Page images
PDF
EPUB

(b) Cost-reimbursement type letter contracts. In accordance with the requirements of § 18-16.859-2, the following clause shall be included in letter contracts which are expected to be cɔnverted to cost-reimbursement type definitive contracts:

TERMINATION (JANUARY 1964)

(a) In case a definitive contract is not executed by the date specified in Article VI of the Schedule, because of the inability of the parties to agree upon a definitive contract, this Letter Contract may be terminated in its entirety by either party by delivering to the other party a notice in writing specifying the effective date of termination, which date shall not be earlier than thirty (30) days after receipt of such notice.

(b) The performance of work under this Letter Contract also may be terminated by the Government in accordance with this clause in whole, or from time to time in part:

(1) whenever the Contractor shall default in performance of this Letter Contract in accordance with its terms (including in the term "default" any such failure by the Contractor to make progress in the prosecution of the work hereunder as endangers such performance), and shall fail to cure such default within a period of 10 days (or such longer period as the Contracting Officer may allow) after receipt from the Contracting Officer of a notice specifying the default; or

(ii) whenever for any reason the Contracting Officer shall determine that such termination is in the best interest of the Government.

Any such termination shall be effected by delivery to the Contractor of a Notice of Termination specifying whether termination is for the default of the Contractor or for the convenience of the Government, the extent to which performance of work under this Letter Contract is terminated, and the date upon which such termination becomes effective. If, after notice of termination of this Letter Contract for default under (i) above, it is determined for any reason that the Contractor was not in default pursuant to (i) above, or that the Contractor's failure to perform or to make progress in performance is due to causes beyond the control and without the fault or negligence of the Contractor pursuant to the provisions of the clause of this Letter Contract relating to excusable delays, the Notice of Termination shall be considered to have been issued under (ii) above, and the rights and obligations of the parties hereto shall in such event be governed accordingly.

(c) After receipt of a Notice of Termination and except as otherwise directed by the Contracting Officer the Contractor shall:

(1) stop work under this Letter Contract on the date and to the extent specified in the notice of termination;

(ii) place no further orders or subcontracts for materials, services, or facilities, except as may be necessary for completion of such portion of the work under this Letter Contract as is not terminated;

(iii) terminate all orders and subcontracts to the extent that they relate to the performance of work terminated by the Notice of Termination;

(iv) assign to the Government, in the manner, at the times, and to the extent directed by the Contracting Officer, all of the right, title, and interest of the Contractor under the orders and subcontracts so terminated, in which case the Government shall have the right, in its discretion, to settle or pay any or all claims arising out of the termination of such orders and subcontracts;

(v) with the approval or ratification of the Contracting Officer, to the extent he may require, which approval or ratification shall be final and conclusive for all purposes of this clause, settle all outstanding liabilities and all claims arising out of such termination of orders and subcontracts, the cost of which would be reimbursable in whole or in part, in accordance with the provisions of this Letter Contract;

(vi) transfer title (to the extent that title has not already been transferred) and, in the manner, to the extent, and at the times directed by the Contracting Officer, deliver to the Government: (A) The fabricated or unfabricated parts, work in process, completed work, supplies, and other material produced as a part of, or acquired in respect of the performance of, the work terminated by the Notice of Termination; (B) The completed or partially completed plans, drawings, information, and other property which, if this Letter Contract had been completed, would be required to be furnished to the Government; and (C) The jigs, dies, and fixtures, and other special tools, and tooling acquired or manufactured for the performance of this Letter Contract for the cost of which the Contractor has been or will be reimbursed under this Letter Contract;

(vii) use his best efforts to sell in the manner, at the times, to the extent, and at the price or prices directed or authorized by the Contracting Officer, any property of the types referred to in (vi) above: Provided, however, That the Contractor (A) shall not be required to extend credit to any purchaser, and (B) may acquire any such property under the conditions prescribed by and at a price or prices approved by the Contracting Officer; and: Provided further, That the proceeds of any such transfer or disposition shall be applied in reduction of any payments to be made by the Government to the Contractor under this Letter Contract or shall otherwise be credited to the price or cost of the work covered by this Letter Contract or paid in such other manner as the Contracting Officer may direct;

(viii) complete performance of such part of the work as shall not have been terminated by the Notice of Termination; and

(ix) take such action as may be necessary, or as the Contracting Officer may direct, for the protection and preservation of the property related to this Letter Contract which is in the possession of the Contractor and in which the Government has or may acquire an interest.

The Contractor shall proceed immediately with the performance of the above obligations notwithstanding any delay in determining the amount of any items of reimbursable cost, under this clause. At any time after expiration of the plant clearance period, as defined in Part 8, NASA Procurement Regulation, as it may be amended from time to time, the Contractor may submit to the Contracting Officer a list, certified as to quantity and quality, of any or all items of termination inventory not previously disposed of, exclusive of items the disposition of which has been directed or authorized by the Contracting Officer, and may request the Government to remove such items or enter into a storage agreement covering them. Not later than fifteen (15) days thereafter, the Government will accept such items and remove them or enter into a storage agreement covering the same: Provided, That the list submitted shall be subject to verification by the Contracting Officer upon removal of the items, or if the items are stored, within forty-five (45) days from the date of submission of the list, and any necessary adjustment to correct the list as submitted shall be made prior to final settlement.

(d) After receipt of a Notice of Termination, the Contractor shall submit to the Contracting Officer his termination claim in the form and with the certification prescribed by the Contracting Officer. Such claim shall be submitted promptly, but in no event later than one (1) year from the effective date of termination, unless one or more extensions in writing are granted by the Contracting Officer upon request of the Contractor made in writing within such one (1) year period or authorized extension thereof. However, if the Contracting Officer determines that the facts justify such action, he may receive and act upon any such termination claim at any time after such one (1) year period or any extension thereof. Upon failure of the Contractor to submit his termination claim within the time allowed, the Contracting Officer may, subject to any Settlement Review Board approvals required by NASA Regulations in effect on the date of the execution of this contract, determine, on the basis of information available to him, the amount, if any, due to the Contractor by reason of the termination, and shall thereupon pay to the Contractor the amount so determined.

(e) Subject to the provisions of paragraph (d) hereof, and subject to any Settlement Review Board approvals required by NASA Regulations in effect as of the date of execution of this Letter Contract, the Contractor and the Contracting Officer may agree upon the whole or any part of the amount or amounts to be paid to the Contractor by reason of the total or partial termination of work pursuant to this clause. In the event of any termination pursuant to paragraph (a) or (b) (i) hereof, such amount or amounts shall not include any allowance for fee. In the event of any termination pursuant to paragraph (b) (ii) hereof, such amount or amounts may include a reasonable allowance for fee, but only on work actually done in connection with the terminated portion of this Letter Contract. Any such amount shall not exceed the maximum amount specified in Article IIIa of the Schedule. Any such agreement shall be embodied in an amendment to this Letter Contract and the Contractor shall be paid the agreed amount.

(f) In the event of the failure of the Contractor and the Contracting Officer to agree in whole or in part, as provided in paragraph (c) above, as to the amount or amounts to be paid to the Contractor in connection with the termination of work pursuant to this clause, the Contracting Officer shall, subject to any Settlement Review Board approvals required by NASA Regulations in effect as of the date of execution of this Letter Contract, determine, on the basis of information available to him, and in accordance with the applicable cost principles of the NASA Procurement Regulation as in effect on the date of this Letter Contract, the amount, if any, due to the Contractor by reason of the termination and shall pay such amount to the Contractor. In the event of the termination of this Letter Contract pursuant to paragraph (a) or (b) (i) hereof, no allowance for fee shall be included in the amount to be paid the Contractor.

(g) The Contractor shall have the right of appeal, under the clause of this Letter Contract entitled "Disputes," from any determination made by the Contracting Officer under paragraph (d) or (f) above (including any disputes as to whether termination has in fact taken place pursuant to paragraph (a) or (b)(i) hereof), except that if the Contractor has failed to submit a claim within the time provided in paragraph (d) above and has failed to request extension of such time, he shall have no such right of appeal. In any case where the Contracting Officer has made a determination of the amount due under paragraph (d) or (f) above, the Government shall pay to the Contractor the following:

(i) If there is no right of appeal hereunder or if no timely appeal has been taken, the amount so determined by the Contracting Officer; or

(ii) If an appeal has been taken, the amount finally determined on such appeal.

(h) In arriving at the amount due the Contractor under this clause, there shall be deducted:

(i) All unliquidated advance or other payments theretofore made to the Contractor, applicable to the terminated portion of this Letter Contract;

(ii) Any claim which the Government may have against the Contractor in connection with this Letter Contract; and

(iii) The agreed price for, or the proceeds of sale of, any materials, supplies, or other things acquired by the Contractor or sold pursuant to the provisions of this clause and not otherwise recovered by or credited to the Government.

(i) The Government may from time to time, under such terms and conditions as it may prescribe, make partial payments and payments on account against costs incurred by the Contractor in connection with the terminated portion of this Letter Contract whenever in the opinion of the Contracting Officer the aggregate of such payments shall be within the amount to which the Contractor will be entitled hereunder. If the total of such payments is in excess of the amount finally agreed or determined to be due under this clause, such excess shall be payable by the Contractor to the Government upon demand, together with interest computed at the rate of 6 percent per annum, for the period from the date such excess payment is received by the Contractor to the date on which such excess is repaid to the Government: Provided, However, that no interest shall be charged with respect to any such excess payment attributable to a reduction in the Contractor's claim by reason of retention or other disposition of termination inventory until ten days after the date of such retention or disposition, or such later date as determined by the Contracting Officer by reason of the circumstances.

[29 F.R. 16602, Dec. 5, 1964, as amended at 31 F.R. 631, Jan. 18, 1966]

§ 18-8.703 Termination clause for fixedprice construction contracts.

The following clause shall be used in any fixed-price type construction contract in excess of $10,000.

TERMINATION FOR CONVENIENCE OF THE
GOVERNMENT (NOVEMBER 1964)

(a) The performance of work under this contract may be terminated by the Government in accordance with this clause in whole, or from time to time in part, whenever the Contracting Officer shall determine that such termination is in the best interest of the Government. Any such termination shall be effected by delivery to the Contractor of a Notice of Termination specifying the extent to which performance of work under the contract is terminated, and the date upon which such termination becomes effective.

(b) After receipt of a Notice of Termination, and except as otherwise directed by the Contracting Officer, the Contractor shall:

(i) Stop work under the contract on the date and to the extent specified in the Notice of Termination.

(ii) Place no further orders or subcontracts for materials, services, or facilities except as may be necessary for completion of such portion of the work under the contract as is not terminated;

(iii) Terminate all orders and subcontracts to the extent that they relate to the performance of work terminated by the Notice of Termination;

(iv) Assign to the Government, in the manner, at the times, and to the extent directed by the Contracting Officer, all of the right, title, and interest of the Contractor under the orders and subcontracts so terminated, in which case the Government shall have the right, in its discretion, to settle or pay any or all claims arising out of the termination on such orders and subcontracts;

(v) Settle all outstanding liabilities and all claims arising out of such termination of orders and subcontracts, with the approval or ratification of the Contracting Officer, to the extent he may require, which approval or ratification shall be final for all the purposes of this clause;

(vi) Transfer title to the Government and deliver in the manner, at the times, and to the extent, if any, directed by the Contracting Officer

(A) The fabricated or unfabricated parts, work in process, completed work, supplies, and other material produced as a part of, or acquired in connection with the performance of, the work terminated by the Notice of Termination; and

(B) The completed or partially completed plans, drawings, information, and other properties which, if the contract had been completed, would have been required to be furnished to the Government;

(vii) Use his best efforts to sell, in the manner, at the times, to the extent, and at the price or prices directed or authorized by the Contracting Officer, any property of the types referred to in (vi) above; provided, however, that the Contractor

(A) Shall not be required to extend credit to any purchaser, and

(B) May acquire any such property under the conditions prescribed and at a price or prices approved by the Contracting Officer: And provided further, That the proceeds of any such transfer or disposition shall be applied in reduction of any payments to be made by the Government to the Contractor under this contract or shall otherwise be credited to the price or cost of the work covered by this contract or paid in such other manner as the Contracting Officer may direct;

(viii) Complete performance of such part of the work as shall not have been terminated by the Notice of Termination; and

(ix) Take such action as may be necessary, or as the Contracting Officer may direct, for the protection and preservation of the property related to this contract which is in the possession of the Contractor and in which the Government has or may acquire an interest.

At any time after expiration of the plant clearance period as defined in Part 8, NASA Procurement Regulation, as it may be amended from time to time, the Contractor may submit to the Contracting Officer a list, certified as to quantity and quality, of any or all items of termination inventory not previously disposed of, exclusive of items the disposition of which has been directed or authorized by the Contracting Officer, and may request the Government to remove such items or enter into a storage agreement covering them. Not later than fifteen (15) days thereafter, the Government will accept title to such items and remove them or enter into a storage agreement covering the same; provided, that the list submitted shall be subject to verification by the Contracting Officer upon removal of the items, or if the items are stored, within forty-five (45) days from the date of submission of the list, and any necessary adjustment to correct the list as submitted shall be made prior to final settlement.

(c) After receipt of a Notice of Termination, the Contractor shall submit to the Contracting Officer his termination claim, in the form and with the certification prescribed by the Contracting Officer. Such claim shall be submitted promptly but in no event later than one (1) year from the effective date of termination, unless one or more extensions in writing are granted by the Contracting Officer, upon request of the Contractor made in writing within such one (1) year period or authorized extension thereof. However, if the Contracting Officer determines that the facts justify such action, he may receive and act upon any such termination claim at any time after such one (1) year period or extension thereof. Upon failure of the Contractor to submit his termination claim within the time allowed, the Contracting Officer may, subject to any Settlement Review Board approvals required by NASA Regulations in effect as of the date of execution of this contract, determine, on the basis of information available to him, the amount, if any, due to the Contractor by reason of the termination and shall thereupon pay to the Contractor the amount so determined.

(d) Subject to the provisions of paragraph (c), and subject to any Settlement Review Board approvals required by NASA Regulations in effect as of the date of execution of this contract, the Contractor and the Contracting Officer may agree upon the whole or any part of the amount or amounts to be paid to the Contractor by reason of the total or partial termination of work pursuant to this clause, which amount or amounts may

include a reasonable allowance for profit on work done: Provided, That such agreed amount or amounts, exclusive of settlement costs, shall not exceed the total contract price as reduced by the amount of payments otherwise made and as further reduced by the contract price of work not terminated. The contract shall be amended accordingly, and the Contractor shall be paid the agreed amount. Nothing in paragraph (e) of this clause, prescribing the amount to be paid to the Contractor in the event of failure of the Contractor and the Contracting Officer to agree upon the whole amount to be paid to the Contractor by reason of the termination of work pursuant to this clause, shall be deemed to limit, restrict, or otherwise determine or affect the amount or amounts which may be agreed upon to be paid to the Contractor pursuant to this paragraph (d).

(e) In the event of the failure of the Contractor and the Contracting Officer to agree as provided in paragraph (d) upon the whole amount to be paid to the Contractor by reason of the termination of work pursuant to this clause, the Contracting Officer shall, subject to any Settlement Review Board approvals required by NASA Regulations in effect as of the date of execution of this contract, determine, on the basis of information available to him, the amount, if any, due to the Contractor by reason of the termination and shall pay to the Contractor the amounts determined as follows:

(i) With respect to all contract work performed prior to the effective date of the Notice of Termination, the total (without duplication of any items) of—

(A) The cost of such work;

(B) The cost of settling and paying claims arising out of the termination of work under subcontracts or orders as provided in paragraph (b) (v) above, exclusive of the amounts paid or payable on account of supplies or materials delivered or services furnished by the subcontractor prior to the effective date of the Notice of Termination of work under this contract, which amounts shall be included in the cost on account of which payment is made under (A) above, and

(C) A sum, as a profit, equal to 2 percent of the part of the amount determined under (A) above which represents the cost of articles or materials delivered to the site but not incorporated in the work in place on the effective date of the Notice of Termination, plus a sum equal to 8 percent of the remainder of such amount, but the aggregate of such sums shall not exceed 6 percent of the whole of the amount determined under (A) above: Provided, however, That if it appears that the Contractor would have sustained a loss on the entire contract had it been completed, no profit shall be included or allowed under this subdivision (C) and an appropriate adjustment shall be made reducing the amount of the settlement to reflect the indicated rate of loss: and

(11) The reasonable cost of the preservation and protection of property incurred pursuant to paragraph (b)(ix); and any other reasonable cost incidental to termination of work under this contract, including expense incidental to the determination of the amount due to the Contractor as the result of the termination of work under this

contract.

The total sum to be paid to the Contractor under (1) above shall not exceed the total contract price as reduced by the amount of payments otherwise made and as further reduced by the contract price of work not terminated. Except for normal spoilage, and except to the extent that the Government shall have otherwise expressly assumed the risk of loss, there shall be excluded from the amounts payable to the Contractor under (i) above, the fair value, as determined by the Contracting Officer, of property which is destroyed, lost, stolen, or damaged so as to become undeliverable to the Government, or to a buyer pursuant to paragraph (b) (vii).

(f) Any determination of costs under paragraph (c) or (e) hereof shall be governed by the principles for consideration of costs set forth in Part 15, Subpart 4 of the NASA Procurement Regulation as in effect on the date of this contract.

(g) The Contractor shall have the right of appeal, under the clause of this contract entitled "Disputes," from any determination made by the Contracting Officer under paragraph (c) or (e) above, except that if the Contractor has failed to submit his claim within the time provided in paragraph (c) above and has failed to request extension of such time, he shall have no such right of appeal. In any case where the Contracting Officer has made a determination of the amount due under paragraph (c) or (e) above, the Government shall pay to the Contractor the following:

(i) If there is no right of appeal hereunder or if no timely appeal has been taken the amount so determined by the Contracting Officer; or

(ii) If an appeal has been taken, the amount finally determined on such appeal.

(h) In arriving at the amount due the Contractor under this clause there shall be deducted:

(i) All unliquidated advance or other payments on account theretofore made to the Contractor, applicable to the terminated portion of this contract;

(ii) Any claim which the Government may have against the Contractor in connection with this contract; and

(iii) The agreed price for, or the proceeds of sale of, any materials, supplies, or other things kept by the Contractor or sold, pursuant to the provision of this clause, and not otherwise recovered by or credited to the Government.

(1) If the termination hereunder be partial, prior to the settlement of the terminated portion of this contract, the Contractor may file with the Contracting Officer a request in writing for an equitable adjustment of the price or prices specified in the contract relating to the continued portion of the contract (the portion not terminated by the Notice of Termination), and such equitable adjustment as may be agreed upon shall be made in such price or prices; however, nothing contained herein shall limit the right of the Government and the Contractor to agree upon the amount or amounts to be paid to the Contractor for the completion of the continued portion of the contract when said contract does not contain an established contract price for such continued portion.

(j) The Government may from time to time, under such terms and conditions as it may prescribe, make partial payments and payments on account against costs incurred by the Contractor in connection with the terminated portion of this contract whenever in the opinion of the Contracting Officer the aggregate of such payments shall be within the amount to which the Contractor will be entitled hereunder. If the total of such payments is in excess of the amount finally agreed or determined to be due under this clause, such excess shall be payable by the Contractor to the Government upon demand, together with interest computed at the rate of 6 percent per annum, for the period from the date when such excess payment is received by the Contractor to the date on which such excess is repaid to the Government: Provided, however, That no interest shall be charged with respect to any such excess payment attributable to a reduction in the Contractor's claim by reason of retention or other disposition of termination inventory until ten days after the date of such retention or disposition, or such later date as determined by the Contracting Officer by reason of the circumstances.

(k) Unless otherwise provided for in this contract, or by applicable statute, the Contractor, from the effective date of termination and for a period of three years after final settlement under this contract, shall preserve and make available to the Government at all reasonable times at the office of the Contractor, but without direct charge to the Government, all his books, records, documents, and other evidence bearing on the costs and expenses of the Contractor under this contract and relating to the work terminated hereunder or, to the extent approved by the Contracting Officer, photographs, microphotographs, or other authentic reproductions thereof.

[31 F.R. 632, Jan. 18, 1966]

§ 18-8.704 Research and development contracts with nonprofit institutions (including educational institutions).

« PreviousContinue »