B. Equipment associated with this project which will be provided from other appropriations: NONE.

Activity POC: CDR ROBERT SCHLESINGER Phone No: 360-396-4640

JOINT USE CERTIFICATION:

The Deputy Chief of Naval Operations (Fleet Logistics and Readiness) certifies that this project has been considered for joint use potential. construction is recommended. The reason for this recommendation is:

Unilateral

Mission requirements, operational considerations, and location are incompatible with use by other components.

Form

DD Dec 76 1391C

Submitted to Congress

Page No. 279-280

[merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][ocr errors][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][ocr errors][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small]

Supports the Trident Submarine Launched Ballistic Missile System by maintaining and operating facilities for administration and personnel support for operations of the submarine force. Provides logistics support to other activities in the area and acts as host for the following: Trident Submarine Squadron, Trident Refit Facility, Trident Training Facility, Strategic Weapons Facility, Pacific, Marine Corps Security Force.

[blocks in formation]

Page No. 281-282

[merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][ocr errors][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small]

Construct a concrete tilt-up building with fire protection and alarm system, data and communications (telephone, public address, central monitoring) cabling, to house seven shops/groups (Tile Setters; Towed Array Alignment; Sandblast and Painting Equipment Maintenance; Shipwright; Nuclear Freeze Shop: Divers; and Squadron 17 (Performance Monitoring Team)) that are being displaced from buildings near the Marginal Wharf.

Utilities will consist of a new transformer, electrical and water service,

Form

DD 1 Dec 76 1391

Submitted to Congress

(Continued On DD 1391C)

Page No. 283

[blocks in formation]

Built-in

sewage lift station, compressed air, and oil/water separator. equipment includes a 5-ton overhead bridge crane. The project will provide parking for 100 vehicles and a paved lay-down area to support the shops/groups. Four buildings will be demolished as part of this project totalling 1,692 square meters (18,210 square feet). The construction of this project will include anti-terrorism/force protection features. 11. Requirement:

1,858 m2

Adequate: 0 m2

Substandard:

0 m2

PROJECT:

This project constructs a building to house seven shops that are being displaced from their existing buildings due to the introduction of the D-5 missile to Naval Submarine Base Bangor, WA. (Current mission)

REQUIREMENT:

Adequate facilities are required to house the shops at the Marginal Wharf. With the introduction of the D-5 missile system, the explosive arc distances from the Explosive Handling Wharf (EHW) to other facilities will extend further out. The net explosive weight for the D-5 is greater than the net explosive weight for the C-4 missile. The complete Marginal Wharf complex will be encompassed by the explosive arc from the Explosive Handling Wharf. Therefore, no personnel will be permitted within that arc and the shops must be relocated before the introduction of the D-5, presently set for 1 July 2002.

CURRENT SITUATION:

Until this project is completed, personnel in the encumbered shops will have to cease work and vacate during D5 handling operations at the EHW, resulting in work delay and lost productivity.

IMPACT IF NOT PROVIDED:

The Department of Defense Explosive Safety Board (DDESB) will not permit the continued operations of the shops on or near the Marginal Wharf, within the arc generated by the D-5 missile being handled at the EHW. If this project is not completed, the buildings currently used for the shops/groups will have to be vacated during missile evolutions at a cost in lost work time. This explosive safety issue has to be addressed by relocating the shops/groups.

[blocks in formation]

Submitted to Congress

Page No. 284

[blocks in formation]

A. Estimated Design Data: (Parametric estimates have been used to develop project costs. Project design conforms to Part II of Military Handbook 1190, Facility Planning and Design guide)

[blocks in formation]

B. Equipment associated with this project which will be provided from other appropriations: NONE.

Activity POC: MR. GEORGE SHEPARD Phone No: (360) 396-5013

[blocks in formation]

Submitted to Congress

Page No. 285