accordance with the provisions of subparagraph (g)(2) below, a reduction in the billing prices shall be negotiated. Similarly, the parties may negotiate an increase in billing prices by any or all of the difference between the target price and the ceiling price upon submission of factual data from the Centractor showing that final costs under this contract will be substantially greater than target cost.

[blocks in formation]
[blocks in formation]

Any adjustment of billing prices shall be reflected in a modification to this contract, and shall not affect the determination of the total final price under paragraph (d) above. After execution of the contract modification referred to in subparagraph (d)(3) above, the total amount paid or to be paid on all invoices or vouchers shall be adjusted to reflect the total final price and any additional payments, refunds, or credits, resulting therefrom shall be promptly made.

[blocks in formation]

(1) This paragraph (g) shall not apply after final price revision.

(2) Within forty-five (45) days after the end of each quarter of the Contractor's fiscal year, beginning for the quarter in which a delivery is first made (or services are first performed) and accepted by the Government under. this contract, and as of the end of each quarter, the Contractor shall submit to the Contracting Officer, with a copy thereof to the cognizant contract auditor, a cumulative statement setting forth:

(i) the total contract price of all supplies delivered (or services performed) and accepted by the Government for which final prices have been established;

(ii) on DD Form 633-6 or other format approved by the Contracting Officer, the total costs (estimated to the extent necessary) reasonably incurred for and properly allocable solely to the supplies delivered (or services performed) and accepted by the Government for which final prices have not been established;

(iii) that portion of the total target profit which is in direct proportion to the supplies delivered (or services performed) and accepted by the Government for which final prices have not been established, increased or decreased in accordance with the incentive profit formula set forth in (d)(2) above when the amount of costs stated under (ii) above differs from the aggregate target costs of such supplies or services; and

(iv) the total amount of all invoices or vouchers for supplies delivered (or services performed) and accepted by the Government (including amounts applied or to be applied to liquidate

[blocks in formation]

(3) Notwithstanding any provision of this contract authorizing greater payments, if on any quarterly statement the amount of (2)(iv) above exceeds the sum of (2)(i), (ii), and (iii) above, the Contractor shall immediately refund or credit to the Government against existing unpaid invoices or vouchers covered by such statement the amount of such excess less (i) the cumulative total of any previous refunds or credits under this clause (exclusive of any tax credits under Section 1481 of the Internal Revenue Code of 1954) and (ii) any applicable tax credits under Section 1481 of the Internal Revenue Code of 1954. If any portion of such excess has been applied to the liquidation of progress payments, such amount (less all tax credits under the Internal Revenue Code) may be added or restored to the unliquidated progress payment account, to the extent consistent with the "Progress Payments" clause of this contract, instead of direct refund thereof.

(4) The Contractor shall (i) insert in each price redetermination or incentive price revision subcontract hereunder the substance of this paragraph (g), including this subparagraph (4), modified to omit mention of the Government and reflect the position of the Contractor as purchaser and of the subcontractor as vendor, and to omit that portion of subparagraph (3) relating to tax credits, and (ii) include in each cost-reimbursement type subcontract hereunder a requirement that each price redetermination and incentive price revision subcontract thereunder will contain the substance of this paragraph (g), including this subparagraph (4) modified as outlined in (i) above.

(h) Disagreements. If the Contractor and the Contracting Officer fail to agree upon the total final price within 60 days after the date on which the data required by (c) above are to be submitted, or within such further time as may be specified by the Contracting Officer, such failure to agree shall be deemed to be a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract and the Contracting Officer shall promptly issue a decision thereunder.

(i) Termination. If this contract is terminated prior to establishment of the total final price, prices of supplies or services subject to price revision under this clause shall be established pursuant to this clause for (i) completed supplies accepted by the Government and services performed and accepted by the Government, and (ii) in the event of a partial termination, supplies and services which are not terminated. The termination shall be otherwise accomplished pursuant to other applicable provisions of this contract.

(j) Equitable Adjustment Under Other Clauses. If an equitable adjustment in the contract price is made under any other clause of this contract before the total final price is established, the adjustment shall be made in the total target cost and may be made in the maximum dollar limit on the total final price, the total target profit or both. If such an adjustment is made after the total final price is established, adjustment shall be made only in the total final price.

Page LIO

Contract DAAK30-77-C-0018

SECTION L (Cont'd)

GENERAL PROVISIONS

(k)

Exclusion From Target Price and Total Final Price. Whenever any clause of this contract provides that the contract price does not or will not include an amount for a specific purpose, such provision shall mean that neither any target price nor the total final price includes or will include any amount for such purpose.

(1) Separate Reimbursement. The cost of performance of an obligation that any clause of this contract expressly provides is at Government expense shall not be included in any target price or in the total final price, but shall be reimbursed separately.

(m) Taxes. As used in the "Federal, State and Local Taxes" clause of this contract or any other clause of this contract that provides for. certain taxes or duties to be included in, or excluded from, the contract price, the term "contract price" includes the total target price, or if it has been established, the total final price. When a provision in such clause or clauses requires that the contract price be increased or decreased as a result of changes in the obligation of the Contractor to pay or bear the burden of certain taxes or duties, such increase or decrease shall be made in the total target price or, if it has been established, in the total final price, so as not to affect the contractor's profit or loss on this contract.

Page L11

Contract DAAK 30-77-C-0018

SECTION L (Cont'd)

GENERAL PROVISIONS

10.

Mandatory Small Business Subcontracting Program

(a) It is the policy of the Government that small business concerns shall have the maximum practicable opportunity to participate in the performance of Government contracts.

(b) The contractor agrees to use his best efforts to carry out this policy in the award of his subcontracts to the fullest extent consistent with the efficient performance of this contract. A "small business concern" is a concern that meets the pertinent criteria established by the Small Business Administration (SBA) and set forth in paragraph 1-701 of the Armed Services Procurement Regulation.

(c) In keeping with national policy, it is the US Army objective that a vigorous procurement program be accomplished at the prime contractor and subcontractor levels to ensure the equitable participation of small business concerns in accomplishment of TE/PEP LRIP. The US Army has assessed the possibilities for small business subcontracting opportunities involving TE/PEP LRIP work in support of this procurement requirements and has concluded that reasonable opportunities do exist. It is the US Army's firm belief that, in consonance with each offerors design approach, a proportionate share of the total dollar value of all subcontracts resulting from this prime contract should be awarded to small business concerns as defined above. Accordingly, each offeror shall indicate, by percentage, the applicable proportionate share. ( 9%)

(d) The offeror, prior to any contract award shall submit a Small Business Subcontracting Program plan which (i) clearly describes how the prospective contractor, in the event of contract award, and by means of this plan, proposes to implement the governmental policy stated in (a) above, and (ii) takes into account the estimated proportionate share stated in (c) above. The plan submitted will be considered by the Government in its overall assessment of each offerors response.

(e) Upon contract award, the contractor agrees to implement and aggressively conduct, for the life of this contract, the program for the utilization of small business concerns established in accordance with paragraph (d) above. In this connection, the contractor shall:

(1) Designate a liaison officer who will (i) administer the contractor's "Mandatory Small Business Subcontracting Program" and (ii) maintain liaison with the Government on small business matters.