| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1968 - 922 pages
...writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor...receive and act upon any such claim asserted at any time/prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1959 - 1028 pages
...in writing within 30 days from the date of receipt by the Contractor of the notification of extra or change : Provided, however, That the Contracting Officer,...upon any such claim asserted at any time prior to the date of final settlement of the contract. If the parties fail to agree upon the adjustment to be... | |
| Administrative law - 1974 - 918 pages
...delivery. (b) If any such change causes an increase or decrease In the estimated cost of, or the tune required for the performance of any part of the work...upon any such claim asserted at any time prior to flnal payment under this contract. Failure to agree to any adjustment shall be a dispute concernIng... | |
| Administrative law - 1982 - 988 pages
...equitable adjustment shall be made (a) in the estimated cost or delivery schedule, or both, and (b) in such other provisions of the contract as may be...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's... | |
| Administrative law - 1955 - 1316 pages
...delivery schedule, or both, (11) In the amount of any fixed fee to be paid to the Contractor, and (111) In such other provisions of the contract as may be...decides that the facts Justify such action, may receive ana act upon any such claim asserted at any time prior to final payment under this contract. Failure... | |
| Administrative law - 1966 - 968 pages
...equitable adjustment shall be made In the estimated cost, the completion schedule, or both, and the contract shall be modified in writing accordingly....upon any such claim asserted at any time prior to § 7.702-5 final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| Administrative law - 1978 - 880 pages
...equitable adjustment shall be made (a) in the estimated cost or delivery schedule, or both, and (b) in such other provisions of the contract as may be...Contracting Officer, if he decides that the facts justify sucn action, may receive and act upon any such claim asserted at any time prior to final payment under... | |
| Administrative law - 2000 - 568 pages
...equitable adjustment shall be made (a) in the estimated cost or delivery schedule, or both, and (b) in such other provisions of the contract as may be...Provided, however, That the Contracting Officer, if he/she decides that the facts justify such action, may receive and act upon any such claim asserted... | |
| Administrative law - 1985 - 592 pages
...the estimated cost or delivery schedule, or both, and (b) in such Appendix A— Public Health Service other provisions of the contract as may be so affected,...Provided, however, That the Contracting Officer, if he/she decides that the facts justify such action, may receive and act upon any such claim asserted... | |
| Administrative law - 1998 - 656 pages
...adjustment shall be made (i) in the contract price or time of performance, or both, and (ii) in such provisions of the contract as may be so affected,...Provided, however, That the Contracting Officer, if he/she decides that the facts justify such action, may receive and act upon any such claim asserted... | |
| |