CONTRACT CLAUSES AND SOLICITATION PROVISIONS

7-304.1 Changes.

CHANGES (1965 JUN)

The Contracting Officer may at any time, by a written order, and without notice to the sureties, if any, make changes, within the general scope of this contract, in any one or more of the following: (i) drawings, designs, or specifications; (ii) method of shipment or packing; and (iii) place of inspection, delivery, or acceptance. If any such change causes an increase or decrease in the cost of, or the time required for performance of, this contract, or otherwise affects any other provisions of this contract, whether changed or not changed by any such order, an equitable adjustment shall be made (i) in the contract price or time of performance, or both, and' (ii) in such other provisions of the contract as may be so affected, and the contract shall be modified in writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor of the notification of change; provided, however, that the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled “Disputes". However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed.

(End of clause)

In the foregoing clause, the period of "thirty (30) days" within which any claim for adjustment must be asserted, may be varied in accordance with Departmental procedures. In accordance with 10 U.S.C. 2306(f), prior to the pricing of any change order that is expected to exceed $100,000, except where the price is based on adequate price competition, established catalog or market prices of commercial items sold in substantial quantities to the general public, or prices set by law or regulation, the contracting officer shall require the contractor to furnish a Certificate of Current Cost or Pricing Data (see 3-807.6) and shall assure the contract includes or is modified to include a defective pricing data clause (see 7-104.29).

7-304.2 Alterations in Contract. The clause in 7-105.1(a) may be inserted. 7-304.3 Approval of Contract. The clause in 7-105.2 may be inserted. 7-304.4 Bill of Materials. In accordance with 7-105.6, the clause set forth therein may be inserted.

7-304.5 Notice of Shipments. The clause in 7-105.4 may be inserted.

7-304.6 Reports of Work. In accordance with 7-404.6, the clause set forth therein may be inserted.

7-304.7 Liquidated Damages. In accordance with 1-310, the clause in 7-105.5 may be inserted.

7-304.8 Reserved.

7-304.9 Reserved.

7-304.10 Warranties. In accordance with 1-324, an appropriate warranty may be inserted.

7-304.11 Stop Work Orders. In accordance with 7-105.3, the clause set forth therein may be inserted.

7-304.12 Term of Performance or Delivery Date. Insert a clause in accordance with 1-305.5. Clauses in 7-104.92 shall be used as a guide.

7-304.12

ARMED SERVICES PROCUREMENT REGULATION

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

Part 4-Cost-Reimbursement Type Research and Development Contracts

7-400 Scope of Part. This Part sets forth uniform contract clauses for use in cost-reimbursement type research and development contracts as defined in

7-401.

7-401 Applicability. As used throughout this Part, the term "cost-reimbursement type research and development contract” shall mean any contract (other than a letter contract, notice of award, or modification not effecting new procurement) which (i) is entered into on a cost, cost-sharing or cost-plus-a-fee basis as covered in 3-405, and (ii) is for experimental, developmental, or research work.

7-402 Required Clauses. The following clauses shall be inserted, as required, in all cost-reimbursement type research and development contracts.

7-402.1 Definitions. In accordance with 7-103.1, insert the clause therein. 7-402.2 Limitation of Cost or Funds.

(a) The following clause shall be used in fully funded cost-reimbursement type research and development contracts which do not provide for cost-sharing. The words "exclusive of any fee", occurring twice in paragraph (a) of the clause, may be deleted in any contract not providing for the payment of a fee.

LIMITATION OF COST (1966 OCT)

(a) It is estimated that the total cost to the Government for the performance of this contract, exclusive of any fee, will not exceed the estimated cost set forth in the Schedule, and the Contractor agrees to use his best efforts to perform the work specified in the Schedule and all obligations under this contract within such estimated cost. If, at any time, the Contractor has reason to believe that the cost which he expects to incur in the performance of this contract in the next succeeding sixty (60) days, when added to all costs previously incurred, will exceed seventy-five percent (75%) of the estimated cost set forth in the Schedule, or if, at any time, the Contractor has reason to believe that the total cost to the Government for the performance of this contract, exclusive of any fee, will be greater or substantially less than the then estimated cost hereof, the Contractor shall notify the Contracting Officer in writing to that effect, giving the revised estimate of such total cost for the performance of this contract.

(b) Except as required by other provisions of this contract specifically citing and stated to be an exception from this clause, the Government shall not be obligated to reimburse the Contractor for costs incurred in excess of the estimated cost set forth in the Schedule, and the Contractor shall not be obligated to continue performance under the contract (including actions under the Termination clause) or otherwise to incur costs in excess of the estimated cost set forth in the Schedule, unless and until the Contracting Officer shall have notified the Contractor in writing that such estimated cost has been increased and shall have specified in such notice a revised estimated cost which shall thereupon constitute the estimated cost of performance of this contract. No notice, communication or representation in any other form or from any person other than the Contracting Officer shall affect the estimated cost of this contract. In the absence of the specified notice, the Government shall not be obligated to reimburse the Contractor for any costs in excess of the estimated cost set forth in the Schedule, whether those excess costs were incurred during the course of the contract or as a result of termination. When and to the extent that the estimated cost set forth in the Schedule has been increased, any costs incurred by the Contractor in excess of the estimated cost prior to such increase shall be allowable to the same extent as if such costs had been incurred after the increase; unless the Contracting Officer issues a termination or other notice and directs that the increase is solely for the purpose of covering termination or other specified expenses

(c) Change orders issued pursuant to the Changes clause of this contract shall not be considered an authorization to the Contractor to exceed the estimated cost set forth in the Schedule in the absence of a statement in the change order, or other contract modification, increasing the estimated cost.

7-402.2

ARMED SERVICES PROCUREMENT REGULATION

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

(d) In the event this contract is terminated or the estimated cost not increased the Government and the Contractor shall negotiate an equitable distribution of all property produced or purchased under the contract based upon the share of costs incurred by each.

(End of clause)

(b) The following clause shall be used in fully funded cost-reimbursement type research and development contracts which provide for cost-sharing. The contract schedule shall include a cost-sharing formula agreed upon by the parties prior to execution of the contract. This formula shall provide for the ratio of costsharing with regard to both the originally established total estimated cost and any increase thereto, pursuant to (b) of the clause.

LIMITATION OF COST (COST-SHARING) (1973 MAY)

(a) It is estimated that the cost to the Government for the performance of this contract (exclusive of any fee) will not exceed the estimated cost to the Government set forth in the Schedule, and the Contractor agrees to use his best efforts to perform the work specified in the Schedule and all obligations under this contract within such estimated cost to the Government plus the share of the cost of performance agreed to be borne by the Contractor, as set forth in the Schedule. If, at any time, the Contractor has reason to believe that the costs which he expects to be incurred in the performance of this contract in the next succeeding sixty (60) days, when added to all costs previously incurred, will exceed seventy-five percent (75%) of the estimated total cost to the Government and to the Contractor then set forth in the Schedule, or if, at any time, the Contractor has reason to believe that the total cost for the performance of this contract (exclusive of any fee) will be greater or substantially less than the then estimated total cost thereof, the Contractor shall notify the Contracting Officer in writing to that effect, giving his revised estimate of such total cost for the performance of this contract.

(b) Except as required by other provisions of this contract specifically citing and stated to be an exception from this clause, the Government shall not be obligated to reimburse the Contractor for costs incurred in excess of the estimated cost to the Government set forth in the Schedule, and the Contractor shall not be obligated to continue performance under the contract (including actions under the Terminations clause) or otherwise to incur costs in excess of the estimated total cost set forth in the Schedule, unless and until the Contracting Officer shall have notified the Contractor in writing that such estimated total cost has been increased and shall have specified in such notice a revised estimated total cost which shall thereupon constitute the estimated total cost of performance of this contract. The increase in such estimated total cost shall be allocated in accordance with the formula set forth in the Schedule governing such increases. No notice, communication or representation in any other form or from any person other than the Contracting Officer shall affect the estimated cost to the Government of this contract. In the absence of the specified notice, the Government shall not be obligated to reimburse the Contractor for any costs in excess of the estimated cost to the Government set forth in the Schedule, whether those excess costs were incurred during the course of the contract or as a result of termination. When and to the extent that the estimated total cost set forth in the Schedule has been increased, any costs incurred by the Contractor in excess of the estimated total cost prior to such increase shall be allowable to the same extent and in the same percentage as if such costs had been incurred after the increase; unless the Contracting Officer issues a termination or other notice and directs that the increase is solely for the purpose of covering termination or other specified expenses.

(c) Change orders issued pursuant to the Changes clause of this contract shall not be considered an authorization to the Contractor to exceed the estimated cost to the Government set forth in the Schedule in the absence of a statement in the change order, or other contract modification, increasing the estimated cost.

(d) In the event this contract is terminated or the estimated cost not increased, the Government and the Contractor shall negotiate an equitable distribution of all property produced or purchased under the contract based upon the share of costs incurred by each.

(End of clause)

7-402.2

ARMED SERVICES PROCUREMENT REGULATION

90-107 0-82-24

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

(c) The following clause shall be used in incrementally funded cost-reimbursement type research and development contracts which do not provide for cost sharing.

LIMITATION OF FUNDS (1966 OCT)

(a) It is estimated that the cost to the Government for the performance of this contract will not exceed the estimated cost set forth in the Schedule, and the Contractor agrees to use his best efforts to perform the work specified in the Schedule and all obligations under this contract within such estimated cost.

(b) The amount presently available for payment and allotted to this contract, the items covered thereby, and the period of performance which it is estimated the allotted amount will cover, are specified in the Schedule. It is contemplated that from time to time additional funds will be allotted to this contract up to the full estimated cost set forth in the Schedule, exclusive of any fee. The Contractor agrees to perform or have performed work on this contract up to the point at which the total amount paid and payable by the Government pursuant to the terms of this contract approximates but does not exceed the total amount actually allotted to the contract.

(c) If at any time the Contractor has reason to believe that the costs which he expects to incur in the performance of this contract in the next succeeding sixty (60) days, when added to all costs previously incurred, will exceed seventy-five percent (75%) of the total amount then allotted to the contract, the Contractor shall notify the Contracting Officer in writing to that effect. The notice shall state the estimated amount of additional funds required to continue performance for the period set forth in the Schedule. Sixty (60) days prior to the end of the period specified in the Schedule the Contractor will advise the Contracting Officer in writing as to the estimated amount of additional funds, if any, that will be required for the timely performance of the work under the contract or for such further period as may be specified in the Schedule or otherwise agreed to by the parties. If, after such notification, additional funds are not allotted by the end of the period set forth in the Schedule or an agreed date substituted therefor, the Contracting Officer will, upon written request by the Contractor, terminate this contract pursuant to the provisions of the Termination clause on such date. If the Contractor, in the exercise of his reasonable judgment, estimates that the funds available will allow him to continue to discharge his obligations hereunder for a period extending beyond such date, he shall specify the later date in his request and the Contracting Officer, in his discretion, may terminate this contract on that later date.

(d) Except as required by other provisions of this contract specifically citing and stated to be an exception from this clause, the Government shall not be obligated to reimburse the Contractor for costs incurred in excess of the total amount from time to time allotted to the contract, and the Contractor shall not be obligated to continue performance under the contract (including actions under the Termination clause) or otherwise to incur costs in excess of the amount allotted to the contract, unless and until the Contracting Officer has notified the Contractor in writing that such allotted amount has been increased and has specified in such notice an increased amount constituting the total amount then allotted to the contract. To the extent the amount allotted exceeds the estimated cost set forth in the Schedule, such estimated cost shall be correspondingly increased. No notice, communication or representation in any other form or from any person other than the Contracting Officer shall affect the amount allotted to this contract. In the absence of the specified notice, the Government shall not be obligated to reimburse the Contractor for any costs in excess of the total amount then allotted to the contract, whether those excess costs were incurred during the course of the contract or as a result of termination. When and to the extent that the amount allotted to the contract has been increased, any costs incurred by the Contractor in excess of the amount previously allotted shall be allowable to the same extent as if such costs had been incurred after such increase in the amount allotted; unless the Contracting Officer issues a termination or other notice and directs that the increase is solely for the purpose of covering termination or other specified expenses.

(e) Change orders issued pursuant to the Changes clause of this contract shall not be considered an authorization to the Contractor to exceed the amount allotted in the Schedule in the absence of a statement in the change order, or other contract modification, increasing the amount allotted.

7-402.2

ARMED SERVICES PROCUREMENT REGULATION

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

(f) Nothing in this clause shall affect the right of the Government to terminate this contract. In the event this contract is terminated, the Government and the Contractor shall negotiate an equitable distribution of all property produced or purchased under the contract based upon the share of costs incurred by each.

(g) In the event that sufficient funds are not allotted to this contract to allow completion of the work contemplated by this contract, the Contractor shall be entitled to that percentage of the fee set forth in the Schedule equivalent to the percentage of completion of the work contemplated by this contract.

(End of clause)

(d) The following clause shall be used in incrementally funded cost-reimbursement type research and development contracts which provide for cost-sharing.

LIMITATION OF FUNDS (COST-SHARING) (1966 OCT)

(a) It is estimated that the cost to the Government for the performance of this contract will not excced the estimated cost to the Government set forth in the Scheduie, and the Contractor agrees to use his best efforts to perform the work specified in the Schedule and all obligations under this contract within such estimated cost to the Government plus the share of the cost of performance agreed to be borne by the Contractor, as set forth in the Schedule.

(b) The amount presently available for payment by the Government and allotted to this contract, the items covered thereby, the Government's share of the cost thereof, and the period of performance which it is estimated the allotted amount will cover, are specified in the Schedule. It is contemplated that from time to time additional funds will be allotted to this contract up to the full estimated cost to the Government set forth in the Schedule, exclusive of any fixed fee. The Contractor agrees to perform or have performed work on this contract up to the point at which the total amount paid and payable by the Government pursuant to the terms of this contract approximates but does not exceed the total amount actually allotted by the Government to the con

tract.

(c) If at any time the Contractor has reason to believe that the costs which he expects to incur in the performance of this contract in the next succeeding sixty (60) days, when added to all costs previously incurred, will exceed seventy-five percent (75%) of the total of the amount then allotted to the contract by the Government plus the Contractor's corresponding share, the Contractor shall notify the Contracting Officer in writing to that effect. The notice shall state the estimated amount of additional funds required to continue performance for the period set forth in the Schedule. Sixty (60) days prior to the end of the period specified in the Schedule the Contractor will advise the Contracting Officer in writing as to the estimated amount of additional funds, if any, that will be required for the timely performance of the work under the contract or for such further period as may be specified in the Schedule or otherwise agreed to by the parties. If, after such notification, additional funds are not allotted by the end of the period set forth in the Schedule or an agreed date substituted therefor, the Contracting Officer will, upon written request by the Contractor, terminate this contract pursuant to the provisions of the Termination clause on such date. If the Contractor, in the exercise of his reasonable judgment, estimates that the funds available will allow him to continue to discharge his obligations hereunder for a period extending beyond such date, he shall specify the later date in his request, and the Contracting Officer, in his discretion, may terminate on that later date.

(d) Except as required by other provisions of this contract specifically citing and stated to be an exception from this clause, the Government shall not be obligated to reimburse the Contractor for costs incurred in excess of the amount from time to time allotted by the Government to the contract, and the Contractor shall not be obligated to continue performance under the contract (including actions under the Termination clause) or otherwise to incur costs in excess of the total of the amount then allotted to the contract by the Government plus the Contractor's corresponding share, unless and until the Contracting Officer has notified the Contractor in writing that the amoun allotted by the Government has been increased and has specified in such notice an increased amount constituting the total amount then allotted by the Government to the contract. To the extent the total of the amount allotted by the Government plus the Contractor's cor

7-402.2

ARMED SERVICES PROCUREMENT REGULATION