...Subject to the provisions of paragraph c, the Contractor and the Contracting Officer may agree upon the whole or any part of the amount or amounts to be paid...and the Contractor shall be paid the agreed amount. Nothing in paragraph e of this clause, prescribing the amount to be paid to the Contractor in the 147... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1963 - 938 pages
...Subject to the provisions of paragraph (c), the Contractor and the Contracting Officer may agree upon the whole or any part of the amount or amounts to be paid...amounts may include a reasonable allowance for profit, but only on work done in connection with the terminated portion of the contract. The contract shall... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1954 - 1160 pages
...an interest. 100 Finding! of Fact (c) The Contractor and the Contracting Officer may agree upon the whole or any part of the amount or amounts to be paid...total or partial termination of work pursuant to this Article, which amount or amounts may include a reasonable allowance for profit, and the Government... | |
| Administrative law - 1939 - 1306 pages
...Government has or may acquire an Interest. (c) The contractor and the contracting officer may agree upon the whole or any part of the amount or amounts to be paid...total or partial termination of work pursuant to this Article, which amount or amounts may Include a reasonable allowance for profit, and the Government... | |
| United States. Office of War Mobilization - Government publications - 1944 - 128 pages
...Government has or may acquire an interest. (c) The contractor and the contracting officer may agree upon the whole or any part of the amount or amounts to be paid...total or partial termination of work pursuant to this article, which amount or amounts may include a reasonable allowance for profit, and the Government... | |
| United States. War Department - 1944 - 72 pages
...Contracts (PR 15-901) provides that the contractor and the contracting officer may agree upon "the whole or any part of the amount or amounts to be paid...contractor by reason of the total or partial termination of the work." It is also provided that in the event a negotiated settlement cannot be agreed upon, for... | |
| United States. Congress. House. Committee on Naval Affairs - 1944 - 1320 pages
...Government has or may acquire an Interest. (r) The contractor and the contracting officer may agree upon the whole or any part of the amount or amounts to be paid to the contractor by reason of the total <T partial termination of work pursuant to this article, which amount or amounts may include a reasonable... | |
| United States. Congress. House. Committee on Naval Affairs - 1944 - 1312 pages
...contractor and the contracting offleer may agree upon the whole or any part of the amount or amounts to he paid to the contractor by reason of the total or partial termination of work pursuant to this article, which amount or amounts may include a reasonable allowance for profit, and the Government... | |
| Administrative law - 1964 - 676 pages
...Subject to the provisions of paragraph (c), the Contractor and the Contracting Officer may agree upon the whole or any part of the amount or amounts to be paid...agreed amount. (e) In the event of the failure of the Contractor and the Contracting Officer to agree in whole or in part, as provided in paragraph (d)... | |
| |