Page images
PDF
EPUB

not later than one year from the date the Government takes such possession. The Contractor, at his own expense, shall also remedy damage to equipment, the site, or the buildings or the contents thereof which is the result of any failure or defect, and restore any work damaged in fulfilling the terms of this clause. Should the Contractor fail to remedy any such failure or defect within a reasonable time after receipt of notice therof, the Government shall have the right to replace, repair, or otherwise remedy such failure or defect at the Contractor's expense. This warranty shall not delay final acceptance of or final payment for the contract work.

(b) All subcontractors', manufacturers' and suppliers' warranties and guaranties, express or implied, respecting any part of the work and any materials used therein shall be deemed obtained-and shall be enforced-by the Contractor as the agent and for the benefit of the Government without the necessity of separate transfer or assignment thereof, provided that, if directed by the Contracting Officer, the Contractor shall require such subcontractors, manufacturers and suppliers to execute such warranties and guaranties in writing to the Government.

(c) Any work repaired or replaced pursuant to this clause shall also be subject to the provisions of this clause to the same extent as work originally performed. The rights and remedies of the Government provided in this clause are in addition to and do not limit any rights afforded to the Government by any other clause of this contract.

[33 F.R. 265, Jan. 9, 1968]

[blocks in formation]

To the extent that a variation is caused by the conditions specified in the clause in § 7.103-4 of this chapter, that quantity may be accepted only to the extent specified in the Schedule. Except as set forth in § 1.325-2, the permissible variation shall be stated as a percentage and may be an increase, a decrease, or a combination of both. There should be no standard or usual percentage or variation. Each procurement for which an overrun or underrun is permissible should be based upon the normal commercial practices of the particular industry for particular items, and the permitted percentage should be no larger than is necessary to afford a contractor reasonable protection. In no event shall the permissible variation exceed plus or minus 10 percent. The clause set forth below shall be included in the Schedule, only when one or more of the causes of quantity variation foreseeable exists at the time of solicitation.

[blocks in formation]

Consideration shall be given to the quantity to which the percentage variation applies. For example, when it is contemplated that delivery will be made to multiple destinations and it is desired that the quantity variation extend to the item quantity for each destination, this requirement must be set forth with particularity. Similarly, when it is desired that the quantity variation extend to the total quantity of each item and not to the quantity for each destination, it may be desirable to express a percentage limitation for each destination to prevent unrealistic distribution of any increase or decrease.

[31 F.R. 7807, June 2, 1966]

§ 1.325-2 Subsistence.

The permissible variation in the procurement of small quantities of subsistence may be stated in the Schedule as follows:

(a) Standard pack items purchased on a package, carton, can or other than pound basis: maximum variation for 250 units or less-ne a rest full shipping container.

(b) Non-standard pack items other than carcass meats not purchased on a package, carton, or can basis: maximum variation for 250 pounds or less-nearest piece or shipping container.

(c) Carcass meats: maximum variation for 500 pounds or less-nearest piece, quarter, side or carcass.

[31 F.R. 7807, June 2, 1966]

§ 1.326 Component breakout.
130 F.R. 14887, Dec. 2, 1965]
§ 1.326-1 Scope.

(a) Sections 1.326-1-1.326-5 set forth guidance for making decisions on whether or not components should be purchased by the Government directly

*Insert in the blank the designation(s) to which the percentages apply, such as: (1) The total contract quantity; (2) item 1 only; (3) each quantity specified in the delivery schedule of the "Time of Delivery" clause; (4) the total item quantity for each destination; (5) the total quantity of each item without regard to destination.

and furnished to an end item contractor as Government-furnished material, for incorporation in the end item. Sections 1.326-1-1.326-5, however, do not pertain to all such decisions, but only to those which deal with whether components have been included as contractorfurnished material in a previous procurement of the end item should be "broken out" from a forthcoming end item procurement for direct Government purchase. Thus, §§ 1.3261-1.326-5 do not pertain to the initial Government-furnished equipment/contractor-furnished equipment decisions that must be made at the inception of a procurement program.

(b) Items procured as spare parts are governed by the "DOD High Dollar Spare Parts Breakout Program" described in DOD Joint Regulation AR 715–22, NAVMATINST P4200.33, AFR 57-6, MCO P4200.13, DSAM 4105.2, and are not covered by §§ 1.326-1-1.326–5.

(c) Sections 1.326-1-1.326-5 apply to procurements of weapons systems or other items of major equipment involving components whose direct purchase by the Government may result in substantial net cost savings over the life of the procurement program. Accordingly, they will seldom be applicable to a procurement of such a system or item of less than $1,000,000. The term "component”, as used in §§ 1.326-1-1.326-5, includes subsystems, assemblies, subassemblies, and other major elements of an end item, but does not include elements of relatively small annual purchase value.

[30 F.R. 14887, Dec. 2, 1965]

§ 1.326-2 Policy.

Whenever it is anticipated that the prime contract for a weapons system or other major end item will be awarded without adequate price competition, and the prime contractor is expected to acquire a component without such competition, it is Department of Defense policy to break out that component it:

(a) Substantial net cost savings will probably be achieved; and

(b) Such action will not jeopardize the quality, reliability, performance or timely delivery of the end item.

The desirability of breakout should also be considered (regardless of whether the prime contract or the component being purchased by the prime contractor is on the basis of price competition) whenever substantial net cost savings will result

(1) from greater quantity purchase or (2) from such factors as improved logistics support through reduction in varieties of spare parts and economies in operations and training through standardization of design. Primary breakout consideration shall be given to those components of the end item representing the highest annual procurement costs and offering the largest potential net savings through breakout.

[30 F.R. 14887, Dec. 2, 1965] § 1.326-3

Responsibility for component breakout selection, review and decision.

The project manager (or if there is no project manager such other official as may be designated by the Head of the Procuring Activity) supported by a project team (to include cognizant engineering, production, logistics, maintenance and other appropriate personnel, and the contracting officer or his designee) shall be responsible for:

(a) Earmarking as susceptible to break out those components potentially conforming to the criteria and policy set forth herein;

(b) Conducting the breakout review and evaluation described in § 1.326-4.

(c) Making the decision whether or not to break out the component; and

(d) Preparing records explaining such decision in compliance with § 1.326-5. [30 F.R. 14887, Dec. 2, 1965]

§ 1.326-4 Breakout guidelines.

(a) Each decision on whether or not to break out a component must embrace (1) assessment of the potential risks of degrading the end item through such contingencies as delayed delivery and reduced reliability of the component, (2) calculation of estimated net cost savings (i.e., estimated purchase savings less any offsetting costs), and (3) analysis of the technical, operational, logistic and administrative factors involved. As to each of these, the decision must be supported by adequate explanatory information, including an assessment by, and consultation with, the end item contractor where feasible.

(b) In deciding whether a component should be broken out, the guidelines set forth below (in the form of questions) should be considered. Answers will rarely be "positively yes" or "positively no" but usually "probably yes" or "probably no," with the degree of probability governed by the facts of the particular

case. The decision will depend largely upon the degree and significance of the risks to quality performance, reliability and timely delivery of the end item which would be involved in breakout and upon the estimated overall cost savings. Where the risks, if any, are acceptable and breakout is expected to result in substantial overall cost savings, the component should be broken out. On the other hand, if such risks are unacceptable, the components should not be broken out.

(1) Are the design of the component (and the design of the end item insofar as it will affect the component) sufficiently stable that further design or engineering effort by the end item contractor in respect to the component is unlikely to be required?

(2) Is a suitable data package available with rights to use it for Government procurement? (Note that breakout may be warranted even though competitive procurement is not possible.) (See Subpart B, Part 9 of this chapter.)

(3) Can any problems of quality control and reliability of the component be resolved without requiring effort by the end item contractor?

(4) Is it anticipated that requirements for technical support (i.e., functions such as development of proposed detailed specifications; development of test requirements to prove design adequacy or compliance with design; monitoring tests to assure compliance with established requirements; definition of quality assurance requirements for production of articles; and analysis and correction of service-revealed deficiencies) here. tofore performed by the end item contractor will be negligible? If not, does the Government have the resources (manpower, technical competence, facilities, etc.) to provide such support, or can such support be obtained from the end item contractor (even though the component is broken out) or other source?

(5) Can breakout be accomplished without causing unacceptable difficulties in logistics support (e.g., be jeopardizing requisite standardization of components)?

(6) Can breakout be accomplished without causing overfragmentation of the end item that might materially impede administration, management, and performance of the end item contact (e.g., by unduly complicating production scheduling or identifying (and fixing re

sponsibility for) end item failure that may be caused by a defective component) ?

(7) Can breakout be accomplished without jeopardizing delivery requirements of the end item?

(8) If a decision is made to break out a component and to acquire it from a new source, can advance procurement funds be made available to provide that source any necessary additional lead time?

(9) Is there a source other than the present manufacturer capable of supplying the component?

(10) Has the component been (or is it known that it is going to be) purchased directly by the Government as a support item in the supply system or as GFE in other end items?

(11) Would the financial risks and other responsibilities being assumed by the prime contractor that will have to be assumed by the Government if the item is broken out be acceptable?

(12) Will breakout result in substantial net cost savings? Estimates of probable savings in cost should be developed for each case on its own facts, with consideration given to any estimated off-setting costs such as increases in the cost of requirements determination and control, contracting, contract administration, data package purchase, material inspection, qualification or preproduction testing, ground support and test equipment, transportation, security, storage, distribution, and technical support.

(c) If application of the guidelines in paragraph (b) of this section reveals conditions currently unfavorable to breakout, the feasibility of eliminating such conditions should be considered. For example, where adequate technical support is not available from Government resources, or similar assistance must be obtained in order to successfully accomplish breakout, consideration should be given to the procurement of the necessary services, such as product assurance suitability services, from the end item contractor or other qualified

source.

[30 F.R. 14887, Dec. 2, 1965, as amended at 33 F.R. 7348, May 18, 1968]

§ 1.326-5 Records and review procedure.

The records of the purchasing activity shall contain documentation of:

(a) Those components which have been reviewed and determined to have no potential for breakout;

(b) Those components which have been reviewed and earmarked as being susceptible to breakout pursuant to § 1.326-3; and

(c) Those components for which a decision to break out has been made. Documentation of these three categories, and for those components once earmarked but no longer considered susceptible to breakout, shall be signed by the cognizant project manager or other designated official and reflect the facts and conditions of the case, including any assessment by the contractor, and the basis for the decision. Components that have been earmarked for potential breakout shall be reviewed well in advance of each successive procurement, with a decision made as to whether the component will be broken out for the ensuing procurement. Such reviews, made preferable in the course of requirements determination, but in any event before procurement of the requirement is initiated, shall be repeated until a final decision on whether or not to break out is reached, and shall be documented. When breakout is delayed or postponed, the documentation shall include a description of the actions required to accomplish breakout, identify the activities responsible for such actions, and indicate the fiscal year when breakout should be effected.

[30 F.R. 14888, Dec. 2, 1965, as amended at 31 F.R. 1039, Jan. 27, 1966]

§ 1.327 Use of excess aluminum in National stockpile.

[31 F.R. 9851, July 21, 1966]

§ 1.327-1 Government Use Program.

It has been determined to be in the public interest to establish a Government Use Program requiring, to the maximum practicable extent, purchase of excess aluminum in the Government stockpile by defense contractors, directly or through subcontractors or suppliers, equal in weight to the weight of aluminum products as defined in § 1.327-2, purchased by the Government or used in the production of items delivered under defense contracts. In implementation of this Program, all contracts in the categories listed below, shall contain the clause in § 1.327-2, or in the case of

construction contracts, the clause as modified in § 1.327-3:

(a) Purchases in the amount of $500 or more of aluminum products as defined in § 1.327-2.

(b) Purchases of supplies or construction in the amount of $25,000 or more where the aluminum products used in the production of items delivered under the contract or in the production of items incorporated in construction performed under the contract are estimated by the contracting officer to approximate 10,000 pounds or more.

In

These provisions do not apply to pro-
curements of supplies or construction
effected by procuring activities located
outside, for use outside, the United
States, its possessions, and Puerto Rico.
These provisions are applicable to new
procurements that are effected by
amendments to an existing contract.
such cases, only the new procurement
portion of the total contract is considered
in determining whether the clause is
required and, if required, the extent of
its applicability. Copies of all aluminum
controlled material allotments made to
contractors, together with a showing of
any modifications or quantity adjust-
ments thereto, shall be forwarded by
the allotting activity to GSA at the ad-
dress specified in the contract clause
within 30 days following the calendar
quarter for which all or any portion of
the allotment was made. Copies or
pertinent abstracts of all contracts or
purchase orders for aluminum products
(subject to paragraph (a) of this sec-
tion) and modifications affecting alumi-
num product quantities shall be for-
warded by the purchasing activity to
GSA at the same address.

[31 F.R. 9851, July 21, 1966]
§ 1.327-2 Contract clause.

REQUIRED SOURCE FOR ALUMINUM INGOT
(MARCH 1966)

(a) As used in this clause (1) the term "aluminum products" means aluminum or aluminum alloy in its last commercial form delivered by the producer, mill, or foundry as an end item under this contract, or used to produce an end item under this contract, such as by way of example (but not limited to) wrought aluminum products; forgings and castings; rolled bar, rod, structural shapes, and bare wire; aluminum conductor steel reinforced and bare aluminum cable; insulated or covered wire or cable; extruded bar, rod, shapes and tube (extruded, drawn, and welded tube); sheet, strip, and plate,

pig or ingot; granular or shot; slab; foil; and powder, flake, or paste; and (ii) the term "supplier" includes vendors, materialmen, warehousemen, distributors, or manufacturers of aluminum products or other items containing aluminum in any form.

a

(b) Except as provided in (c) below, the Contractor (or subcontractor or supplier, where applicable) shall purchase from the General Services Administration (GSA) quantity of aluminum pig or ingot equal in weight to the gross weight of aluminum products constituting, or used in the production of, the items to be delivered under this contract. Such purchase shall be in accordance with the terms and conditions of sale prescribed therefor by GSA. Each order placed with GSA pursuant to this clause shall state that it is placed in accordance therewith and shall be sent to:

Director, Industry Materials Division, Defense Materials Service, General Services Administration, Washington, D.C. 20405. Aluminum purchased pursuant to this clause may be used in any manner the Contractor desires and need not be earmarked in any way after delivery to the Contractor, nor physically incorporated in the items to be delivered hereunder.

(c) To the extent the Contractor (or subcontractor or supplier, where applicable) places subcontracts or purchase orders for aluminum products or for items other than aluminum products and containing aluminum in any form, he is not required with respect to such subcontracts or purchase orders to purchase aluminum from the GSA. However, he agrees to incorporate this clause, except paragraph (d):

(i) In any such subcontract or purchase order for aluminum products in the total amount of $500 or more, or

(ii) In any such subcontract or purchase order in the total amount of $25,000 or more for any items containing aluminum in any form where the quantity of aluminum products used in the production of such items is estimated to be 10,000 pounds or more.

(d) The Contractor shall furnish to the GSA, calendar quarter summaries (within 30 days following the close of the applicable quarter) of all subcontracts and purchase orders placed by him pursuant to (c) (i) above that will identify (1) each aluminum product supplier involved, (ii) the quantity (by weight) of aluminum products, and (iii) the Authorized Control Material allotment number if any, applicable to specific quanties. The requirements of this paragraph (d) are applicable only to the prime Contractor and not to any subcontractor or other supplier hereunder. This reporting requirement has been approved by the Bureau of the Budget in accordance with the Federal Reports Act of 1942.

(e) The requirements of this clause are not intended to preclude basic agreements or other arrangements between the parties to

any contracts (subcontracts or purchase orders) subject to this clause that will permit reference in such contracts to the applicability of the requirements of this clause, without the need for physically incorporating this clause in its entirety in each affected subcontract or purchase order.

(f) In placing subcontracts and purchase orders subject to the clause, the Contractor and all subcontractors and suppliers are authorized and encouraged to consolidate aluminum product purchases hereunder with other defense rated order purchases (ACM, DO, or DX) and other identifiable Government orders so as to apply the requirements of this clause to the total purchase. Otherwise, it is required either that aluminum product purchases subject to this clause be separately made, or, if consolidated with other aluminum product purchases, that the quantities (by weights) of aluminum products subject to this clause be separately set forth in the purchase document and identified as subject to this clause.

(g) Required purchases of aluminum from GSA by Contractors, subcontractors, or suppliers, shall be made within 90 days from the date (i) of final delivery pursuant to a contract, subcontract, or purchase order containing the requirements of this clause, or (ii) when the Contractor, subcontractor or supplier, has completed deliveries of aluminum products aggregating 100,000 pounds, whichever is earlier: Provided, however, That any Contractor, subcontractor, or supplier, may defer required purchases of aluminum for the purpose of consolidating purchases to meet the requirement of two or more contracts, subcontracts, or purchase orders containing this clause until 90 days after the aggregate purchase requirements of such contracts, subcontracts, or purchase orders equal the minimum order quantities established by GSA (approximately 10,000 pounds or more). Successive consolidated purchases thereafter may be made at any time within 90-day intervals. The 90-day limitations may be extended upon approval in writing by the GSA.

(h) Certain producers of aluminum have entered into contracts with GSA effective as of November 1, 1965, under which they have made long term commitments to purchase certain minimum and maximum quantities of aluminum from that Agency. The obligations of such producers under this clause shall be governed by the provisions of those contracts to the extent of any inconsistency.

(i) All purchases made pursuant to this clause, other than from GSA, are required to be rated (ACM, DO or DX) in accordance with DMS Regulation 1, NPA Order M-5A and BDSA Regulation 2, and are subject to the provisions of those regulations concerning the maintenance of records, rights of inspection and audit, and the penalty provisions contained therein for willful noncompliance.

[31 F.R. 9851, July 21, 1966]

« PreviousContinue »