Such causes may include, but are not restricted to, acts of God or of the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually... The Code of Federal Regulations of the United States of America - Page 2711962Full view - About this book
| Administrative law - 1983 - 782 pages
...floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather; but in every case the failure to perform must be beyond...arises out of causes beyond the control of both the Cootractor and subcontractor, and without the fault or negligence of either of them, the Contractor... | |
| Administrative law - 1978 - 880 pages
...floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather; but in every case the failure to perform must be beyond...such default arises out of causes beyond the control oi both the Contractor and subcontractor, and without the fault or negligence of either of them, the... | |
| Administrative law - 1985 - 738 pages
...quarantine restrictions, strikes, freight embargoes, and unusually severe weather; but in every case failure to perform must be beyond the control and...causes beyond the control of both the Contractor and the subcontractor, and without the fault or negligence of either of them, the Contractor shall not... | |
| Administrative law - 1982 - 1316 pages
...floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather; but in every case the failure to perform must be beyond...the default of a subcontractor, and if such default anses out of causes beyond the control of both the Contractor and subcontractor, and without the fault... | |
| Administrative law - 1977 - 1240 pages
...floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather; but In every case the failure to perform must be beyond...perform Is caused by the default of a subcontractor, and U such default arises out of causes beyond the control of both the Contractor and subcontractor, and... | |
| Administrative law - 1969 - 628 pages
...floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather; but in every case the failure to perform must be beyond...the failure to perform is caused by the default of а subcontractor, and if such default arises out of causes beyond the control of both the Contractor... | |
| Administrative law - 1981 - 524 pages
...unusually severe weather; but in every case the failure to perform must be beyond ths control and without the fault or negligence of the Contractor. If the...default arises out of causes beyond the control of bolh the Contractor and subcontractor, and without the fault or negligence of either of them, the Contractor... | |
| Administrative law - 1964 - 1202 pages
...floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather, but In every case the failure to perform must be beyond...Contractor. If the failure to perform Is caused by the failure of a subcontractor to perform or make progress, and if such failure arises out of causes beyond... | |
| Administrative law - 1974 - 348 pages
...floods; epidemics; quarantine restrictions; strikes; freight embargoes; and unusually severe weather; but in every case the failure to perform must be beyond...Contractor. If the failure to perform is caused by the failure of a subcontractor to perform or make progress, and If such failure arises out of causes beyond... | |
| Administrative law - 1970 - 670 pages
...unusually severe weather; but in every case the failure to perform must be beyond tbe control and without the fault or negligence of the Contractor. If the...subcontractor, and If such default arises out of causes beyond tbe control of both the Contractor and subcontractor, and without the fault or negligence of either... | |
| |