Chapter 2 UMTRA Project Has Grown in Size and Cost Since its inception in 1979, the UMTRA project has grown in both size and cost. The surface cleanup at the Title I sites is almost complete, but it took DOE nearly 8 years longer than expected and cost 37 percent more than the agency anticipated. The schedule changes and cost increases resulted from several factors, including unexpected quantities and locations of tailings, changes in federal regulatory requirements, and state and local concerns. As for the cleanup of the groundwater at the Title I sites, efforts have only recently begun. DOE initiated groundwater cleanup at the Title I sites in 1991 and currently estimates completion in about 2014, at a cost of at least $147 million.' Surface Cleanup Is DOE is currently seeking reauthorization of the surface cleanup program through fiscal year 1998, or 8 years past the act's original deadline. When it was enacted in 1978, the Uranium Mill Tailings Radiation Control Act directed DOE to complete the cleanup of the Title I sites by March 1990 (7 years after EPA's standards became effective). The deadline for the surface cleanup was later extended through fiscal year 1994, and then still later, through 1996.2 According to DOE, these extensions were necessary because of growth in the program's size and complexity. The Department currently expects that its surface cleanup will be completed by the beginning of 1997. DOE is working with NRC to expedite the licensing process so that all of the work is completed by the end of 1998. As of October 1995, the surface cleanup was complete at 15 of the 24 Title I sites, was under way at 7 additional sites, and was being planned at another 2 sites. Of the 15 sites where DOE has completed cleanup, 3 have been licensed by NRC as meeting EPA's standards. Ten of the other 12 sites are working on obtaining an NRC license (e.g., preparing paperwork for submission to NRC or undergoing NRC's review or inspection). Additionally, DOE has completed the surface cleanup at about 97 percent of the 5,276 nearby properties--which DOE terms vicinity properties—included in the program as of October 1995. 'These amounts, as well as all others in this chapter, have been converted to present-value 1995 dollars Although DOE, through its 1992 planning process, requested that the program be authorized through fiscal year 1998, the Energy Policy Act of 1992 provided authorization only through 1996. 'According to DOE officials, unlike the other sites, the sites at Monument Valley, Arizona, and Riverton, Wyoming, will not be licensed because the tailings were relocated to either a Title I or a Title Il site. Chapter 2 UMTRA Project Has Grown in Size and Cost In January 1995, DOE estimated that the total cost of the surface cleanup at the Title I sites will be about $2.3 billion, or $621 million (37 percent) more than it estimated in 1982. Through fiscal year 1994, expenditures for the surface cleanup already totaled about $2 billion, and DOE expects to spend another $300 million in completing this cleanup. Of the total projected cost of $2.3 billion, DOE expects to spend about 22 percent cleaning up the vicinity properties and the rest on cleaning up the 24 Title I sites. Through fiscal year 1995, the states will have contributed $99.9 million, and they are expected to spend another $29.6 million through the completion of the program as their share of the cleanup costs. Table 2.1 summarizes the status and cost of the surface cleanup at the 'In DOE's accounting system, this amount is reported as $1.47 billion in what DOE terms "escalated" dollars While DOE's budget system accounts for the two largest cost components of the cleanup at vicinity properties, it cannot fully itemize all these costs. As a result, according to DOE, the 22 percent of the total project cost that DOE expects to spend for cleaning up these properties is understated to a small extent. 27-350 97-4 *All dollars are adjusted to present-value 1995 dollars "Processing site only *Includes 115 vicinity properties that were cleaned up under Grand Junction's remedial action program *Anticipated completion date "Includes contaminated materials from the vicinity property in the Burrell, Pennsylvania, area 'The collection of costs at the Belfield and Bowman sites was not consistent during fiscal years 1980-94, sometimes the costs for both sites were included in the totals for one site, and sometimes the costs were split. However, the combined costs are correct *The UMTRA project is responsible for cleaning up the vicinity properties only-the former uranium mill site in Edgemont is owned and was cleaned up by the Tennessee Valley Authority in the late 1980s. As the table shows, among all of DOE'S cleanup sites, the Grand Junction, Colorado, location stands out in several respects. Its projected cleanup costs are by far the highest, as would be expected since it had the second greatest volume of contaminated material and the greatest number of vicinity properties that needed cleanup. The table also shows that the cost of cleaning up the high-priority In general, at those locations where the tailings were taken off-site for disposal, the costs were greater than they were at the sites where the Chapter 2 UMTRA Project Has Grown in Size and Cost Several Factors Compliance With EPA's tailings were kept on-site. Averaged over all locations, the estimated cost of off-site disposal is about $130 million per location, compared with about $55.6 million per location for on-site disposal. With work completed at 15 of the 24 Title I sites, the bulk of the expenditures for surface cleanup have already been made, as shown in table 2.1. The estimated remaining costs make up only 13 percent of the projected total cost. For the most part, DOE has completed the surface cleanup at those sites that posed the greatest potential health risk to the public (e.g., sites located near major population centers). At most of the other sites, DOE's cleanup efforts are well under way. 6 AS DOE's surface cleanup at the Title I sites grew in size and complexity, its One of the major factors that DOE identified as driving up the cost of its surface cleanups was EPA's establishment of groundwater standards, which were proposed in 1987 and finalized in January 1995. EPA developed these standards specifically for the UMTRA project.' The standards addressed the likely types and levels of contamination associated with all "The 1982 estimate assumed that the cleanups would be completed in 7 years and that only one pile of |